Resolved
That the Cabinet note the Council’s performance for Quarter 3 against this suite of performance measures and projects, and the actions taken to address performance issues.
Cabinet noted this item on Tuesday 17 March 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
That the Cabinet note the Council’s performance for Quarter 3 against this suite of performance measures and projects, and the actions taken to address performance issues.
1.1To provide a summary by exception of performance for the third quarter of 2014/15 (October - December 2014).
2.1Performance is monitored using a suite of performance measures which includes corporate, local and service plan measures, combining traditional quantitative indicators with more qualitative measures where appropriate. A summary of performance is provided in this report with more detailed information shown in Appendix 1.
2.2Delivery of the Councils corporate aims and priorities is achieved through a number of workstreams and key improvement projects. Progress is monitored through service planning and project highlight reports with brief updates included in quarterly performance reports by exception. A full list of current corporate projects and their status is provided in Appendix 2.
2.3Following a review by Members, the status assessments (RAG rating) for projects has been refined. The overall RAG status of projects is set out in the report but a more detailed RAG matrix is shown in Appendix 2.
2.4The above Worcester City performance information is set out under the relevant Portfolio headings: • Cleaner and greener city • Safer and stronger communities • Economic prosperity • Customer service and communications • Value for money
2.4Performance is reported by exception and will include details of both under- performance and examples of good performance and achievements. Full details including trend information and status against targets, (using RAG – Red, Amber or Green) are provided as appendices.
3. Performance Summary
3.1Overall 62% of performance measures available in Quarter 3 have met or exceeded the target. This is a decrease from the same period in 2013/14 (87%). It should be noted that the basket of measures is different.
3.2Corporate Projects and activities: This report includes progress updates for Corporate Projects from the Corporate Project Register which support the corporate priorities. 11 of the 27 corporate projects and activities are on target (five have yet to fully start). 3.3 Cleaner and Greener City
3.3.1 Summary:
Status Projects Performance Measures 1 0 <> 2 0 4 8 n/a 1 5
3.3.2 Positive Performance
• There has been improvement compared to Q3 2013/14 last year for all four measures collected through the Clean Streets Survey which determine the percentage of areas surveyed which are assessed to be of an acceptable level for detritus, litter, grass cutting and hedge cutting.
All four measures have met the quarterly targets and performance is attributed to improved processes and monitoring to proactively target problem areas. New machines are also helping to reduce the time taken to complete the works.
3.3.3 Exceptions:
Projects
• Crematorium Programme Start date: April 2014 Completion date: April 2017 Overall Programme Status: Amber
The Crematorium Programme includes the below projects:
Lean Working and Customer Service Improvements Start date: April 2014 Completion date: Mar 2015 Status: Amber
Recruitment to vacancies is in progress. Minor works to establish supervisory office/workstations within the main building completed. Financial planning (income stream projections) paper, methodology and model is being progressed for completion in February 2015.
Project assessed as Amber to reflect the wider and deeper scope of work required than initially identified within the time frame.
Refurbishment of main buildings Start date: April 2014 Completion date: Sept 2015 Status: Amber Scope of works agreed and work to progress detailed specification and finish options is in progress. Amber status is reflective of the scope of work to be completed within the time frame and potential budget implications.
Burial Spaces Start date: TBC Completion date: TBC Status: Red
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
2014-15 Q3 Performance Report APP 1 measuresAppendix | 8 pages | Download |
PDF |
2014-15 Q3 Performance Report APP 2 ProjectsAppendix | 1 pages | Download |
PDF |
2014-15 Q3 Performance Report PMBS v0 4Report | 11 pages | DownloadRead as text |
PDF |
Quarter 3, 2014/15 Performance ReportReport | 2 pages | Download |
Follow Cabinet at Worcester and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 21 Mar 2017 | MinutesThat the minutes of the meeting held on 14 th February 2017 be approved as a correct record and signed by the Chairman. | Approved | Open |
| 21 Mar 2017 | The Shambles Public Realm Improvement - Key DecisionThat the Cabinet agree to approve expenditure of £400,000 from the 2015-16 New Homes Bonus Allocation for public real... | Agreed | Open |
| 21 Mar 2017 | Worcester City Masterplan UpdateThat the Cabinet agree to: 1. approve the allocation £75k from the “City Plan Fund” towards the production of an upda... | Agreed | Open |
| 21 Mar 2017 | Perdiswell Golf CourseThat the Cabinet agree to: 1. endorse the proposals in this report, in particular the maintenance of ‘pay and play’ p... | Agreed | Open |
| 21 Mar 2017 | Refurbishment of the Cinderella Sports Ground - Key DecisionThat the Cabinet agree to: 1. approve the project to refurbish the Cinderella Sports Ground as a Community sports fac... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.