That the Committee (a) notes the Worcester City Council Housing Land Monitor 2014, including the assessment of the 5 year supply of housing land; and (b) endorse the approach that the Local Planning Authority continues to approve sustainable housing development in Worcester in accordance with the adopted development plans, the emerging South Worcestershire Development Plan development strategy, and the National Planning Policy Framework. This approach accords with the aims of: 1) boosting housing supply now; and securing a robust five year housing supply position in the future when a ‘policy-on’ housing requirement target can be used so that when adopted the SWDP will be considered an up to date plan.
Word for word from the decision Worcester published for this meeting.Source: committee.worcester.gov.uk
1.1To inform Planning Committee of the results of the Housing Land Monitor 2014 and the updated housing land supply position with regard to maintaining a 5 year supply of housing land.
1.2The report recommends that Committee endorse the approach that the Local Planning Authority continues to approve sustainable housing development in Worcester in accordance with the adopted development plans, the emerging South Worcestershire Development Plan (SWDP) development strategy, and the National Planning Policy Framework. This approach accords with the aims of boosting housing supply now, and securing a robust 5 year housing supply position in the future when a ‘policy-on’ housing requirement target can be used so that when adopted the SWDP will be considered an up to date plan.
Background
2.1The City Council publishes annually a Housing Land Monitor. The 2014 Housing Land Monitor (see Appendix 1) contains analysis of housing development in 2013/14 and provides the annual update on Worcester City’s 5 year housing land supply at 31st March 2014. This is the principal information source about the supply of available and deliverable housing land within Worcester City, which provides evidence for development management purposes. Appendix 2 to this report to Committee explains the method and the justification for this latest assessment of the 5 year housing land supply.
3. 2014 Housing Land Monitor – key results and analysis
3.1The HLM 2014 report shows evidence of improvements in housing development in the City compared to last year regarding: completions, the pipeline of commitments not yet started, and delivery of affordable dwellings and completions on brownfield land.
3.2Completions In the twelve months ending on the 31st March 2014 a total of 280 (net) dwellings were completed in Worcester. This matches the annualised delivery rate for the City in the emerging South Worcestershire Development Plan (SWDP). It is a significant increase over the 142 dwellings completed in the previous year. Total completions between 2006 and 2014 amounted to 2,503 dwellings. 3.3 Commitments -Compared to 2012/13, the pipeline supply of approved dwellings has increased with 1,422 dwellings on 100 sites either under construction or with a planning approval. This is the second successive increase in the number of commitments with over 450 more homes in the process of being built than in April 2012. It includes 100 social rented, extra care apartments and bungalows (now under construction) for Sanctuary Housing at the Health and Wellbeing campus at University Park. The number of dwellings under construction or on sites where construction had begun fell from 419 in 2012/13 to 338 dwellings in 2013/14, due in part to sites with completions delivered in 2013/14.
3.4Lapsed Planning permission for 32 units on five sites lapsed during 2013/14. This represents a lapse rate of 2.5% on the commitments total in April 2013. This is relatively low, compared to an historic 5% lapse rate, which the SWDP Inspector endorsed for housing supply calculations for plan-making purposes.
3.5Brownfield /greenfield The proportion of housing completions on brownfield sites rose to 80% compared to 74% and 75% in 2012/13 and 2013/14, and the proportion on greenfield sites declined this year to 19.5%. The City continues a strong, long term record of re-using land and buildings.
3.6Affordable housing Of the 280 net completions, 100 were affordable housing units, a significant rise above the 14 new affordable homes in delivered in 2012/13. This exceeds the average of 80 units per year over the last eight years.
4. 5 Year housing Land Supply
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Minutes of Previous Planning CommitteeThat the minutes of the meeting held on 23 rd July 2026 be approved as a correct record and signed by the Chair, subj...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.