CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Worcester City Council
Cabinet, Tuesday 16 June 2015 at 7.00pm

Quarter 4, 2014/15 Performance Report

Noted Executive 4 papers

Cabinet noted this item on Tuesday 16 June 2015. Below is the council's own wording, with the papers it was decided on.

Item5

Resolved

That the Cabinet note the Council’s Quarter 4 and annual performance for 2014/15 against this suite of performance measures and projects.
Word for word from the decision Worcester published for this meeting. Source: committee.worcester.gov.uk

Follow this further

Built from Worcester's papers

What the report saysPro

Report to Cabinet, 12 pages

Purpose of report

1.1To provide a summary by exception of performance for the final quarter (January - March 2015) and the annual performance for 2014/15.

Background

2.1Performance is monitored using a suite of performance measures which includes corporate, local and service plan measures, combining traditional quantitative indicators with more qualitative measures where appropriate. A summary of performance is provided in this report with more detailed information shown in Appendix 1.

2.2Delivery of the Councils corporate aims and priorities is achieved through a number of workstreams and key improvement projects. Progress is monitored through service planning and project highlight reports with brief updates included in quarterly performance reports by exception. A full list of current corporate projects and their status is provided in Appendix 2.

2.3Following a review by Members, the status assessments (RAG rating) for projects has been refined. The overall RAG status of projects is set out in the report but a more detailed RAG matrix is shown in Appendix 2.

2.4The above Worcester City performance information is set out under the relevant Portfolio headings: • Cleaner and greener city • Safer and stronger communities • Economic prosperity • Customer service and communications • Value for money

2.4Performance is reported by exception and will include details of both under- performance and examples of good performance and achievements. Full details including trend information and status against targets, (using RAG – Red, Amber or Green) are provided as appendices.

3. Performance Summary

3.1For quarter 4, 49% of performance measures have met or exceeded the target. However, the annual outturn shows that 63% of the measures met or exceeded targets. This is an improvement from 2013/14 (57%) although it should be noted that the basket of measures is different. 3.2 Corporate Projects and activities: This report includes progress updates for Corporate Projects from the Corporate Project Register which support the corporate priorities. Eight of the 26 corporate projects and activities are on target. (Nine have yet to fully start or are on hold and the remaining are either amber or red).

3.3Cleaner and Greener City

3.3.1 Summary:

Status Projects Performance Measures Q4 2014/15  0 1 1 <> 5 2 1  3 5 8 n/a 1 5 3

3.3.3 Exceptions:

Projects

• Crematorium Programme Start date: April 2014 Completion date: April 2017 Overall Programme Status: Amber

The Crematorium Programme includes the below projects:

Refurbishment of main buildings Start date: April 2014 Completion date: Sept 2015 Status: Amber

In support of preparing the detailed specification for tender in June a planning application is in progress along with a display of the proposed décor of the chapel for public consultation in early April. Options for continuing a service level during the planned 3 week chapel closure in August are in development for consideration by the Board.

Overall the project is assessed as Amber as both the budget and time elements of the RAG criteria are Amber. The scheme costs are estimated pending tendering. In preparing the detailed specification, previously un-costed and budgeted elements have been identified. These elements may be covered by existing contingencies or required additional budget; the position is not clarified at this point.

The time RAG reflects the scope of work to be completed within a challenging time frame including the need for the specification to be finalised so that tenders can go out in June. There is also an associated minor risk in securing external stakeholder support for the temporary chapel proposed to facilitate business continuity during the 3 week closure.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
2014-15 Q4 Performance Report APP 1 measuresAppendix 9 pages Download
PDF
2014-15 Q4 Performance Report APP 2 ProjectsAppendix 1 pages Download
PDF
2014-15 Q4 Performance Report PMBS FinalReport 12 pages DownloadRead as text
PDF
Quarter 4, 2014/15 Performance ReportReport 2 pages Download

At this meeting

Whole meeting

On this subject at Worcester

Search all
  1. Quarter 4, 2014/15 Performance ReportThis decision
  2. Quarter 4 and Annual Key Performance Indicator Report for 2025/26Agreed
  3. Quarter 4 and Annual Performance Report for 2025/26Noted
  4. Quarter 4 and Annual Performance Report for 2025/26Agreed
  5. Quarters 2 and 3 Performance Report 2025-26Decided
  6. Quarter 3 Performance Report For 2025/26Agreed

More from Worcester Cabinet

All decisions
MeetingDecisionOutcome
21 Mar 2017 MinutesThat the minutes of the meeting held on 14 th February 2017 be approved as a correct record and signed by the Chairman. Approved Open
21 Mar 2017 The Shambles Public Realm Improvement - Key DecisionThat the Cabinet agree to approve expenditure of £400,000 from the 2015-16 New Homes Bonus Allocation for public real... Agreed Open
21 Mar 2017 Worcester City Masterplan UpdateThat the Cabinet agree to: 1. approve the allocation £75k from the “City Plan Fund” towards the production of an upda... Agreed Open
21 Mar 2017 Perdiswell Golf CourseThat the Cabinet agree to: 1. endorse the proposals in this report, in particular the maintenance of ‘pay and play’ p... Agreed Open
21 Mar 2017 Refurbishment of the Cinderella Sports Ground - Key DecisionThat the Cabinet agree to: 1. approve the project to refurbish the Cinderella Sports Ground as a Community sports fac... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies