Worcestershire Hub Shared Service - Quarter 1 2015/16

Decided Committee 2 papers

South Worcestershire Shared Services Partnership Joint Committee decided this item on Friday 18 September 2015. Below is the council's own wording, with the papers it was decided on.

Item33

Resolved

That the Joint Committee note: 1. the progress made during Quarter 1; 2. the performance and the transition and transformation plan being delivered under the new managed service provider, Civica UK Ltd.; and 3. the financial outturn position for 2014/15.
Word for word from the decision Worcester published for this meeting. Source: committee.worcester.gov.uk

Follow this further

Built from Worcester's papers

What the report saysPro

Report to South Worcestershire Shared Services Partnership Joint Committee, 10 pages

Q1 Performance Report Worcestershire Hub Shared Service Partnership Customer Services August 2015

Monthly Performance Report – Worcestershire Hub Shared Service Partnership – Customer Services Page number 1 Executive Summary Performance Highlights The Worcestershire Hub Shared Service was commissioned to Civica on 1st May 2015. The KPI's also changed on 1st May in line with the contract and therefore for the purposes of continuity this report reflects the new KPI's. 82% of calls answered in 90 seconds. The move of the contact centre to its new home in Pershore was successfully undertaken without interruption to the operation. 8m 34s waiting time in F2F against a target of 15 minutes. 72% of administration tasks completed within agreed targets. Quality benchmarking has commenced with the targets to be agreed following the benchmarking period. Commissioning of the service was undertaken without impact on customer satisfaction.

Performance Lowlights None to report.

Summary of any critical service failures: None to report.

Q1 Performance At a Glance Actual for the KPI DESCRIPTION TARGET Previous Quarter quarter

% of calls answered within 90 70% KPI01 70% 82% seconds (based on old SLA)

Average wait time for face to face KPI02 < 15 minutes 8m 34s 12m 47s enquiries

% of administration tasks KPI03 65% 72% 89% completed within service level % of enquiries meeting quality KPI04 TBA TBA% TBA% criteria

KPI 01 – Telephony Customer Contact Service Measure To answer incoming telephone calls within the agreed service level.

KPI Target

Monthly Performance Report – Worcestershire Hub Shared Service Partnership – Customer Services Page number 2 70% of all calls answered to be within 90 seconds. Calls answered are those that enter the queue following the completion of the IVR process and the 90 seconds begins on entering the queue (i.e. st after the IVR process). It should be noted that this target was changed on the 1 May 2015 to coincide with the contract start.

Purpose To ensure timely access to service by phone to a standard that is consistent with channel shift plans.

Quarterly result:

Performance table: Average No. Of Calls No. Of Calls No. of Calls % of Calls Talk Time - Month Offered Offered No. of Calls No. of Calls % Calls Answered Answered hh:mm:ss SLA Target (Including (excluding Abandoned Answered Answered Switchboard) Switchboard) within SLA within SLA (excluding Switchboard) Apr-15 24222 19522 2657 21565 89% 17447 80% 00:03:56 70% May-15 21102 17169 1484 19618 93% 16539 84% 00:03:29 70% Jun-15 22755 17771 1549 20805 91% 17220 83% 00:03:20 70%

Commentary: The start of the quarter was challenging with the peak for Primary and Middle School Notifications which increased demand. Normal flexibility measures were utilised to support achievement of the service level with all non-call handling team members trained to assist with the peak and all off call activity restricted including annual leave.

During May the performance was good despite it being the first month of the new Civica contract. This is a credit to the staff who, despite the changeover and the uncertainty that change of this nature brings, demonstrated flexibility, and resilience allowing Civica to complete a number of changeover activities during the month whilst achieving the KPI. There was also no discernable impact on the customer satisfaction scores reported indicating that the commissioning of the service has not adversely impacted the quality of service or customer experience. Quality monitoring however has supported customer feedback in the contact centre whereby the registration service continued to create repeat contacts within the Hub as a result of the delay in the service returning customer telephone calls. Feedback was provided to the service and towards the end of the quarter, which appears to have been actioned and the service improving.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Q1 report for JC Sept 15 v 2 0Report 10 pages DownloadRead as text
PDF
Worcestershire Hub Shared Service: Quarter 1 2015/16Report 6 pages Download

At this meeting

Whole meeting

On this subject at Worcester

Search all
  1. Worcestershire Hub Shared Service - Quarter 1 2015/16This decision
  2. Worcestershire Growth Hub HostingAgreed
  3. Worcestershire Careers HubDecided
  4. Worcestershire Hub Shared Service – Quarter 2 2016/17 and 2017/18 BudgetNoted
  5. Worcestershire Hub Shared Service – Quarter 1 2016/17Noted
  6. Worcestershire Hub Annual Performance Report 2015/16Noted

More from Worcester South Worcestershire Shared Services Partnership Joint Committee

All decisions
MeetingDecisionOutcome
25 Nov 2016 MinutesThat the minutes of the meeting held on 16 th September 2016 be approved as a correct record and signed by the Chairman. Approved Open
25 Nov 2016 Revenues & Benefits Shared Service Performance Report April to October 2016That the Joint Committee note the performance of the Revenue and Benefits Shared Services for the period April – Octo... Noted Open
25 Nov 2016 South Worcestershire Revenues and Benefits Shared Service - Revised Budget 2016-17 and Budget for 2017-2018That the Joint Committee: 1. note the financial performance (budget monitoring) of the Shared Service for the 7 month... Noted Open
25 Nov 2016 Worcestershire Hub Shared Service – Quarter 2 2016/17 and 2017/18 BudgetThat the Joint Committee: 1. note the operational performance and levels of customer satisfaction for the Worcestersh... Noted Open
25 Nov 2016 IT Shared Service Budget And Strategy ReportThat the Joint Committee: 1. note the Financial and Service Performance for 2016/17 to the end of October 2016; and 2... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies