That the Committee: 1. note the Worcester City Council Housing Land Monitor 2015, including the assessment of the 5 year supply of housing land; and 2. endorse the approach that the Local Planning Authority continues to approve sustainable housing development in Worcester in accordance with the adopted development plans, the emerging South Worcestershire Development Plan development strategy, and the National Planning Policy Framework. This approach accords with the aims of: 1) boosting housing supply now; and 2) securing a robust five year housing supply position in the future when a ‘policy-on’ housing requirement target can be used so that when adopted the SWDP will be considered an up to date plan.
Word for word from the decision Worcester published for this meeting.Source: committee.worcester.gov.uk
Appendix 1 - Explanation of 5 year land supply calculations 34
Appendix 2 - Housing Schedules 36
2 Tables
Table 1 Housing Completions April 1996 to March 2015 6
Number of dwellings (gross) completed on greenfield land since Table 2 9 2006
Table 3 Total number of gross completions by planning policy type 11
Table 4 Completed dwellings by type and dwelling size 2014/15 13
Table 5 Completed dwellings by type since 2006 13
Table 6 Residential completions by ward 2014/15 16
Table 7 Total Affordable Housing Completions since 2006 17
Table 8 Affordable Housing Completions during 2014-2015 18
Table 9 Sites with planning permission for housing at 31 March 2015 20
Table 10 Annual change in Worcester City Housing Supply 2014/15 21
Land with planning permission for residential development at 31 Table 11 22 March 2015 (including under construction)
Table 12 Housing Targets for Wider Worcester and Worcester City 27
Table 13 2006-2015 completions compared to various policy targets 28
Table 14 5 year housing land target in Worcester 2015-2020 30
Table 15 Residential commitments in Worcester at 1st April 2015 31
Table 16 5 year land supply in Worcester at 1st April 2015 32
Figures Figure 1 Net completions since 2006 7
Proportion of completions on brownfield and greenfield land Figure 2 10 since 2006 Proportion of completions from small sites (0 to 9 dwellings) and Figure 3 12 large sites (10 or more dwellings) since 2006
Figure 4 Density of completed dwellings by band in 2014-2015 14
Figure 5 Proportion of sites built within each density band since 2006 15
Number of affordable and open market units completed since Figure 6 18 2006
3 1. INTRODUCTION 1.1 The National Planning Policy Framework (March 2012) contains the core planning principle that local planning authorities should identify and meet the need for housing in their area. It places great emphasis on the requirement for local planning authorities to boost significantly the supply of housing. To assist with this, the local planning authorities should: “identify and update annually a supply of specific deliverable sites sufficient to provide five years worth of housing against their housing requirements”1.
1.2This Housing Land Monitor identifies the residential land supply in the City as at 1 April 2015. The land supply is then compared against, the targets set by the interim findings of the inspector appointed to conduct the Examination in Public of the South Worcestershire Development Plan (SWDP).
1.3The report includes details of housing completions, demolitions and commitments which have occurred in the year from 1st April 2014 to 31st March 2015, alongside other information on housing issues such as affordable housing delivery. It also details Worcester City Council’s 5 year housing land supply position. The information in this report provides the basis for monitoring existing City of Worcester Local Plan and Balanced Housing Market Development Plan Document policies, whilst also informing policy formulation and site allocations for the emerging SWDP.
2. WORCESTER CITY HOUSING COMPLETIONS 2014 to 2015
2.1This section of the report examines the number and make up of residential dwellings completed within Worcester City in 2014/15. The section is split into two parts, firstly total annual new build completions and secondly demolitions, conversions and change of use. The combined result of these two sections provides the report with a net completions figure. The net figure, along with previous years, is used to monitor against housing targets.
1 NPPF (2012) para 47
4 Total Annual New Build Completions in 2014/15
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Minutes of Previous Planning CommitteeThat the minutes of the meeting held on 23 rd July 2026 be approved as a correct record and signed by the Chair, subj...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.