Resolved
That the minutes of the meeting held on 22 nd March 2016 be approved as a correct record and signed by the Chairman.
Cabinet approved this item on Tuesday 14 June 2016. Below is the council's own wording, with the papers it was decided on.
Resolved
That the minutes of the meeting held on 22 nd March 2016 be approved as a correct record and signed by the Chairman.
CABINET
22nd March 2016
Present: Councillor Bayliss in the Chair
Councillors Amos, [name removed], Johnson, Mitchell and Roberts Also in Attendance: Councillors Berry and J. Squires
109 Declarations of Interest
The following declaration of interest was made:
Councillor Mrs L. Hodgson – Quarter 3 Performance Report for 2015/16 (Minute 115) - As a Governor of Heart of Worcestershire College
110 Public Participation
None.
111 Minutes
RESOLVED: That the minutes of the meeting held on 9th February 2016 be approved as a correct record and signed by the Chairman.
112 Major Projects - Progress Report
The Cabinet received an update on progress made against some key Corporate Plan projects as well as some other major projects approved by Cabinet during 2015/16. The Leader presented the report and highlighted in particular the new Swimming Pool at Perdiswell, the Crematorium Refurbishment and the redevelopment of Cathedral Square.
Other Cabinet Members welcomed the report and it was highlighted that the Swimming Pool project was on time and to budget at this stage.
Other Members present were also given an opportunity to comment and in response to questions it was explained that the highways work at Cathedral Square was consistent with the approved scheme.
RESOLVED: That the Cabinet note the progress that has been made on major projects during the last 12 months.
113 Perdiswell Culvert Repairs - Award Of Contract - Key Decision
The Cabinet considered proposals for repairs to the Perdiswell Culvert. The Portfolio Holder for a Cleaner, Greener and Safer City presented the report and explained that the Cabinet had given approval for repairs in December 2014. As the work progressed it became apparent that, due to the deterioration to the culvert, alternative repair work was required in the form of a new culvert laid parallel to and bypassing the existing. 22nd March 2016 2
The nature of the project meant that the final specification was dependent on preliminary survey work and prevailing site conditions. This meant that the final specification, and therefore costs, would be agreed shortly before the commencement of work on site in April 2016.
It had been established that the revised scheme would require additional funding of up to £295k. It was anticipated that external funding of £95k would be confirmed by the Environment Agency during April 2016. Therefore the Council would be required to contribute up to an additional £200k. There was potential for additional external funding to be secured during early 2016/17, reducing the Council’s contribution, although there was a significant risk that this would not be available.
Other Cabinet Members commented and expressed support for proceeding with the works at the earliest opportunity in view of the implications of a collapse of the culvert.
Other Members present also supported the proposals. In response to questions, it was clarified that should a collapse occur then the risk of flooding would occur upstream of the culvert.
RESOLVED: That the Cabinet:
1. delegate authority to finalise the specification and award a contract for repairs to the Perdiswell Culvert to the Service Manager, Cleaner and Greener City in consultation with the Corporate Director, Resources; and
2. allocate additional funding of up to £295k to provide a capital project budget of £800k for these works. The additional funding to be met from internal earmarked reserves and external funding.
114 Quarter 3 Financial Monitoring Report - 2015/16
The Cabinet considered the Quarter 3 Financial Monitoring report covering the period to 31st December 2015. The Portfolio Holder for Resources presented the report and highlighted the main points. Other Cabinet Members and other Members present also commented.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
MinutesMinutes | 6 pages | DownloadRead as text |
Follow Cabinet at Worcester and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 21 Mar 2017 | MinutesThat the minutes of the meeting held on 14 th February 2017 be approved as a correct record and signed by the Chairman. | Approved | Open |
| 21 Mar 2017 | The Shambles Public Realm Improvement - Key DecisionThat the Cabinet agree to approve expenditure of £400,000 from the 2015-16 New Homes Bonus Allocation for public real... | Agreed | Open |
| 21 Mar 2017 | Worcester City Masterplan UpdateThat the Cabinet agree to: 1. approve the allocation £75k from the “City Plan Fund” towards the production of an upda... | Agreed | Open |
| 21 Mar 2017 | Perdiswell Golf CourseThat the Cabinet agree to: 1. endorse the proposals in this report, in particular the maintenance of ‘pay and play’ p... | Agreed | Open |
| 21 Mar 2017 | Refurbishment of the Cinderella Sports Ground - Key DecisionThat the Cabinet agree to: 1. approve the project to refurbish the Cinderella Sports Ground as a Community sports fac... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.