CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Worcester City Council
Cabinet, Tuesday 25 October 2016 at 7.00pm

Play Area Investment

Decided Executive 1 paper

Cabinet decided this item on Tuesday 25 October 2016. Below is the council's own wording, with the papers it was decided on.

Item53

Resolved

That Cabinet allocate a one off budget of £100k for investment in play equipment at Oldbury Road, Medway Road, and King George V Park.
Word for word from the decision Worcester published for this meeting. Source: committee.worcester.gov.uk

Follow this further

Built from Worcester's papers

What the report saysPro

Report to Cabinet, 4 pages

Recommendation

1.1That Cabinet allocate a one off budget of £100k for investment in play equipment at Oldbury Road, Medway Road, and King George V Park.

Background

2.1For 2016/17 the Council has allocated a one off sum of a further £100k, funded by New Homes Bonus grant. This was detailed in the Budget and Council Tax report to Council in February 2016 that stated “Play areas have been a priority investment area for Cabinet for the past few years and 2016/17 is no different. Additional funds will be set aside to ensure quality play area provision.”

2.2Maintenance of the Council’s play areas is primarily funded by existing revenue budgets of £175k p.a. which cover staff, minor components and sundry items, and replacement of end of life items including play equipment, safety surfacing and fencing. The annual budget for replacement of end of life items is £100k p.a.

2.3The Council maintains 44 equipped play areas distributed across the City, with over 300 individual items of play equipment such as swings, slides, roundabouts, climbing frames and multiplay units.

2.4Play areas range in size from destination sites in the City’s premier parks down to small local sites containing only a few items of equipment.

2.5A small number of additional publicly accessible play areas are owned and maintained by a social housing provider.

2.6Condition and safety inspections of play equipment are carried out regularly to identify any issues that require remedial action. Minor items such as bearings, swing seats and other sundries are dealt with as they arise. Equipment requiring more substantial repair, refurbishment or replacement is identified by officers for inclusion in an annual programme funded from the annual budget. Occasionally equipment identified as end of life requires immediate removal.

2.7Where additional spend is available from s106 funding, this is used to supplement the base budget to replace equipment where appropriate. For example, the dilapidated Diglis Fields play area was replaced in 2015 at a cost of £80k funded by s106 contributions. 2.8 Opportunities may also arise through the planning process for additional play areas and equipment provided either as part of a development or “off site” through s106 agreements. For example a new play area was installed at the Green Centre in Dines Green at a cost of £50k in 2014, funded through s106 agreements.

2011 Review

2.9A detailed review of play area provision and maintenance was carried out in late 2011 by an all party Member working group. The working party reported their findings to Cabinet in December 2011.

2.10In summary, the group highlighted that the budgetary provision at that time was insufficient to maintain the existing stock of play equipment across 52 play areas and a range of options were presented that included reduction in provision and additional funding.

2.11In receiving the report Cabinet thanked the working party for their work in investigating the issue and noted that the proposed budget for 2012/13 included an increase for play maintenance. This brought the budget up to current levels.

Progress

2.12Since 2011, an improvement in the quality of provision has been achieved and the current provision for play is well maintained and provides a safe environment.

2.13However, equipment continues to deteriorate with age, and from time to time individual items or entire play areas are identified as reaching end of life and requiring replacement or removal following routine inspection. Vandalism is not generally a major problem in Worcester but occasionally equipment has been subject to significant damage.

2.14A detailed review of stock condition, predicted longevity and implications for refurbishment and replacement is due to be undertaken in early 2017.

2.15The annual budget for 2016/17 is fully committed to the replacement of end of life equipment and of one particular item that was subject to arson.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Play Area InvestmentReport 4 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Worcester

Search all
  1. Play Area InvestmentThis decision
  2. Strategic Play Area Development PlanAgreed
  3. Referral Report from Place and Economic Development Committee - Proposal to Develop a Worcester City Strategic Play Area Development PlanAgreed
  4. Strategic Play Area Development PlanNoted
  5. Play Area Investment ProgrammeNoted
  6. Play Area Condition UpdateDecided

More from Worcester Cabinet

All decisions
MeetingDecisionOutcome
21 Mar 2017 MinutesThat the minutes of the meeting held on 14 th February 2017 be approved as a correct record and signed by the Chairman. Approved Open
21 Mar 2017 The Shambles Public Realm Improvement - Key DecisionThat the Cabinet agree to approve expenditure of £400,000 from the 2015-16 New Homes Bonus Allocation for public real... Agreed Open
21 Mar 2017 Worcester City Masterplan UpdateThat the Cabinet agree to: 1. approve the allocation £75k from the “City Plan Fund” towards the production of an upda... Agreed Open
21 Mar 2017 Perdiswell Golf CourseThat the Cabinet agree to: 1. endorse the proposals in this report, in particular the maintenance of ‘pay and play’ p... Agreed Open
21 Mar 2017 Refurbishment of the Cinderella Sports Ground - Key DecisionThat the Cabinet agree to: 1. approve the project to refurbish the Cinderella Sports Ground as a Community sports fac... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies