Quarter 2 Performance and Feedback Report for 2016/17
NotedFinance2 papers
Performance Management and Budget Scrutiny Committee noted this item on Monday 12 December 2016. Below is the council's own wording, with the papers it was decided on.
That the Committee: 1. note the Council’s Quarter 1 performance for 2016/17; and 2. agreed to make the following specific comments to Cabinet: • The Committee highlighted the change in crime reporting methodology, which has resulted in an increase in the number of incidents of crime. • The Committee suggested that more information on trends and benchmarking would be useful in future performance reports on key city information. • Any proposals to develop self-serve transactions should be subject to a satisfactory business case. The Committee highlighted that not all people use online services.
Word for word from the decision Worcester published for this meeting.Source: committee.worcester.gov.uk
Report to Performance Management and Budget Scrutiny Committee, 26 pages
APPENDIX 1 WORCESTER CITY COUNCIL PERFORMANCE AND FEEDBACK Quarter 2, 2016/17
CORPORATE PLAN – PROJECTS AND STRATEGIES
Appendix 1 includes Council-led and partnership projects and strategies that contribute to the delivery of the Corporate Plan.
Key: P – Project – defined and managed under the corporate project management methodology S – Strategy – a developing plan or strategy for the delivery of the a Corporate Plan goal
Theme 1 - Increasing Prosperity through successful businesses and great jobs
Project (P) Title Q1 Q2 Explanatory Note or RAG RAG Strategy (S) P Delivery of Technology Park G G Infrastructure works proceeding to plan. Speculative development still Worcester 6 on track. Easement agreements for utility access on city land to be put in place for quarter 3/4. S Adopt and deliver the South G G Developer contribution and Affordable Housing Supplementary Worcestershire Development Planning Documents and Community Infrastructure Levy progressing Plan (SWDP) according to Local Development Scheme timetable S Skills Strategy Roll Out G G Approved at Cabinet. Programmes to be developed in quarters 4. S Infrastructure delivery plan G G Community Infrastructure levy Charging Schedule submitted for (IDP) that supports business Examination. success and growth within SWDP S Economic Prosperity Strategy A G The Council’s City Plan was launched in September 2016. Its second theme addresses Prosperity and seeks a range of related strategies and action plans to support its aims. A Tourism Strategy will be produced in Winter 2016 and this will be followed by a City Transport and Master Plan refresh.
1 Theme 2 – Growing a vibrant city with sports, leisure and retail
Project (P) Title Q1 Q2 Explanatory Note or RAG RAG Strategy (S) P Swimming Pool & Leisure G G The pool will open in the first week of January 2017. Centre P Retention of Cinderella A A Project has been redesigned to suit mixed funding partners and design Ground requirements.
P Improve signage and way G G Installation of tourist information panels has been delayed due to finding staffing issues at the County Council. However the roll-out is anticipated to be completed in quarter 4. S Destination Management Plan G G The Tourism Strategy is due to be presented to Cabinet in December 2016 / February 2017.
Theme 3 – Making the most of our history and heritage
Project (P) Title Q1 Q2 Explanatory Note or RAG RAG Strategy (S)
P Refurbishment and A A The project is rated ‘Amber’ as key approvals (listed building consent) development of the are still to be obtained. Not withstanding this, the £430k project is on Commandery Museum target for delivery in May 2017. including the Battle of Worcester story P Museums Shared Service – G On The County Council have requested Worcester hosting of the shared change of hosting Hold Shire/City service be considered in 2017/18. arrangements
2 Theme 4 – Continuing to enhance our city centre and riverside
Project (P) Title Q1 Q2 Explanatory Note or RAG RAG Strategy (S)
P Cathedral Square G G Retail development is on target to completed quarter 1, 2017/18. improvements Public realm improvements on target to complete July 2017.
P Cornmarket Improvements A G Public art statues installed on the 1st September 2016. Parking bay re-alignment completed by 2nd October. P Angel Place Improvements A G Angel Place issues to be addressed by County Council at the same time as the works in Upper Broad Street – by the end of 2016/17. P Diglis Public Realm Project G/A G Project is now back on track following appointment of a new contractor. P Public realm improvement – Not G Public Realm Improvement Programme has started. Upper Broad Started refurbishment of further Street and Angel Place snagging to be completed 2016/17. areas of the City Centre - Assessment of Lower Broad Street, Shambles and Riverside projects including Broad Street, the to be reported to Cabinet in 2017/18. Shambles and Riverside public realm
3 Theme 5 – Ensuring our city is clean, green and safe
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Performance Management and Budget Scrutiny Committee at Worcester and we tell you when its next papers are published, before the meeting rather than after it.
Q3 Financial Monitoring Report 2016/17That the Committee note the financial monitoring details including budget variances, year end forecasts and performan...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.