Resolved

That the Cabinet: 1. approve an additional budget of £25k to replace and refurbish Street Name Plates; 2. allocate an additional one off budget of £80k for investment in the City’s CCTV infrastructure; and 3. ask Scrutiny Committee to consider potential interventions and make recommendations for measures and investment to further mitigate adverse effects of Gulls in the City.
Word for word from the decision Worcester published for this meeting. Source: committee.worcester.gov.uk

Follow this further

Built from Worcester's papers

What the report saysPro

Report to Cabinet, 9 pages

Recommendation

1.1That Cabinet approve an additional budget of £25k to replace and refurbish Street Name Plates;

1.2That Cabinet allocate an additional one off budget of £80k for investment in the City’s CCTV infrastructure; and

1.3That Cabinet ask Scrutiny Committee to consider potential interventions and make recommendations for measures and investment to further mitigate adverse effects of Gulls in the City.

Background

2.1This report covers proposals for additional investment in Street Name Plate Renewal and Refurbishment, investment in CCTV infrastructure, and work to mitigate the effect of gulls in the City.

2.2Officers have been working with Cabinet Members on all three areas to develop proposals and recommendations for Cabinet approval.

2.3The street name plates renewal programme is in the second of two years and this report covers the case for extension of funding into a third year.

2.4Officers have reviewed the CCTV infrastructure and have been finalising detailed requirements for procurement of updated cameras which will require additional funding.

2.5Discussions are also in progress with Worcester BID regarding the potential for coordinating additional measures to further mitigate the effect of gulls.

2.6All three items have also been areas of wider Member interest and, following a notice of motion, on 29th September 2016 the Council resolved that:

1) the following service improvements shall (subject to business case and options appraisal) be funded from Service Improvement Reserve:

a) An additional £15k to help tackle the gull problems across the City; b) An additional £25k to continue to replace the tired and damaged street name signs across the city; 1 c) An additional £80k to update and modernise the City’s CCTV cameras; and

2) the relevant Corporate Directors, in conjunction with the S151 officer, shall produce options and a business case for each for consideration by Cabinet at its meeting in December 2016.

2.7This resolution provides the potential for funding of these three work areas and this report outs forward proposals for each.

3. Proposals

Street Name Plates

3.1The City Council is responsible for the provision and maintenance of Street Name Plates (SNPs) which indicate the name of each of the City’s streets, and cul de sacs. These are usually mounted on low level poles or attached to walls and buildings at low or high level.

3.2Over time SNPs deteriorate due to weathering, accident damage and vandalism. These can therefore require replacement or, particularly in the case of cast iron “heritage” SNPs, refurbishment.

3.3For some years the Council’s working practice has been to ensure that there is at least one SNP at each end of each street and at least one SNP at the entrance to each cul-de-sac. There are currently approximately 2900 SNPs in the City.

3.4Responding to customer and Councillor requests in addition to officer monitoring, the Council has replaced or refurbished approximately 20-25 damaged or faded SNPs per annum prior to 2015/16. This was delivered at a cost of approximately of £1500 p.a. for materials with staff, vehicle and equipment resources provided for in base revenue budgets.

3.5A review of SNPs was undertaken in 2015 which identified that there were approximately 2% (28 number) of streets where the minimum standard of one SNP at each end of each street and one SNP at the entrance to each cul-de-sac was not being met. This equated to 48 SNPs for replacement.

3.6Additionally, the quality of some SNPs had deteriorated due to minor damage and weathering to a point where in some cases they could be judged as detracting from the street scene. The latter is a more subjective assessment, but it was estimated there were approximately 240 required.

3.7In 2015/16 and 2016/17 an additional budget of £20k per annum was allocated to expedite the SNP replacement programme. No additional allocation was made for future years at that time.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Use of Service Improvement ReserveReport 9 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Worcester

Search all
  1. Use of Service Improvement ReserveThis decision
  2. Museums Worcestershire Service PlanApproved
  3. Museums Worcestershire Strategic Plan 2025-2030 and Service Plan 2025-26Approved
  4. Museums Worcestershire Service Plan 2024-25Approved
  5. Museums Worcestershire Service PlanApproved
  6. Museums Worcestershire Service Plan 2022-23Approved

More from Worcester Cabinet

All decisions
MeetingDecisionOutcome
21 Mar 2017 MinutesThat the minutes of the meeting held on 14 th February 2017 be approved as a correct record and signed by the Chairman. Approved Open
21 Mar 2017 The Shambles Public Realm Improvement - Key DecisionThat the Cabinet agree to approve expenditure of £400,000 from the 2015-16 New Homes Bonus Allocation for public real... Agreed Open
21 Mar 2017 Worcester City Masterplan UpdateThat the Cabinet agree to: 1. approve the allocation £75k from the “City Plan Fund” towards the production of an upda... Agreed Open
21 Mar 2017 Perdiswell Golf CourseThat the Cabinet agree to: 1. endorse the proposals in this report, in particular the maintenance of ‘pay and play’ p... Agreed Open
21 Mar 2017 Refurbishment of the Cinderella Sports Ground - Key DecisionThat the Cabinet agree to: 1. approve the project to refurbish the Cinderella Sports Ground as a Community sports fac... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies