That the Committee make the following comments to Cabinet: · The Committee accept recommendations 1.1 and 1.2 of the Cabinet report. · The Committee recommend that the reference to housing in recommendation 1.3 be withdrawn. This recommendation should therefore read: “To ask officers to prepare an options appraisal for the development of the site and to report back their findings to a subsequent meeting of the Cabinet.”
Word for word from the decision Worcester published for this meeting.Source: committee.worcester.gov.uk
1.1To approve the demolition of Sansome Walk Swimming Pool and Leisure Centre;
1.2To delegate to the S.151 Officer in consultation with the Cabinet Member for Performance and Resources authority to approve financing for the demolition works, to include site security, ground condition surveys and applications for all relevant planning and environmental consents; and
1.3To ask officers to prepare an options appraisal for the development of the site, particularly housing, for which the site is allocated in the South Worcestershire Development Plan (SWDP), and to report back their findings to a subsequent meeting of the Cabinet.
Background
2.1The Swimming Pool and Leisure Centre site at Sansome Walk (see appendix 1) is owned by Worcester City Council and comprises approx. 2.1 acres (0.85 hcts). The centre comprises 3 swimming pools, a running and weights gym, 3 exercise areas and some 85 car parking spaces. The site is currently the subject of a lease to the leisure centre operator, Freedom Leisure.
2.2The site is and will become surplus to the Council's requirements following construction of a replacement swimming pool at Perdiswell. The new swimming pool is due to open in early 2017. The lease to Freedom Leisure will be surrendered following the opening of the new swimming pool at Perdiswell.
2.3It is necessary for the Council to consider the long-term use of Sansome Walk, however, the Council also needs to ensure that the site is safe and secure in the short to medium term.
3. Demolition of building on health and safety grounds
3.1The Council needs to demolish the swimming pool and leisure centre as there is a significant health and safety risk to the Council once this site becomes vacant.
3.2A vacant site at Sansome Walk is a likely to target for a number of issues that pose a high health and safety risk to the Council, including, vandalism, theft and fire. The site will also present a significant health and safety risk to anyone who enters on the site and the Council has a duty of care as the owner of the building to ensure that the site does not present a risk to anyone entering the site, including trespassers. In particular a vacant building will present risks of falls from height, and slip and trip hazards.
3.3Site security, involving physical works and patrols which will incur significant cost, can mitigate but not satisfactorily reduce these risks.
3.4Further work is required by officers to obtain the relevant environmental and planning consents to demolish the buildings on the site. There will need to be ground investigation works carried out to determine the extent of any land contamination. Asbestos investigations and removal works may be required as part of the demolition process.
3.5Given the range of potential works that need to be undertaken and the significant likelihood of the building being the subject of targeted vandalism, the Council needs to demolish the buildings in the short-term on health and safety grounds.
4. Options Appraisal
4.1The site is allocated in the SWDP for housing, a use which is also support by the new City Plan.
4.2As part of an appraisal of future delivery options, the Council will need to consider whether to realise a capital receipt from the disposal of the site or whether there is also the potential to generate a revenue stream.
4.3A “Void Management Plan” is being put in place to ensure the empty site is secure and safe when vacated by Freedom Leisure. This will be in place until either preliminary demolition by the Council or redevelopment after an options appraisal.
Alternative options considered
5.1As noted above, the site presents a significant health and safety risk and therefore it is not considered viable to simply erect a hoarding around the site and allow the building to remain in situ until such time that the site is developed.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.