That the Council: 1. notes the content of the examiner’s report on the joint examination of the South Worcestershire CIL Charging Schedules (Appendix 1) and agrees the modifications in the report that are considered necessary to make the Charging Schedules sound; 2. adopts the amended CIL Charging Schedule (Appendix 3), as set out in (a) above as the appropriate basis for charging CIL in Worcester; 3. adopts the Regulation 123 List and the instalment policy (Appendix 3) alongside the Worcester CIL Charging Schedule in (b); 4. agrees that CIL will be implemented from Monday 4 September 2017; 5. agrees the revised South Worcestershire Joint Advisory Panel Terms of Reference (Appendix 4) relating to CIL expenditure governance arrangements; and 6. delegate authority to the Corporate Director - Place, in consultation with the Chair of the Place and Economic Development Sub-Committee, to undertake the final stages associated with the formal adoption and implementation of CIL, including any minor textual changes to documents in the interest of clarity and accuracy.
Word for word from the decision Worcester published for this meeting.Source: committee.worcester.gov.uk
(a) Notes the content of the examiner’s report on the joint examination of the South Worcestershire CIL Charging Schedules (Appendix 1) and agrees the modifications in the report that are considered necessary to make the Charging Schedules sound.
(b) Adopts the amended CIL Charging Schedule (Appendix 3), as set out in (a) above as the appropriate basis for charging CIL in Worcester.
(c) Adopts the Regulation 123 List and the instalment policy (Appendix 3) alongside the Worcester CIL Charging Schedule in (b).
(d) Agrees that CIL will be implemented from Monday 4 September 2017.
(e) Agrees the revised South Worcestershire Joint Advisory Panel Terms of Reference (Appendix 4) relating to CIL expenditure governance arrangements.
1.2Delegate authority to the Corporate Director Place, in consultation with the Chair of the Place and Economic Development Sub Committee, to undertake the final stages associated with the formal adoption and implementation of CIL, including any minor textual changes to documents in the interest of clarity and accuracy.
Background
2.1The Worcester Community Infrastructure Levy (CIL) Charging Schedule sets out the proposed rates of CIL to be charged on different types of new qualifying development in Worcester. Consistent with The Planning Act 2008 and The Community Infrastructure Levy Regulations 2010 (as amended) it is informed by the following evidence; the South Worcestershire Development Plan 2016 (SWDP); South Worcestershire Infrastructure Delivery Plan; and a series of development viability assessments prepared by HDH Planning and Development.
2.2The preparation of the CIL Charging Schedules has been undertaken jointly between the South Worcestershire Councils (SWCs), with the support of Worcestershire County Council, in accordance with the above legislation. Although each of the SWCs will be adopting CIL on a separate basis joint working on CIL formally started in September 2013, with further rounds of consultation and supporting evidence updates in 2015, and 2016. The final CIL documentation was submitted to the Planning Inspectorate for examination in July 2016. A public hearing into the CIL was held at The Guildhall in Worcester on 29 November 2016, overseen by the independent examiner [name removed], and his report was received in January 2017 (Appendix 1).
2.3The examiner’s report concluded that, subject to some minor modifications, the charging schedule provides an appropriate basis for the collection of CIL in Worcester. Further to the examination the examiner’s minor modifications recommendations to the CIL were advertised, and at the same time the SWCs took the opportunity to consult on a revised Regulation 123 List from 13 February to 27 March 2017. The responses to this final consultation stage, with officer recommendations are set out in Appendix 2.
2.4As a result of this process Worcester is now in a position to adopt the Charging Schedule, Regulation 123 List and instalment policy and implement CIL in Worcester (Appendix 3). Subject to the approval of the recommendations, in this report, the charging of CIL will commence on Monday 4 September 2017 on all liable development granted planning permission on or after that date.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.