That Planning Committee approve the draft Water Management and Flooding Supplementary Planning Document, as set out at Appendix 1 to this report, for a six week public consultation in February and March 2018. 2. That delegated authority is given to the Deputy Director - Economic Development and Planning, in consultation with the Chair of Planning Committee, to make any minor changes to the document before it is published for consultation.
Word for word from the decision Worcester published for this meeting.Source: committee.worcester.gov.uk
1.1That Planning Committee approve the draft Water Management and Flooding Supplementary Planning Document, as set out at Appendix 1 to this report, for a six week public consultation in February and March 2018.
1.2That delegated authority is given to the Deputy Director - Economic Development and Planning, in consultation with the Chair of Planning Committee, to make any minor changes to the document before it is published for consultation.
Background
2.1The purpose of the SPD is to provide guidance for planning applicants, planning officers and other interested parties on how the requirements of policies SWDP28, SWDP29 and SWDP30 of the adopted South Worcestershire Development Plan (SWDP), relating to Flood Risk, Sustainable Drainage Systems and Water Supply, are applied. The SPD also aims to assist co-ordination between the regulatory authorities in the resolution of water management.
2.2The intention is to publish this document for a six week public consultation, commencing in early February 2018.
2.3A Scoping Paper for this proposed SPD was published and consulted upon between Monday 13th February 2017 and Monday 27th March 2017. Nine responses were received and are summarised below. These responses helped shape the initial draft SPD and are summarised below and a full Statement of Consultation is included at Appendix 2 to this report.
Environment Agency – supportive of the production of the SPD and detailed a number of areas which the SPD might want to discuss, including roles and remits, biodiversity betterment and climate change.
Worcestershire County Council – agreed that the issues outlined in the Scoping Paper should be addressed in the SPD and provided further sources of information.
Natural England – topic unlikely to have a major impact on the natural environment, but may nonetheless have some effects. Provided some general information to refer to in the preparation of the SPD. Network Rail – provided information on Network Rail’s infrastructure and the requirements for drainage and water features in close proximity to it.
The Woodland Trust – promotes the use of trees and woods in appropriate locations to alleviate certain types of flood risk, and highlights a number of innovative schemes from across the UK.
David Lock Associates on behalf of Hallam Land Management – highlighted the importance of detailing national policy and guidance and that the SPD should make clear what is required and what is encouraged.
Worcestershire Wildlife Trust – agreed with scope of the SPD and provided useful information on issues that need to be considered when assessing development proposals.
South Worcestershire Land Drainage Partnership – agreed with the issues identified and provided references to a number of relevant documents.
Historic England – welcomed the preparation of the SPD as there are often implications for heritage assets. Appropriate management of flood risk could be beneficial for the historic environment.
2.4A focused consultation on the initial draft SPD was then run with key stakeholders from Wednesday 16th August 2017 to Friday 8th September 2017. A further five responses were received and they tended to be minor amendments to wording, additional paragraphs and useful references. They have assisted in refining the SPD to the draft which is proposed for consultation.
2.5Statutory consultees i.e. Historic England, Natural England and the Environment Agency were also consulted on Sustainability Appraisal issues and asked whether or not they require a separate Strategic Environmental Assessment. They both considered that it did not.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Minutes of Previous Planning CommitteeThat the minutes of the meeting held on 23 rd July 2026 be approved as a correct record and signed by the Chair, subj...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.