Resolved
That the Committee note the Council’s Quarter 3 Performance report for 2017/18.
Environment Committee noted this item on Tuesday 30 January 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
That the Committee note the Council’s Quarter 3 Performance report for 2017/18.
Appendix 1
Environment Committee Performance Report
Projects & Actions
Action Status
Cancelled
Overdue; Neglected
Unassigned; Check Progress
Not Started; In Progress; Assigned
Completed
Riverside park management plan Councillors and officers held a meeting to discuss challenges Responsible Alice Davey and opportunities which could improve the riverside. The Officer Riverside Park management plan is now being updated with Due Date 31-Mar-2018 actions arising from the meeting and feedback from the Green Flag Judge, in time for submission to Green Flag at Current Status the end of January 2018. Expected Outcome Project is showing as amber as a milestone to provide a mapping tool to stakeholders has been delayed but will be completed during Q4.
Gheluvelt Park Sons of Rest building Contract appointed and works commenced, including new Responsible Alice Davey bat boxes in nearby park trees as part of licence to mitigate Officer any disturbance during the demolition and construction. Due Date 30-Jun-2018 The contractor is working with the Worcester Resource Exchange centre to try an reuse the original buildings Current Status materials. Expected Outcome
Green Flags across the City Stakeholder meetings set for January to review Responsible Alice Davey management plans for Gheluvelt, Cripplegate and Fort Royal Officer Parks. Management plans will be updated before Due Date 30-Aug-2018 submission deadline at the end of January 2018. Current Status Expected Outcome
2 Environmental Enforcement review The initial review work has considered environmental Responsible Alice Davey enforcement in the context of council wide enforcement Officer policy. The proposed new Environmental Enforcement Policy Due Date 31-Jan-2018 will sit under an umbrella of corporate enforcement policies. A draft is currently being reviewed by the Legal team. Current Status Expected The review of the environmental enforcement function will Outcome be considered during January 2018, in light of the above policy.
Tree planting project Surveys completed for chosen locations and specification Responsible Sue Horrobin agreed between City Council and County Highways. Have a Officer plan of what trees will be planted where and we are working Due Date 31-Mar-2018 with County in order to tender works. Project is still on track for completion before the end of March. Current Status Expected Outcome
Cleaner Streets Report was considered by Environment Committee on 31st Responsible Sue Horrobin October and task & finish group established. Officer Due Date 31-Mar-2020 Some capacity challenges have been posed to this project due to service focussing on waste and recycling project but Current Status it remains on track for completion as planned. Expected Outcome
Recycling and Refuse Collection New rounds on track to commence 23rd January as detailed Responsible Sue Horrobin in report to October Environment Committee. Officer Communications plan including letters to customers and Due Date 31-Mar-2020 media campaign is underway. Current Status Expected Outcome
3 Key Performance Indicators
PI Status
Alert
Warning
OK
Unknown
Data Only
Standards for cleanliness - % assessed as having acceptable levels of detritus Current Value 90.4% Current Target 85% RAG
Aim to Maximise
Improved scores potentially due to the improved performance of sweeper vehicles and application of a new weed ripper machine which removes weeds and detritus from the gutter. One survey was carried out the day after the neighbourhood team had visited the area.
Standards for cleanliness - % assessed as having acceptable levels of litter Current Value 95.8% Current Target 85% RAG
Aim to Maximise
Improvement potentially due to allocation of staff from grass cutting to cleansing duties during the winter period.
4 Standards for cleanliness - % assessed as having acceptable levels for grass cutting Current Value 98.1% Current Target 85% RAG
Aim to Maximise
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Environment Commitee Q3 DRAFT 0.4Report | 6 pages | DownloadRead as text |
PDF |
Quarter 3 Performance Report 2017-18Report | 1 pages | Download |
Follow Environment Committee at Worcester and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 10 Mar 2026 | MinutesThat the minutes of the meeting held on 27 th January 2026 be approved as a correct record and signed by the Chair. | Approved | Open |
| 10 Mar 2026 | Proposed Committee Scorecard for 2026/27That the committee agree the proposed content of the Environment Performance Scorecard for 2026/27. | Agreed | Open |
| 10 Mar 2026 | Parking and Environmental Enforcement Service UpdateThat the Committee note the contents of the report. | Noted | Open |
| 27 Jan 2026 | MinutesThat the minutes of the meeting held on 4 th November 2025 be approved as a correct record and signed by the Chair. | Approved | Open |
| 27 Jan 2026 | Medium Term Financial Plan (MTFP) UpdateThat the Committee note the update on the Medium-Term Financial Plan (MTFP) as detailed in Appendix 1. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.