Resolved
That the Committee note the Council’s Quarter 4 performance for 2017/18.
Communities Committee noted this item on Wednesday 30 May 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
That the Committee note the Council’s Quarter 4 performance for 2017/18.
Appendix 1
Communities Committee Performance Report
Projects and Actions
Action Status
Cancelled
Overdue; Neglected
Unassigned; Check Progress
Not Started; In Progress; Assigned
Completed
Astwood Muslim Cemetery enhancements Project complete and installed. Responsible Alice Davey Officer Public launch delayed pending drainage works from PPL Due Date 31-Mar-2018 Current Status Expected Outcome
Review of Community Safety Partnership arrangements The new Partnership Plan was adopted at the South Responsible Alice Davey Worcestershire Community Safety Partnership meeting on 1 Officer February 2018. Due Date 31-Mar-2018 Current Status Expected Outcome
Retention of Cinderella Ground Boundary fencing completed during this period. Responsible Alice Davey Officer Project remains on track in terms of first dates for football Due Date 31-Mar-2019 (2018/19 season) and cricket (2019 season). Current Status Following further input from ECB, pavilion design is subject Expected to some minor amendments which have delayed granting of Outcome planning permission.
2 Implementation of Year 3 actions within the Private Sector Housing Strategy During Quarter 4 we have further refined the empty homes Responsible Nina procedure detailing the process, assessment of empty Officer Warrington homes and referrals to Council Tax to maximise NHB of Due Date 31-Mar-2018 those properties which have since been occupied. As well as further developing links with the Housing Solutions and Current Status Enabling Officer which will provide additional expertise in Expected this area. Outcome
Throughout this year the majority of the milestones have been completed. The outstanding milestone/action of reviewing BME groups in private rented accommodation has been scoped, researched and the report of the findings is being drafted. This action should be completed shortly.
Implementation of year 1 actions within the Health & Well Being Action Plan Actions for year 1 of the plan are either complete or on- Responsible Nina going. Officer Warrington Due Date 31-Mar-2018 On-going and future activities are included in the Year 2 Action Plan. These include strengthening the Worcester city Current Status Dementia action alliance and application to become a Expected dementia-friendly community and strengthening working Outcome with the mosque.
Review of the operation and delivery model of the Council’s Community Centres • Report to Communities Committee March 6th 2018. Responsible Alice Davey Recommendation approved to support the Community Trust Officer with a grant against the provision in 2018/19 with an Due Date 31-Mar-2018 associated Service Level Agreement. • Business planning support input now complete. Current Status • Business Plan produced by end Jan 2018. Expected Outcome Monitoring to continue throughout 2018/19
3 Key Performance Indicators - End of Year
PI Status Performance Trends
Alert Improving
Warning No Change
OK Getting Worse
Unknown
Data Only
Total number of crime incidents Current Quarter 2,021 Value Current Quarter Target Quarter RAG
Aim to Minimise
Annual Value Target Status Short Trend 2016/17 8,485 2017/18 9,860
Number of anti-social behaviour (ASB) incidents Current Quarter 1,381 Value Current Quarter Target Quarter RAG
Aim to Minimise
Annual Value Target Status Short Trend 2016/17 6,032 2017/18 6,264
4 Active participation at leisure centres Current Quarter 195,847 Value Current Quarter 183,626 Target Quarter RAG
Aim to Maximise
PLC - 16,427 took part in group ex, 3,700 up on Q4 in 2017. This was achieved through the improved group exercise timetable which now offers over 96 classes a week. Quarter 4 also saw 12,400 school swimmers, 1,900 up on 2017 Q4. St John’s C - 3115 under target for quarter due to increased competition and bad weather in January and March. NWSC - 3378 under target for quarter due to increased competition and the bad weather in January and March which resulted in the centre being closed for several days.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Communities 6Report | 7 pages | DownloadRead as text |
PDF |
Quarter 4 Performance Report for 2017/18Report | 1 pages | Download |
Follow Communities Committee at Worcester and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 24 Jun 2026 | MinutesThat the minutes of the meeting held on 11 th March 2026 be approved as a correct record and signed by the Chair. | Approved | Open |
| 24 Jun 2026 | Annual Disabled Facilities Grant UpdateThat the Committee agree to: 1. note the contents of this update report and in particular delivery of Disabled Facili... | Agreed | Open |
| 24 Jun 2026 | Long-Term Rough Sleeping Innovation Programme (LTRSIP)That the Committee agree to: 1. note the content of the report and in particular the detail outlined surrounding the ... | Agreed | Open |
| 24 Jun 2026 | Worcester City Strength in Community StrategyThat the Committee: 1. agree to note the contents of this report and the Worcester City Strength in Community Strateg... | Agreed | Open |
| 24 Jun 2026 | Extension of the Closure of Pedestrian Footpaths at Brickfields Railway Crossing and Kays Railway Crossing by Use of Public Space Protection Orders (PSPOs)That the Committee: 1. agree to note the findings of the report, in particular the outcome of the public consultation... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.