Application P17D0380 - Warmstry Court, Quay Street

Refused Planning 3 papers

Planning Committee refused this item on Thursday 19 July 2018. Below is the council's own wording, with the papers it was decided on.

Item53

Resolved

That the Committee refuse planning permission for the following reason: Policy SWDP 28 of the South Worcestershire Development Plan sets criteria for acceptable development within floodplain area “Yellow zone” to ensure development is acceptable in terms of risk to users and does not increase the risks to others, by way of increasing the flood risk overall. However the building is limited by wider constraints of being a Historic Asset and its relationship to the surrounding development of Warmstry court and Bridge Street. In the opinion of the Local Planning Authority, the frequency of likely flooding and the measures required to reduce the impacts are incompatible with residential occupation of the site and the benefits of occupation of the building in conservation terms do not outweigh the risks from flooding for future residents of the building. The frequency and depth of the flooding in the area is anticipated to increase and the measures proposed would continue to be insufficient in times of flood, and as such it is not considered to be sustainable development and fails to meet the criterial as set out in policy SWDP 28 of the South Worcester Development Plan and would thereby also be contrary to the aims and interests that the National Planning Policy Framework seeks to protect and promote with regard to flood risk.
Word for word from the decision Worcester published for this meeting. Source: committee.worcester.gov.uk

Follow this further

Built from Worcester's papers

What the report saysPro

Report to Planning Committee, 2 pages

Recommendation

1.1The Deputy Director - Economic Development and Planning recommends that the Planning Committee refuse planning permission for the following reason:

Policy SWDP 28 of the South Worcestershire Development Plan sets criteria for acceptable development within floodplain area “Yellow zone” to ensure development is acceptable in terms of risk to users and does not increase the risks to others, by way of increasing the flood risk overall.

However the building is limited by wider constraints of being a Historic Asset and its relationship to the surrounding development of Warmstry court and Bridge Street.

In the opinion of the Local Planning Authority, the frequency of likely flooding and the measures required to reduce the impacts are incompatible with residential occupation of the site and the benefits of occupation of the building in conservation terms do not outweigh the risks from flooding for future residents of the building.

The frequency and depth of the flooding in the area is anticipated to increase and the measures proposed would continue to be insufficient in times of flood, and as such it is not considered to be sustainable development and fails to meet the criterial as set out in policy SWDP 28 of the South Worcester Development Plan and would thereby also be contrary to the aims and interests that the National Planning Policy Framework seeks to protect and promote with regard to flood risk.

Background

2.1At the meeting on 24th May 2018 the application was deferred for a site visit in order for members to assess the implications of localised flooding conditions on site.

3. Comments of Deputy Director of Economic Development and Planning

3.1I have no further comments to make in addition to my previous report, which is attached as Appendix 1 and which has been updated to incorporate the substitutions and corrections as detailed in my late paper report for clarity. A copy of the Flood Evacuation Management Plan submitted as part of the application is attached as Appendix 2.

Ward: Cathedral Contact Officer: Sally Watts Tel: (01905 722172) [email protected] Background Papers: Appendix 1- Officer’s report to the Planning Committee at the meeting on 28th June 2018

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Application P17D0380: Appendix 1Appendix 19 pages Download
PDF
Application P17D0380: Appendix 2Appendix 3 pages Download
PDF
Application P17D0380: Warmstry Court, Quay StreetReport 2 pages DownloadRead as text

More from Worcester Planning Committee

All decisions
MeetingDecisionOutcome
13 Aug 2026 Minutes of Previous Planning CommitteeThat the minutes of the meeting held on 23 rd July 2026 be approved as a correct record and signed by the Chair, subj... Approved Open
23 Jul 2026 Minutes of Previous Planning CommitteeThat the minutes of the meeting held on 21 st May 2026 be approved as a correct record and signed by the Chair. Approved Open
23 Jul 2026 Application 26/00440/LB - Worcester City Museum and Art Gallery, Foregate StreetThat the Committee grant Listed Building Consent, subject to conditions set out in section 9 of the report. Decided Open
23 Jul 2026 Planning Committee Annual Report 2025/26That the Committee approve the Planning Committee Annual Report and recommend it to Council for information. Approved Open
21 May 2026 Minutes of Previous Planning CommitteeThat the minutes of the meeting held on 16 th April 2026 be approved as a correct record and signed by the Chair. Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies