That the Joint Committee: 1. note progress to improve the visitor welcome in reception to visitors to the Art Gallery & Museum building; 2. approve the recommendations for change proposed in the business case following review of Worcester City Art Gallery & Museum operations team; and 3 authorise the Museums General Manager to implement the business case recommendations in the accompanying exempt report, following Worcester City Council procedures and in consultation with the Chair and Vice Chair of the Joint Museums Committee.
Word for word from the decision Worcester published for this meeting.Source: committee.worcester.gov.uk
1.1The Joint Museums Committee notes progress to improve the visitor welcome in reception to visitors to the Art Gallery & Museum building.
1.2The recommendations for change proposed in the business case following review of Worcester City Art Gallery & Museum operations team be approved.
1.3The Museums General Manager be authorised to implement the business case recommendations in the accompanying exempt report, following Worcester City Council procedures and in consultation with the Chair and Vice Chair of the Joint Museums Committee.
Background
Art Gallery & Museum reception
2.1As set out in Museums Worcestershire Service Plan for 2018-19, planning is underway to improve the visitor welcome to Worcester City Art Gallery & Museum. This work follows audience evaluation showing a lower satisfaction for visitor welcome than at the other Museums Worcestershire sites.
2.2This project gives an opportunity for museum staff and other City Council staff to work more closely and create a facility that benefits both museum visitors and visitors to the City Council offices. The change in hosting of the museum service has facilitated these discussions and a joint project team will oversee the work.
2.3Investigations are currently underway to determine the impact of the plans on safe fire egress from the City Council offices and this has slightly delayed the budget planning and progress to the project implementation stage.
2.4Museums Worcestershire intends to apply for funding from Arts Council England to part fund this work alongside an improved introduction to the permanent museum displays. Further details will be brought back to the committee at a later meeting. Art Gallery & Museum operations review
2.5At the meeting on 16 November 2017, the Joint Museums Committee approved an approach for delivering a more efficient service and reducing the annual contributions of each partner to the Joint Museums Service through team-by-team review. This included a review of the Museum & Art Gallery operations in 2018-19.
2.6The cost of service transformation was discussed at the Joint Museums Committee on 24 January 2018. It was agreed that museum reserves could be made available to fund structural change in the museum service using the theoretical pro-rata apportionment used to manage the Joint Museums Service finances – 39% Worcestershire County Council and 61% Worcester City Council.
2.7An internal review has been undertaken, considering the most efficient management of the site, the appropriate level of all expenditure and income budgets and evidence of audience engagement.
2.8The business case following this review and its recommendations are set out in the exempt appendix.
3. Preferred Option
3.1The business case in the exempt appendix lays out recommendations based on a review of Worcester City Art Gallery & Museum operations.
Alternative options considered
4.1Alternative options are included in the exempt appendix.
5. Implications
5.1Financial and Budgetary Implications Further financial details on the reception welcome project will be brought to a future meeting for review.
5.2Legal and Governance Implications There are no legal or governance implications to the proposed work.
5.3Risk Implications The operations review has been undertaken as part of the City’s transformation projects. Delays or changes would present a risk to reaching those targets for the City Council.
5.4Corporate/Policy Implications There may be corporate or policy implications to the proposed reception function depending upon its final scope. This will be considered by the joint project team and brought back for review if required.
5.5Equality Implications The business case has been reviewed, concluding that there are no equality implications to this work. 5.6 Human Resources Implications Worcester City HR team have been involved in the preparation work towards the business case review.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Annual Review and Performance in 2025-26That the Joint Committee: 1. approve the Museums Worcestershire Annual Review for 2025/26; and 2. note the informatio...
Quarter 4 Finance Report 2025-26That the Joint Committee: 1. note the financial monitoring details including budget variances for the financial year ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.