CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Worcester City Council
Communities Committee, Wednesday 30 January 2019 at 7.00pm

Strategic Housing Transformation Temporary Accommodation Supply

Agreed Committee 6 papers

Communities Committee agreed this item on Wednesday 30 January 2019. Below is the council's own wording, with the papers it was decided on.

Item52

Resolved

That the Committee agree to: 1. approve the business case and overall approach to acquiring properties for direct letting and management in order to reduce the Council’s reliance on private bed & breakfast and guest house accommodation; 2. approve the acquisition by the Council of the following properties in order to deliver up to 12 units of temporary accommodation, namely: 145 Bromyard Rd – up to 8 units (minimum of 6 units) 197 – 203 Oldbury Road - 4 units; and 3. recommend to Policy & Resources Committee that the cost of acquiring both properties and bringing them into use is met from the remaining New Homes Bonus Earmark Reserve of £236,000.
Word for word from the decision Worcester published for this meeting. Source: committee.worcester.gov.uk

Follow this further

Built from Worcester's papers

What the report saysPro

Report to Communities Committee, 9 pages

Recommendation

1.1That Committee approves the business case and overall approach to acquiring properties for direct letting and management in order to reduce the Council’s reliance on private bed & breakfast and guest house accommodation;

1.2That Committee approves the acquisition by the Council of the following properties in order to deliver up to 12 units of temporary accommodation, namely - i. 145 Bromyard Rd – up to 8 units (minimum of 6 units) ii. 197 – 203 Oldbury Road - 4 units; and

1.3The Committee recommends to Policy & Resources Committee that the cost of acquiring both properties and bringing them into use is met from the remaining New Homes Bonus Earmark Reserve of £236,000.

Background

2.1The Homelessness Reduction Act 2017 (HRA) came into force on the 3rd April 2018. Since its implementation the Housing Service has seen a 40% increase in the number of customers requesting housing assistance which subsequently has increased the number of placements being made into temporary accommodation (TA) and the length of stay. Even though the Council’s performance in respect of preventing performance and relieving homelessness remains steady the increase in demand for services as a result of HRA has caused an increased pressure on TA.

2.2The current provision of TA relies heavily on the use of emergency bed & breakfast accommodation which is more expensive and results in the greatest financial penalty for the Authority in terms of subsidy loss incurred via the housing benefit subsidy system. The forecast loss for 2018/19 is £400k compared to £335k in 2017/18. The table below sets out the position on net housing benefit subsidy from 2014/2015 onwards.

Worcester City Council Housing Benefit Subsidy Report Summary of Totals 2018/19 to date 2017/18 2016/17 2015/16 2014/15 Cost claimed back from government 318,189 252,595 237,283 253,077 315,475 Costs incurred by the Council 267,800 334,756 168,247 102,031 132,493 585,988 587,351 405,530 355,108 447,968 2.3 Each homeless household placed in TA receives a housing benefit entitlement of £103.00 per week regardless of household size. The cost of hotel and bed & breakfast accommodation varies from £175.00 - £490.00 per week, a potential shortfall that needs to be bridged by the Council of between £72.00 - £387.00 per week for each household placed.

2.4Claims are submitted in a timely way for each and every household placed in TA to Housing Benefit and the initial expenditure for the TA is taken from the council’s strategic housing temporary accommodation budget. Housing Benefit pay this budget back in full depending on the benefit entitlement of the household and the claim being completed promptly and accurately. This is an area of work focussed on by the housing service to prevent the loss in appropriate income and recovery rates have remained consistent at 85% or more for several years.

2.5A TA review has been completed and is attached at Appendix 1 confirming that there is a gap in TA supply of 62 units. The review focussed on the existing supply across a range of measures that included type of accommodation, number of units available, cost and suitability. A similar review has been undertaken post the implementation of the HRA taking into account the increase in demand for housing assistance.

2.6A project group was established as requested by the Housing Transformation Board to investigate options to address the identified gap in TA supply. To aid this work an all Member briefing session was held during September 2018 to share the issues the council is facing and which outlined the growing financial impacts and the proposal to acquire a supply of TA which could be managed in-house. A range of property options have been or are under investigation with 2 property options that are recommended by this report, ready to be progressed and delivered subject to approval.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
TA NEEDS ASSESSMENT SUMMARYAppendix 1 2 pages Download
PDF
Temp Accom Overview (Committee)Appendix 2 4 pages Download
PDF
Bromyard RoadAppendix 3 5 pages Download
PDF
Oldbury RoadAppendix 4 4 pages Download
PDF
TA Detailed FinancialsAppendix 5 1 pages Download
PDF
Strategic Housing Transformation Temporary Accommodation SupplyDecisions 9 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Worcester

Search all
  1. Strategic Housing Transformation Temporary Accommodation SupplyThis decision
  2. Referral Report from Communities Committee - Strategic Housing Transformation Temporary Accommodation SupplyAgreed
  3. Worcestershire Strategic Housing Partnership Plan Annual Performance Report 2017/18Noted
  4. New Worcestershire Strategic Housing Partnership PlanAgreed
  5. Strategic Housing IssuesNoted

More from Worcester Communities Committee

All decisions
MeetingDecisionOutcome
24 Jun 2026 MinutesThat the minutes of the meeting held on 11 th March 2026 be approved as a correct record and signed by the Chair. Approved Open
24 Jun 2026 Annual Disabled Facilities Grant UpdateThat the Committee agree to: 1. note the contents of this update report and in particular delivery of Disabled Facili... Agreed Open
24 Jun 2026 Long-Term Rough Sleeping Innovation Programme (LTRSIP)That the Committee agree to: 1. note the content of the report and in particular the detail outlined surrounding the ... Agreed Open
24 Jun 2026 Worcester City Strength in Community StrategyThat the Committee: 1. agree to note the contents of this report and the Worcester City Strength in Community Strateg... Agreed Open
24 Jun 2026 Extension of the Closure of Pedestrian Footpaths at Brickfields Railway Crossing and Kays Railway Crossing by Use of Public Space Protection Orders (PSPOs)That the Committee: 1. agree to note the findings of the report, in particular the outcome of the public consultation... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies