Perdiswell Park Improvements

Noted Committee 1 paper

Environment Committee noted this item on Tuesday 5 March 2019. Below is the council's own wording, with the papers it was decided on.

Item40

Resolved

That the Committee note the contents of the report including the funding allocated to each phase of the works and the progress made on Phase One.
Word for word from the decision Worcester published for this meeting. Source: committee.worcester.gov.uk

Follow this further

Built from Worcester's papers

What the report saysPro

Report to Environment Committee, 2 pages

Recommendation

1.1That the Committee notes the content of this report including the funding allocated to each phase of the works and progress made on Phase One.

Background

2.1In June 2018 the Council allocated funding of £100,000 towards improvements at Perdiswell Park. This is split between work to enhance safety on the leased land following the transfer of 9 holes of the golf course to Ravenmeadow Golf Centre (£30,000), and improvement work around the rest of Perdiswell Park (£70,000). The work is being conducted in 2 phases.

2.2The first phase is on the leased land occupied by Ravenmeadow Golf Centre and is specifically for improvements to wayfinding, signage, pathway surfacing, improved visibility along paths and better demarcation of Public Rights of Way. Our aim is to encourage walkers to stay on the paths when the course is in use and improve health & safety by reducing the risk of impact by golf balls.

2.3The second phase is to look at the wider Perdiswell Park area (including the former golf course and area surrounding the sports pitches) and decide how we improve the public experience of using this area. The new play area which opened in August 2018 has been a successful addition to the site.

3. Information

3.1Phase One: In November 2018, a landscape architect was commissioned to produce a range of options within the agreed budget for improvement works. These options included pathway marker posts, new surfacing and arboricultural work to improve visibility of pathways. In selected locations fencing, hedge rows and other planting was proposed to provide greater buffer zones and demarcation between paths and golf course playing areas.

3.2During January 2019, consultation with Ward Members, the Friends of Perdiswell Group and Golf Centre management was carried out to decide the best options and prioritise the work.

3.3The amendments to the Options Plan have included better definition of pathways, improved surfacing and signage so that walkers will be encouraged to follow approved routes around the course. Areas where undergrowth has encroached on to paths will be cut back and tree canopies raised to provide improved visibility. 3.4 Following approval of the revised Options Plan, the landscape architect will produce a works specification so that we can procure a contractor to start early April. The works should be complete by late Spring.

3.5The main park information signage has been redesigned to support the work being carried out as part of Phase One. The sign now includes public access times for the golf course area and dog trail routes around the course.

3.6Phase Two: From May 2019, we will commence a consultation exercise with stakeholders to build on the ideas for improvements already submitted for the rest of Perdiswell Park. The aim is to enhance visitor experience using the remaining budget provision (£70k) and encourage more use of the site.

3.7Once a feasibility exercise is complete, we will conduct a similar process to Phase One by engaging a landscape architect to develop a range of options for further discussion.

3.8Members will be consulted and kept up to date throughout the process. The improvement works will be completed during 2019/20.

Ward(s): Claines Contact Officer: Tim Allen, Environmental Operations Projects Manager Tel: 01905 752981 [email protected] Background Papers: P & R Committee meeting 05/06/18 Minute 5.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Perdiswell Park ImprovementsReport 2 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Worcester

Search all
  1. Perdiswell Park ImprovementsThis decision
  2. Application 21/01108/FUL - Perdiswell Park, John Comyn DriveRefused
  3. Improvements to Perdiswell ParkApproved

More from Worcester Environment Committee

All decisions
MeetingDecisionOutcome
10 Mar 2026 MinutesThat the minutes of the meeting held on 27 th January 2026 be approved as a correct record and signed by the Chair. Approved Open
10 Mar 2026 Proposed Committee Scorecard for 2026/27That the committee agree the proposed content of the Environment Performance Scorecard for 2026/27. Agreed Open
10 Mar 2026 Parking and Environmental Enforcement Service UpdateThat the Committee note the contents of the report. Noted Open
27 Jan 2026 MinutesThat the minutes of the meeting held on 4 th November 2025 be approved as a correct record and signed by the Chair. Approved Open
27 Jan 2026 Medium Term Financial Plan (MTFP) UpdateThat the Committee note the update on the Medium-Term Financial Plan (MTFP) as detailed in Appendix 1. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies