Art Gallery and Museum Welcome Improvements

Approved Committee 1 paper

Joint Museums Committee approved this item on Wednesday 12 June 2019. Below is the council's own wording, with the papers it was decided on.

Item9

Resolved

That the Joint Committee : 1. consider the proposed project to improve the Art Gallery and Museum foyer and visitor welcome; 2. approve the use of up to £14,000 of the Joint Museums reserve towards the Project; and 3. approve the submission of an application to Arts Council England for work to review and improve the visitor experience.
Word for word from the decision Worcester published for this meeting. Source: committee.worcester.gov.uk

Follow this further

Built from Worcester's papers

What the report saysPro

Report to Joint Museums Committee, 4 pages

Recommendation

1.1That the Joint Museums Committee consider the proposed project to improve the Art Gallery & Museum foyer and visitor welcome;

1.2Approve the use of up to £14,000 of the Joint Museums reserve towards the Project; and

1.3Approve the submission of an application to Arts Council England for work to review and improve the visitor experience.

Background

2.1Visitor numbers at MAG are slowly declining. Evaluation shows that exhibitions are strongly supported, with more than 50% of our audience travelling into Worcester specifically to see each exhibition. But visitor satisfaction with navigation, welcome and general facilities are lower than all other Museums Worcestershire sites, reflecting the lack of recent investment in the public side of the building.

2.2Initial consultation with the Arts Council England has met with support to submit an application seeking to consult and test improvements to the Art Gallery & Museum in order to support the direction of future planning for this museum. This funding stream does not cover capital build expenditure but can enable the improvement of displays, visitor evaluation and staff and business development.

2.3Reception facilities for the City Council offices were not resolved when the library space was converted. This project gives the opportunity for joint benefits for both the City offices and the museum service.

2.4The front-line team at the Art Gallery & Museum were re-structured in early 2019. The role of the staff in the shop now has a stronger focus on welcome, but this responsibility is hard to put into practice with the current arrangement of the foyer. Once in place, their role would include minor reception duties on behalf of the City Council welcoming business visitors as well as their core role welcoming museum visitors. Outside of public museum open hours, City staff could perform reception duties to the office area. 2.5 In 18-19, the museum shop generated an income of £23k. Further analysis (see graph below) has shown that the shop has a customer base that is distinct to the museum visitor. This reflects the shop’s reputation, particularly for its cards. It’s essential for the museum service funding profile to maintain the shop in the foyer, and to increase its income potential.

Shop income 18-19 £3,500.00

£3,000.00

£2,500.00

£2,000.00

£1,500.00

£1,000.00

£500.00

£0.00 ril

ay

ne

ly

st

y

ry

ch r

r

r

r be

be

be

be

ar Ju

gu

ua Ap

M

ar Ju

nu em

to

m

m Au

M br ve

ce Oc

Ja pt

Fe De No Se

target income based on average spend per museum visitor income

2.6The City Council’s Property team were recently transferred from Place Partnership to the City Council. Once established in house, they and the museum team have started work assessing the detailed project requirements for the proposed improvements to the foyer and analysis of the costs.

2.7Alongside the work with the museum service, the Property team have also reviewed the fire safety and protection of the Art Gallery & Museum building. This will also require investment within the City Council’s capital programme, but is being considered as a separate project.

3 Project Outline

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Art Gallery and Museum Welcome ImprovementsReport 4 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Worcester

Search all
  1. Art Gallery and Museum Welcome ImprovementsThis decision
  2. Application 26/00440/LB - Worcester City Museum and Art Gallery, Foregate StreetDecided
  3. Art Gallery and Museum Admission Charges and IncomeAgreed
  4. City Art Gallery and Museum DevelopmentNoted
  5. Art Gallery and Museum DevelopmentNoted
  6. Canaletto Exhibition at Worcester Museum and Art GalleryNoted

More from Worcester Joint Museums Committee

All decisions
MeetingDecisionOutcome
15 Jul 2026 MinutesThat the minutes of the meeting held on 5 th March 2026 be approved as a correct record and signed by the Chair. Approved Open
15 Jul 2026 Election of ChairThat Councillor Robinson be elected as Chair for the ensuing year. Decided Open
15 Jul 2026 Appointment of Vice-ChairThat Councillor Cooper be elected as Vice Chair for the ensuing year. Decided Open
15 Jul 2026 Annual Review and Performance in 2025-26That the Joint Committee: 1. approve the Museums Worcestershire Annual Review for 2025/26; and 2. note the informatio... Approved Open
15 Jul 2026 Quarter 4 Finance Report 2025-26That the Joint Committee: 1. note the financial monitoring details including budget variances for the financial year ... Approved Open