That the Committee approves the proposed works identified to meet short term priorities (see paragraph 3.10) and delegates authority to the Corporate Director - Place in consultation with the Chair and Vice Chair of Environment Committee to approve the final scheme of works to maintain Green Flag status for Riverside Park, subject to detailed costings. 2. That subject to detailed costings and budget availability, the Committee delegates authority to the Corporate Director Place in consultation with the Chair and Vice Chair of Environment Committee to approve additional works (see paragraph 3.10). 3. To recommend to Policy and Resources Committee that £244k of City Plan and Income Generation funding will be used for the delivery of improvement works to the Riverside Park. 4. That the Committee welcomes the award of Green Flag for the Riverside Park.
Word for word from the decision Worcester published for this meeting.Source: committee.worcester.gov.uk
1.1That the Committee approves the proposed works identified to meet short term priorities (see paragraph 3.10) and delegates authority to the Corporate Director - Place in consultation with the Chair and Vice Chair of Environment Committee to approve the final scheme of works to maintain Green Flag status for Riverside Park, subject to detailed costings.
1.2That subject to detailed costings and budget availability, the Committee delegates authority to the Corporate Director Place in consultation with the Chair and Vice Chair of Environment Committee to approve additional works (see paragraph 3.10).
1.3To recommend to Policy and Resources Committee that £244k of City Plan and Income Generation funding will be used for the delivery of improvement works to the Riverside Park.
1.4That the Committee welcomes the award of Green Flag for the Riverside Park.
Background
2.1On 27th November Environment Committee:
Agreed that the area defined in the report will be referred to as ‘Riverside Park’; Noted progress on the Riverside Project and agreed to the recommended short term priorities and actions working towards Green Flag Award status for the Riverside Park; Approved appointment of a landscape consultant to design and specify works to deliver the short term priorities recommended within this report; and Approved the actions identified in the Income Generation Task and Finish Group to be adopted within the Riverside Project.
2.2Environment Committee agreed that attainment of Green Flag status is an initial step in a larger project looking at the Riverside which includes recommendations from the Income Generation Task and Finish Group along with the wider Masterplan. To bring the park to the standard required, the Committee agreed a number of short term priorities, based on feedback from Green Flag judges:
creating an identity to encourage exploration of the Riverside; carrying out essential repairs and maintenance; investigating the conservation and wildlife importance; identifying improvements to complement wildlife and recreational access; engaging with its residential population and promote the facilities and activities within the Riverside; engaging with visitors specifically to highlight the work of its clubs and societies.
2.3Delivery of these priorities will come through a mix of hard/soft landscaping improvements and expanding work already happening as part of the Riverside Park Management Plan. Paragraph 3.10 outlines in more detail plans for delivering against these short term priorities.
2.4An application was submitted to Keep Britain Tidy in January 2019 for the Riverside Park to be considered for Green Flag status and receive critical feedback. The date of judging was held on 23rd May. Council officers hosting the judge’s visit were supported by partner agencies, volunteers and Councillors.
2.5The income generation elements of mooring improvements and concessions are being delivered through the City Council in house Property and Asset team. Progress to date is as follows:
Short term three year lease for Café off Croft Road has been completed with Café Viaduct opening 7 days a week from 1st April. A coffee car concession adjacent to Copenhagen street car park started trading in January. The City Council has ordered the installation of an electricity point for a metered supply. Riverside mooring improvements and boating concession are at feasibility stage. The Council’s Property and Asset Management service is taking the lead on procuring the feasibility study and quotations will be sought following agreement on the consultant’s brief.
3. Key Issues
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.