That the Joint Committee: 1. approve the proposed changes to admission charges at Hartlebury Castle for 2020/2021, as set out in Appendix 3; 2. delegate to Worcestershire County Council’s Assistant Director for Communities the decision to reverse the increased charge if needed following review, as outlined in the preferred option; and 3. approve the temporary alteration from 1/1/2020 of any fees to be included in the annual leaflet.
Word for word from the decision Worcester published for this meeting.Source: committee.worcester.gov.uk
1.1The Museums Manager recommends that the Joint Museums Committee approve the proposed changes to admission charges at Hartlebury Castle for 2020/2021, as set out in Appendix 3;
1.2The Joint Museums Committee delegate to Worcestershire County Council’s Assistant Director for Communities the decision to reverse the increased charge if needed following review, as outlined in the preferred option; and
1.3That the Joint Museums Committee approves the temporary alteration from 1/1/2020 of any fees to be included in the annual leaflet.
Background
2.1At their September meeting, the Joint Museums Committee approved changes to fees & charges for Museums Worcestershire as part of the annual fees-setting process at each local authority. It was noted that Hartlebury Castle Preservation Trust (HCPT) were working on benchmarking and business planning and that a further report would be brought to this meeting if required.
2.2Under the terms of their agreement with Worcestershire County Council (WCC), HCPT should propose changes to the shared admissions charges. They should be reviewed by the Strategic Review Board and then ratified by HCPT’s Trustees and the Joint Museums Committee before the end of November each year.
2.3HCPT have submitted a proposal for new admission charges to Hartlebury Castle in 2020-21 and these are attached as Appendix 1.
2.4Appendix 1 also includes the increased grounds-only charges proposed by HCPT for 2020-21. As these are not a shared admission charge, HCPT have sole responsibility for setting the level of these charges.
2.5HCPT have benchmarked the admission charges against other comparable local attractions, reviewing both the charge and what each includes in their review. A summary of this is included in Appendix 1. 2.6 Previously the split of shared admission charges has been such that overall, each partner has taken a very similar share (see Appendix 2). The proposed changes to admissions charges mean, should visitor numbers remain the same as in 2019, WCC’s annual share will remain static, while HCPT’s annual share will increase by approximately £6,000.
2.7This additional income is required by HCPT to meet the costs under their responsibilities to safely maintain the 40-acre grounds at Hartlebury Castle.
3. Preferred Option
3.1That WCC support HCPT to meet their ongoing high costs of maintaining the grounds by approving the proposed increases to shared admission charges.
3.2It is proposed that the increased charges and their impact on visitor numbers be reviewed in September 2020 by the Hartlebury Strategic Review Board. It is proposed that the option of reversing the increase if required be delegated to WCC’s Assistant Director for Communities in discussion with the Chair of HCPT, and in consultation with the Joint Museums Committee Chair and Vice-Chair.
3.3It is also proposed to alter the format of the Family ticket to bring it in line with similar local attractions, moving from 2 adults and 2 children to 2 adults and 3 children.
Alternative options considered
4.1Audience Finder surveys this year have shown that visitors’ perception of value for money at Hartlebury has decreased by 13%. Museums Worcestershire preference had therefore been to not increase the admission charges this year. However, both Museums Worcestershire and WCC support HCPT’s new business planning for the site and recognise the high costs of grounds maintenance.
4.2HCPT had originally proposed a new grounds element to the Educations Groups ticket. As considerable joint work is being undertaken to attract more schools, this was agreed to be counter-productive. Instead more work will be undertaken to promote HCPT’s education offer, including potential new outdoor sessions.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Annual Review and Performance in 2025-26That the Joint Committee: 1. approve the Museums Worcestershire Annual Review for 2025/26; and 2. note the informatio...
Quarter 4 Finance Report 2025-26That the Joint Committee: 1. note the financial monitoring details including budget variances for the financial year ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.