That the Committee grant planning permission , in accordance with Regulation 3 of the Town and Country Planning General Regulations 1992 subject to the conditions set out in section 9 of the report and to the additional condition for repair and marking out of car park prior to occupation of development.
Word for word from the decision Worcester published for this meeting.Source: committee.worcester.gov.uk
1.1The application was registered on 17 November 2020 and was due for a decision on 12 January 2021. An extension of time for the determination of the application has been agreed until 22nd January 2021 to allow determination by the Planning Committee.
1.2The application has been referred to the Planning Committee in accordance with the adopted Scheme of Delegation.
2. The site and surrounding area 2.1 The site is in the north east of the city, and forms part of the centre of community uses at the heart of the area of Warndon. On the site is an existing community centre and family centre, as well as public park and play area which provides links in the wider area to the local shops and services and 2 primary schools as seen in the site location plan below.
Figure 1. Site location plan. (Block A- community centre, Block B- family centre, Block C- ‘Building blocks’)
2.2The shared site has a large communal car park and the site is accessed via an entrance which runs along the side boundary shared with Oasis Academy Primary School as seen on the photograph below (Figure 2).
Figure 2. Showing the existing entrance to the building block from the car park
2.3The existing detached building is to the rear of the community centre, both are proposed to remain. Built of corrugated metal and forming a single shape with the principle entrance on the west elevation. Figure 3 below, shows the close relationship with the community centre, with many of the functional areas of the community space looking over the building.
2.4The community centre and ‘Building Blocks’ is being run by Worcester Community Trust (WCT), a charity managing 6 community centres in Worcester. The building provides practical training for plastering, tiling, plumbing, electrics, brick laying and rendering.
Figure 3. Photograph showing building block existing building.
2.5The entire site is designated as Green space in the South Worcestershire Development Plan 2016.
3. The proposals
3.1The proposal is for the erection of a new two storey extension to the existing ‘Building Block’ building to form a reception lobby and entrance, office, meeting room, classroom and teaching facilities, training bays, learning corridor and ancillary spaces.
3.2There is a single door to link the existing building to the new extension which will allow for designated areas for training. Plastering, plumbing and tiling would remain in the old building but with more space and electrics and a teaching room at ground floor and bricklaying on the first floor in the extension, accessed via an external staircase.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Minutes of Previous Planning CommitteeThat the minutes of the meeting held on 23 rd July 2026 be approved as a correct record and signed by the Chair, subj...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.