Resolved
That the Sub-Committee note the Council’s Quarter 3 performance for 2020/21.
Income Management Sub-Committee noted this item on Thursday 28 January 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
That the Sub-Committee note the Council’s Quarter 3 performance for 2020/21.
Appendix 1
Income Generation Committee Performance Report
Income Generation Projects and Actions 2020/21
Action Status
Cancelled
Overdue; Neglected
Unassigned; Check Progress
Not Started; In Progress; Assigned
Completed
Commercial Strategy delivery The Treasury consultation on the use of PWLB loans was Sponsor Mark Baldwin concluded in December and the results published as part of Due Date 31-Mar-2022 the financial settlement. The proposals have been accepted in full, which effectively prevents the Council from accessing Original Due 31-Mar-2022 PWLB for loans in the event that it has plans in the capital Date programme to purchase investment properties. This will Current Status require the Commercial Strategy to be rewritten. Expected There is one proposal still under consideration. Estate Outcome surveyors have been appointed to assess the suitability of the site for development but have not been able to access the property because of the closure of a number of businesses at the site due to Covid restrictions. This will be addressed in Q4.
The Council has been award £18m for the Future High Street Fund proposals which will enable substantial investment which will provide a return over time. The full impact of this success will be worked through in Q4 and a procurement process has begun to find a suitable project manager to take the schemes forward. The Towns Fund projects have been defined and a submission will be made at the end of January. This includes schemes which relate to the Council's ambitions in relation to the Riverside and maximising the value of the estate, including community centres.
2 Income Strategy Delivery Delivery against the income strategy continues to be Sponsor Shane Flynn affected by the Covid disruption and wider economic impact. Due Date 31-Mar-2021 There is a risk, for example, that income from car parking, for example, will not return to pre 2020 levels due to Original Due 31-Mar-2021 employees working remotely rather than travelling into the Date city centre and parking all day and from increased internet Current Status shopping. The latter will have a knock on effect on business rates too. Budgeted Income from Bereavement Services has Expected been reduced in line with expected loss of share of this Outcome business.
The conclusion of the PWLB loans consultation means that planned income of c.£500k p.a. will now not be achieved from this source and an alternative source of income needs to be identified, or costs reduced accordingly. Income from properties purchased before the change, however, remains secure. Developments in the FHSF and Towns Fund investment programmes may represent a source of income for the Council in future and this is to be taken into account in the development of the schemes.
The Income Strategy will be reviewed alongside the Commercial Strategy in 2021/22.
Sports facilities Work on the International Hockey Centre has continued Sponsor Shane Flynn although it is now anticipated that the centre will be open Due Date 30-Nov-2020 until autumn of 2021 because of the delays in getting contractors on site due to Covid disruptions. Work on the Original Due 31-Mar-2019 tennis courts at Cripplegate Park is complete and Freedom Date Leisure have established the new service although they Current Status have not been able to deploy this fully to date. the courts have remined open during the lockdown, however. Expected Outcome The Council has continued to support swimming provision through a grant to the Worcester Citizens Swimming Baths Association, which his funded from the Transformation Fund established to support the recovery from Covid. This is generating a small amount of income for the Council in terms of the loan provided in 2019/20, as is the loan to the FA to support the return of Worcester City FC to the city at the FA's Claines Lane ground.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
2020-21 Q3 Inc Gen App1 FinalReport | 7 pages | DownloadRead as text |
PDF |
Quarter 3 Performance Report for 2020/21Report | 1 pages | Download |
Follow Income Management Sub-Committee at Worcester and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 24 Jan 2024 | MinutesThat the minutes of the meeting held on 15 th November 2023 be approved as a correct record and signed by the Chair. | Approved | Open |
| 24 Jan 2024 | Proposed Fees and Charges 2024/25That: 1. the Sub-Committee agree to recommend the proposed schedule of Fees and Charges for 2024/25 to the Policy and... | Agreed | Open |
| 24 Jan 2024 | Quarter 3 Performance Report for 2023/24That the Sub-Committee note the Council’s quarter 3 performance for 2023/24. | Noted | Open |
| 24 Jan 2024 | Items Involving the Disclosure of Exempt informationThat under Section 100A(4) of the Local Government Act 1972, the press and public be excluded from the meeting for th... | Decided | Open |
| 15 Nov 2023 | MinutesThat the minutes of the meeting held on 14 th June 2023 be approved as a correct record and signed by the Chair. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.