Resolved
That the minutes of the meeting held on 14 th October 2020 be approved as a correct record and signed by the Chairman.
Personnel and General Purposes Sub-Committee approved this item on Wednesday 3 March 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
That the minutes of the meeting held on 14 th October 2020 be approved as a correct record and signed by the Chairman.
PERSONNEL AND GENERAL PURPOSES SUB-COMMITTEE
14th October 2020
Present: Councillor Gregson (Vice-Chair) in the Chair
Councillors Bayliss (Vice-Chairman), Berry, [name removed], Mitchell and Squires
Officers: David Blake, Managing Director Shane Flynn, Corporate Director – Finance and Resources Sian Stroud, Deputy Director - Governance
Apologies: Councillor Stephen
8 Appointment of Substitutes
Councillor Laurenson for Councillor Stephen.
9 Declarations of Interest
None.
10 Public Participation
None.
11 Minutes
RESOLVED: That the minutes of the meeting held on 15th July 2020 be approved as a correct record and signed by the Chairman.
12 Parental Bereavement Leave Policy and Procedure
The Sub-Committee considered the adoption of a Parental Bereavement Leave Policy and Procedure. The Corporate Director – Finance and Resources presented the report and explained that Parental Bereavement Leave is a new entitlement for bereaved parents to be absent from work, for up to two weeks. The new statutory right is available to the parents of a child, under the age of 18, who dies on or after 6th April 2020. The proposed Policy reiterated the Council’s commitment to supporting employees during times of bereavement.
Sub-Committee Members expressed support for the proposal.
RESOLVED: That the Sub-Committee approve the new Parental Bereavement Leave Policy and Procedure including enhancing statutory bereavement pay to ensure employees continue to receive their normal pay, regardless of their length of service. 14th October 2020 2
13 Living Wage Foundation Accreditation
The Corporate Director – Finance and Resources presented a report on progress since the previous report to this Sub-Committee on the matter on 26th February 2020.
In summary, Officers had:
• held discussions with Freedom Leisure, the Council’s main contractor that will be affected by these proposals;
• contacted the procurement team at Birmingham City Council who explained how they have built living wage compliance into their procurement processes;
• reviewed the legal position to understand fully the potential implications of procurement regulations in relation to Living Wage Employer accreditation.
Freedom Leisure estimated that this would add around £110,000 a year to their payroll costs. However, the Living Wage Foundation did not anticipate that contractual arrangements with suppliers should altered in mid-contract. Therefore, the change would not come into force under normal circumstances until 2025, by which date the actual rate would have increased. Freedom Leisure had confirmed that their business model can accommodate paying different rates for similar work in different parts of the country.
In summary, City Council accreditation with the Living Wage Foundation appeared to be entirely possible, but with cost implications. It was estimated that annual excess costs, most of which will not be incurred until 2025 on renewal of the leisure contract, would be in the order of £150,000 every year, based on current pay rates and applying inflation and a degree of contingency. If this policy was adopted then the City Council would need to plan for this by incorporating a cost pressure risk in the Medium Term Financial Plan and reviewing the balance of costs and benefits during the tender exercise for the Leisure contract when it is renewed.
In response to questions, the Corporate Director explained that the anticipated cost represented approximately 30% of the total contract fee. If that proved to be unaffordable, a contract variation might need to be considered. The Corporate Director undertook to do a further piece work to ascertain how this might impact on the number of staff employed to deliver the contract.
Sub-Committee Members concluded that there were significant benefits and expressed support for making an application for accreditation.
RESOLVED: That the Sub-Committee agree to:
1. note the analysis set out in this report and the previous report of 26th February 2020; and
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
MinutesMinutes | 3 pages | DownloadRead as text |
Follow Personnel and General Purposes Sub-Committee at Worcester and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 8 Dec 2025 | Item Involving the Disclosure of Exempt InformationThat under Section 100A(4) of the Local Government Act 1972, the press and public be excluded from the meeting for th... | Decided | Open |
| 28 Feb 2024 | MinutesThat the minutes of the meeting held on 18 th October 2023 be approved as a correct record and signed by the Chair. | Approved | Open |
| 28 Feb 2024 | Referral Report from Joint Consultative and Safety Committee: Revised Equalities Policy for ApprovalThat the Sub-Committee: 1. approve the revised Equalities Policy attached at Appendix 1 to the report; and 2. agree t... | Approved | Open |
| 28 Feb 2024 | Unreasonable Customer Behaviour PolicyThat the Sub-Committee approve the new Unreasonable Customer Behaviour Policy attached at Appendix 1 to the report. | Approved | Open |
| 28 Feb 2024 | Item Involving the Disclosure of Exempt InformationThat under Section 100A(4) of the Local Government Act 1972, the press and public be excluded from the meeting for th... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.