That the Committee: 1. approves the proposed Action Plan for 2021-22 to deliver the adopted Environmental Sustainability Strategy 2020-2030; and 2. delegates authority to the Chair and Vice Chair to approve any amendments to the Action Plan that due to urgency may not be able to be brought to this Committee.
Word for word from the decision Worcester published for this meeting.Source: committee.worcester.gov.uk
1.1That the Committee approves the proposed Action Plan for 2021-22 to deliver the adopted Environmental Sustainability Strategy 2020-2030.
1.2That the Committee delegates authority to the Chair and Vice Chair to approve any amendments to the Action Plan that due to urgency may not be able to be brought to this Committee.
Background
2.1The Environmental Sustainability Strategy for the City of Worcester 2020-2030 was endorsed by the Environment Committee on 27 October 2020 and subsequently adopted by Council on 17 November 2020.
2.2The Action Plan for 2021-2022 included in Appendix 1 follows the adoption of the Strategy and looks to plan specific actions to be taken by the Council in the next two years.
3. Action Plan
3.1The Action Plan responds to the priorities for action identified in the Strategy and existing opportunities such as Green Homes Grant funding from central Government to upgrade the energy efficiency of poorly insulated homes where the occupants are on low income.
3.2A number of staff workshops, and meetings with the steering group have been held in the course of developing the Action Plan.
3.3Three headline actions/projects which will be initiated in the short term as per the action plan are: Delivery of the Green Homes Grant programmes A proposed small grants scheme aimed at supporting community environmental projects An annual summit and a regular forum to be established to engage partners
3.4Some of the projects or actions may have no direct cost to the Council, others may be met from existing budgets. Some will require funding from the approved environmental sustainability enabling budget in order to proceed. 3.5 Where a project has a financial cost which is proposed to be met from the enabling budget, a decision report will be brought to a future meeting of the Environment Committee.
3.6Whilst the Action Plan presented has a number of actions under the theme ‘Natural Environment’, following the declaration of the biodiversity emergency on 30 September 2020, it is intended that a dedicated biodiversity action plan will be developed.
3.7The development of the action plan responding to the biodiversity emergency will take place in consultation with stakeholders and partner organisations which have key roles in the protection and enhancement of biodiversity across the city.
3.8This action plan can be expected in the summer of 2021. Development of the plan will be overseen by the same cross-party steering group as for the Environmental Sustainability Strategy and Action Plan.
4. Governance
4.1It has been recognised by the steering group that this Action Plan must be a live document, updated when, for example, new funding opportunities become available.
4.2Proposals for additional actions or other amendments to the Action Plan will be considered in detail by the steering group prior to a decision by the Environment Committee.
4.3Notwithstanding the above, where an opportunity arises requiring a response as a matter of urgency, delegated authority to the Chair and Vice Chair will allow a decision to be taken in a timely manner to ensure that opportunities are not missed.
4.4The Environment Committee will be regularly updated on the progress of the delivery of the Action Plan, with more frequent engagement of the steering group. To regularly review progress against the action plan is within the approved terms of reference for the steering group.
Alternative options considered
5.1This Action Plan is required in order to plan delivery of the proposals and intentions outlined in the Environmental Sustainability Strategy. Without an Action Plan, allowing specific actions to be agreed, funding and resources to be allocated, the effective delivery of the Strategy would be compromised.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.