That the Committee: 1. agree to recommend to Policy and Resources an allocation of up to £15k to support the Wild about Worcester project, specifically for waymarking of the route and promotion of the initiative; and 2. note that the specification for any works to be funded by the City Council will be subject to approval by the Corporate Director, Homes and Communities in consultation with the Chair and Vice-Chair of this Committee.
Word for word from the decision Worcester published for this meeting.Source: committee.worcester.gov.uk
1.1That the Committee agrees an allocation of up to £15k to support the Wild about Worcester project, specifically for waymarking of the route and promotion of the initiative.
1.2That the Committee notes that the specification for any works to be funded by the City Council will be subject to approval by the Corporate Director, Homes and Communities in consultation with the Chair and Vice-chair of this committee.
Background
2.2The Council declared a biodiversity emergency in September 2020, having declared a climate emergency in 2019.
2.3The Environmental Sustainability Action Plan was agreed by the Environment Committee on 16th March 2021. Within this plan, a specific objective was to develop a Biodiversity Action Programme.
2.4The Biodiversity Action Programme was approved by this Committee in November 2021. The programme is focussed on updating management practices to support and enhance biodiversity in the city and also includes support for two specific projects that aim to increase community engagement with enhancing biodiversity.
2.5The report on Environmental Community grants, also on this agenda, describes a number of biodiversity-related projects that have been funded with small grants.
2.6Since the publication of the action programme Worcester Environmental Group (WEG), in collaboration with Onside Advocacy, has come forward with a proposal to establish a way-marked route around Worcester, helping residents to explore green spaces in the city, learn about nature and to improve their physical and mental health.
2.7This route would also act as a ‘wildlife corridor’, promoting the increase of biodiversity and protection of the environment.
2.8In March 2022 this committee received a presentation from Paul Snookes of Worcester Environmental Group on the ‘Wild About Worcester Way’. He proposed using existing rights of way to connect green spaces, with the aim of improving mental health and wellbeing for local residents. 1 More information on the proposal can be found on WEG’s website: https://www.theweg.org.uk/_files/ugd/47b98f_1e26ddc4dbeb43bfb360f209de5553f0.pdf
2.9In the ensuing discussion, Committee Members expressed support for this scheme and the Chair explained that he had asked Officers to present a paper to a future meeting, identifying how the Council can support the project.
3 Preferred Option
3.1WEG has presented a proposal to officers that includes waymarking of the route to ensure that it is easy to follow and that key features are highlighted. Interpretation boards, accessibility improvements, creation of a website, engagement related activities and promotion of the route are also proposed.
3.2WEG has estimated that c. £10 - £15K funding is required to support the delivery of this work, alongside its volunteer workforce.
3.3It is proposed that the request is supported and that this will be funded from an additional allocation of £15k from the Environmental Sustainability reserve.
3.4Release of funding will be dependent on approval by the Council of the design and specification, and evidence of relevant expenditure.
Alternative options considered
4.1The alternative options are to not support the scheme or to allocate a lesser or greater amount.
4.2It is proposed that £15k provides an appropriate level of support to enable the project to succeed.
5 Implications
5.1Financial and Budgetary Implications The Environmental Sustainability reserve was set at £100k in 2021/22, to support delivery of the Council’s Environmental Sustainability Strategy. Commitment against this budget is as follows:
Project Allocation Status Decision date Community Grants £20k Approved(spent) July 2021 Biodiversity management plans £20k Approved November (Council land, Waterway corridors) 2021 Community Grants £20k Proposed July 22 SMG solar PV Outline Business Case £20k Proposed July 22
Wild about Worcester £15k Proposed July 22 Environmental Summit £5k Proposed July 22 Total £100k - -
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.