That the Committee agree to: 1. note the scheme of works to be delivered at in line with funding approved by Policy and Resources Committee in September 2020; 2. the proposal for the delivery of additional works at the site (as outlined within this report), that would require £30,000 capital investment; 3. the additional work as set out within the report and recommend to Council an amendment to the capital programme of £30,000; and 4. delegate authority to the Corporate Director - Operations, Homes and Communities in consultation with the Chair and Vice-Chair of Committee, to agree any final change in proposals within the existing budget, should the findings of any ecological assessment and habitat survey limit the additional works as outlined within the report.
Word for word from the decision Worcester published for this meeting.Source: committee.worcester.gov.uk
1.1Notes the scheme of works to be delivered at Meco Memorial Nature Park in line with funding approved by Policy and Resources Committee in September 2020.
1.2Consider a proposal for the delivery of additional works at the site (as outlined within this report), that would require £30,000 capital investment.
1.3Subject to approval of the additional work as set out within this report, recommend to Council an amendment to the capital programme of £30,000.
1.4Subject to approval by Council as outlined in recommendation 1.3, delegates authority to the Corporate Director - Operations, Homes and Communities in consultation with the Chair and Vice-Chair of Committee, to agree any final change in proposals within the existing budget, should the findings of any ecological assessment and habitat survey limit the additional works as outlined within this report.
Background
2.1At Council on 16th July 2019 a motion was presented to the meeting calling on the City Council to support the creation of a “Park of Peace” in memory of those killed in a bombing raid on the Meco Works during World War 2.
2.2The park would be established on retained land between Sanctuary Close and Hopton Street adjacent to a housing development (see plan and photographs in Appendix 1 & 2) and include recreation facilities for the wellbeing of residents. The motion was supported and approved, and officers were tasked with taking this project forward.
2.3The City’s Landscape Consultant was commissioned to design a scheme in consultation with Ward Members and residents. Originally the scheme was going to include a memorial area to commemorate the victims, seating, a community orchard, pathways, fencing, a boardwalk over wetland, a small kickabout area, and interpretation boards. The cost was assessed during 2020 at £30,000.
2.4A report was duly presented to Policy and Resources Committee on 8th September 2020 with two recommendations; 1) authorising the acceptance of £12,925 from Platform Housing as a contribution towards the park, and 2) for Council to add an additional £17,075 to the Capital Programme in 2020-21. 2.5 As part of this report to Policy & Resources Committee, it was confirmed that ‘Divisional County Councillor’ funding would be used for the design, manufacture and installation of a memorial sculpture.
2.6In March 2021, a s106 Deed of Variation associated with the Platform housing development was agreed which specified the sum of £13,000 as the contribution to the park. This was paid in August 2021. The sum of £17,000 was brought forward to the Capital Programme for 2021/22.
2.7A landscape architect was procured during Autumn 2021 and commenced design work in January 2022. Discussions commenced with Worcestershire County Council with a view to improving the Public Right of Way (PROW) running along the southern boundary of the park.
2.8The first drawings and specification for the improvements were made available in March 2022 with a proposal to phase landscaping works and seasonal planting from Summer 2022 to Spring 2023. The final version of the scheme documentation was available in May 2022.
2.9This specified the improvements as; a memorial area with sculpture, seating and interpretation board, an orchard, a picnic area, additional seating by a path, timber fencing, a pedestrian gate, a connection to a boardwalk with steps across a wetland area and park signage.
2.10In addition, improvements to the ecology of the site were proposed including hibernaculum, wildflower areas, hedgerows, native shrub planting, and improving biodiversity associated with the wetland. Some targeted removal of excess vegetation would also be required to allow for better pedestrian access and establish the new planting.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.