That the Committee agree to: 1. note the Budgets for the various services identified for 2024/25; and 2. note the progress made in delivering the projects included in the City Plan and City Delivery Fund that are relevant to this Committee and confirms the programme of work resourced.
Word for word from the decision Worcester published for this meeting.Source: committee.worcester.gov.uk
1.1That the Committee notes the Budgets for the various services identified for 2023/24; and
1.2That the Committee notes the progress made in delivering the projects included in the City Plan and City Delivery Fund that are relevant to this Committee and confirms the programme of work resourced.
Background
2.1The summary budgets for 2023/24 were approved by Full Council on 21 February 2023 and published in the annual Budget Book.
2.2The transition of the budgets from 2021/22 through to 2023/24 and the detailed budgets for each of the Council’s services relevant to this committee, covering both income and expenditure, is shown in Appendix 1.
2.3The Council also produces a Medium Term Financial Plan (MTFP) for the next 5 years setting out the high level pressures and opportunities that are likely to need to be addressed. Revenue and capital spending decisions made during each budget cycle feed into the MTFP and determine the level of reserves that the Council needs to ensure that services can be sustained in future.
3. Review of Service Budgets
3.1Members are asked to review the existing budget for each service and consider whether it remains appropriate for the required level of service delivery.
3.2Members are invited to submit suggestions of potential service improvements and/or re-prioritisation of budgets in order to continue to achieve service objectives and to deliver the relevant aims of the City Plan.
3.3Given that the Council faces a reduction in its future funding, this exercise is likely to result in a reduction or reallocation of resources rather than an increase in the net budget available.
3.4The MTFP indicates a budget gap which needs to be addressed so that the Council can continue to hold sufficient reserves to meet future needs. A Savings Plan has therefore been initiated and a number of areas identified for cost reduction and/or income improvement. In some cases this has affected service delivery and member approval has therefore been obtained. A summary of the changes is shown below. The budget changes relevant to this committee include:
• The budget approved in February 2023 include financial support towards the significant increase in energy costs borne by the council’s leisure services operator. It now appears that the full support will not be needed and there is an estimated saving of £190k; • Worcester Show – from 2024 an admission charge of £2 is to be introduced, generating income of an estimated £26.8k. The expenditure budget for the show has also not been fully used and is therefore being reduced by £14k; • Allotments – the fees charged to allotment holders are to be increased to reduce the subsidy applied to this service. This is to be a phased increase and in 2025/25 will generate additional income of £14.1k; • HMO licences – an increase in the number of HMO’s in the city gives rise to additional licence income of £10k p.a.; • Community grants are to be reduced over the next three years, with the saving in 2024/25 being £29k; • The Council’s temporary accommodation at Oldbury Road is rented from Platform Housing and a rent reduction of £7k has been agreed.
4. Projects and Capital Expenditure
4.1In a separate report to this committee meeting, Members have received a quarterly progress report on the various projects aligned to this committee. In addition, the 2023/24 Quarter 2 year-end forecast Capital Programme is shown on Appendix 2 and the 2023-2026 Capital programme approved as part of the Budget in February 2023 is shown in Appendix 3.
4.2Members are asked to consider whether the current projects are still appropriate for each service and whether there are any further needs that require addressing. This should include phasing the projects across the full 5-year term of the MTFP based on the need and importance of each one.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Annual Disabled Facilities Grant UpdateThat the Committee agree to: 1. note the contents of this update report and in particular delivery of Disabled Facili...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.