That the Committee agree to note: 1. progress in delivery of the Environmental Sustainability Strategy Action Plan; and 2. the receipt of grant awards for capital works to support decarbonisation of leisure and bereavement services, and to investigate electrification of the Sixways depot.
Word for word from the decision Worcester published for this meeting.Source: committee.worcester.gov.uk
1. That Members note progress in delivery of the environmental sustainability strategy action plan; and
1.1That Members note the receipt of grant awards for capital works to support decarbonisation of leisure and bereavement services, and to investigate electrification of the Sixways depot.
2. Introduction
2.1This report includes the twice-yearly update on the progress to deliver the Environmental Sustainability Strategy Action Plan 2022-24, following the last update to this Committee in November 2023.
2.2A summary of the activity under each theme of the Strategy is provided in report sections 6-12 and an action-by-action update is provided in Appendix 1.
Background
3.1Following the declaration of the climate emergency in July 2019, the Environmental Sustainability Strategy for the City of Worcester was approved by this Committee in October 2020.
3.2This Committee approved the first Action Plan for the delivery of the strategy in March 2021, and the Action Plan for the second phase of delivery of the strategy was approved in November 2022.
3.3In order to ensure effective governance of the strategy and associated action plan, it was agreed that this committee would receive progress reports on the delivery of the action plan twice yearly.
3.4Alongside the declaration of a climate emergency, the Council pledged to work towards the city becoming carbon neutral by 2030.
3.5The Environmental Sustainability Strategy was written and approved by Council in 2020 and was to be refreshed three years after this. Work on this refresh has begun and it is expected an updated Strategy will be brought to this Committee in the Autumn. 3.6 The planned refresh of the strategy will give the council an opportunity to revisit our strategic objectives and policies and strengthen areas of the strategy, for example in relation to climate adaptation and climate risk.
3.7The refreshing of the strategy will be followed by the development of a new action plan. Each action plan covers a two-year period although some actions will be carried over if they have a longer duration.
4. Environmental Sustainability Enabling Reserve
4.1In April 2023, the Environmental Sustainability enabling reserve was refreshed following a recommendation from this Committee to the Policy and Resources Committee, with an allocation of £150k from reserves to this fund, which had £20k remaining unallocated.
4.2In the progress report update to this Committee in November 2023, it was reported that £5k had been approved as match funding for the Heat Networks Detailed Project Development Study, and the remaining balance was unallocated.
4.3In January 2024, this Committee approved up to £40k towards the necessary work to identify the feasibility and cost of depot electrification, required before the fleet can be transitioned to electric vehicle alternatives. In addition, £50k was approved to support the creation of a biodiversity officer post for two years.
4.4Currently the balance of the enabling reserve is £74k, comprised of unallocated funding and underspends on projects which have completed.
5. Progress of actions within the Environmental Sustainability Action Plan
5.1Details for each action within the action plan are provided in the performance report at Appendix 1. The following sections of this report provide a commentary on a theme-by-theme basis.
5.2On this action plan 19 actions are now complete with 19 in progress.
5.3One of the actions in progress is overdue; this is the action to install electric vehicle chargepoints at King Street and Tallow Hill car park. The points at King Street went live in November, the installations at Tallow Hill had been delayed due to archaeological investigations but works are now substantially complete, and the chargers will be live by the end of June.
6. Environmental Sustainability Strategy Theme: Carbon Neutral City Council
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.