CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Worcester City Council
Health and Wellbeing Committee, Monday 3 February 2025 at 7.00pm

Progress Update on the Delivery of the Active Travel Action Plan

Agreed Committee 2 papers

Health and Wellbeing Committee agreed this item on Monday 3 February 2025. Below is the council's own wording, with the papers it was decided on.

Item35

Resolved

That the Committee agree to note the contents of the report.
Word for word from the decision Worcester published for this meeting. Source: committee.worcester.gov.uk

Follow this further

Built from Worcester's papers

What the report saysPro

Report to Health and Wellbeing Committee, 5 pages

Recommendation

1.1That the Committee notes the contents of this report.

2. Introduction

2.1This report sets out the twice-yearly update on the progress to deliver the Active Travel Action Plan 2023-25. A summary of the internal and external actions is provided in section 4 of the report and an action-by-action update is provided in Appendix 1.

2.2This report contains an update on Towns Fund projects relating to active travel, including the Beryl Bikes scheme and the introduction of secure cycle parking.

Background

3.1The two-year Active Travel Action Plan was approved by this committee in June 2023. The plan includes actions internal to the Council and external actions, where the Council can influence, directly or indirectly, the transition to active travel by residents, visitors and those who work in the city.

3.2A cross-party member steering group was established to oversee the development of the Active Travel Action Plan and the subsequent progression of the actions within the plan. Membership of this group has been updated to reflect the changes to membership of this committee and will meet again following this committee cycle.

3.3In order to ensure effective governance of the action plan it was agreed that this committee would receive progress reports on the delivery of the action plan twice yearly.

3.4The current action plan is due to be completed in the summer of 2025. A second iteration of the action plan will be developed with the member steering group in the coming months and brought to committee for approval in the summer.

3.5Reflecting the approach of the current action plan, the next iteration will look at both internal and external changes within the remit of the Council.

4. Progress of Actions in the Active Travel Action Plan

4.1Details for each action within the action plan are provided in the performance report in Appendix 1. The following sections of this report provide a commentary on the progress made to date. 4.2 As the action plan is due to close in the summer of 2025, the majority of actions have now been completed with any subsequent ongoing work now incorporated as business-as-usual activity.

4.3There are two projects that have not been completed due to a change in requirements and circumstances within the council. It has been agreed with the Chair and Vice Chair of this Committee to close these actions.

Internal

4.4Internal actions are focused on increasing active travel amongst staff for both business travel and commuting. The actions include continuing improvements to cycle facilities for staff and the promotion of ongoing active travel related schemes and initiatives. Some of these initiatives are the Cycle to Work scheme and the Sustainability and Health in Future Transport (SHIFT) scheme.

Closed actions

4.4.1 The Council investigated procurement of an e-cargo bike for operational use however were unable to identify sufficient demand to justify the expenditure. Officers will investigate the potential for the Beryl Bikes scheme to include cargo bikes.

4.4.2 The action plan included an action to allow staff to rent the Council’s e-bikes for the weekend to trial the use of an e-bike within their local area. Following the launch of the Beryl Bikes scheme and damage to staff e-bikes this action is not an effective use of resources.

Completed Actions

4.4.3 A number of Bikeability sessions have taken place with 10 staff members having completed the training. A further session is planned for February and has been extended to elected members. Sessions will continue to take place as and when there is sufficient demand from staff and members.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Active Travel Action Plan Update H&W Feb 25Appendix 1 6 pages Download
PDF
Progress Update on the Delivery of the Active Travel Action PlanReport 5 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Worcester

Search all
  1. Progress Update on the Delivery of the Active Travel Action PlanThis decision
  2. Progress Update on the Delivery of the Active Travel Action PlanAgreed
  3. Progress Update on the Delivery of the Active Travel Action PlanNoted
  4. Progress Update on the Delivery of the Rough Sleeper Death Review Report RecommendationsNoted
  5. Progress Update on the Delivery of the Rough Sleeper Death Review Report RecommendationsNoted

More from Worcester Health and Wellbeing Committee

All decisions
MeetingDecisionOutcome
3 Feb 2025 MinutesThat the minutes of the meeting held on 21 st October 2024 be approved as a correct record and signed by the Chair. Approved Open
3 Feb 2025 Quarter 3 Performance Report for 2024/25That the Committee agree to note the Council’s quarter 3 performance for 2024/25. Agreed Open
3 Feb 2025 Setting of the Budget for 2025/26 and Medium Term Financial Plan to 2029/30That the Committee agree to note the proposed Budgets for the various services identified for 2025/26. Agreed Open
3 Feb 2025 Worcester City Discretionary Welfare Assistance Scheme (DWAS)That the Committee agree to: 1. note the content of the report; and 2. delegate authority to the Chair & Vice-Chair o... Agreed Open
21 Oct 2024 Minutesthat the minutes of the meeting held on 29 th July 2024 be approved as a correct record and signed by the Chair. Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies