That the Committee agree to: 1. note the contents of the report; 2. note the feasibility and investigation work being undertaken to identify locations for up to 6 homeless pods in the city; and 3. note that a further report will be presented to this Committee in Summer 2025, updating on work undertaken to explore direct delivery opportunities for the Council in respect of affordable housing.
Word for word from the decision Worcester published for this meeting.Source: committee.worcester.gov.uk
1.2Notes the feasibility and investigation work being undertaken to identify locations for up to 6 homeless pods in the city; and
1.3Notes that a further report will be presented to this Committee in Summer 2025 updating on work undertaken to explore direct delivery opportunities for the Council in respect of affordable housing.
Background
2.1On 8t November 2023, this Committee received its first update report, following the adoption of the Worcester City Housing Enabling Strategy and Delivery Plan.
2.2It is recognised that the demand and need for affordable housing in Worcester continues to increase whilst the supply is not increasing at the same rate. To redress this imbalance in the city, a strategic and co-ordinated approach is required to maximise opportunities to deliver more affordable housing.
2.3The Housing Enabling Strategy sets this strategic framework and focusses on the actions required to support the delivery of additional affordable housing in Worcester.
2.4It compliments other regional strategies including the Worcestershire Homelessness and Rough Sleeper Strategy and Worcestershire Housing Strategy. It sets out 8 strategic goals which are set out in table below. The Delivery Plan is a dynamic document that sets the actions required to deliver the strategy. Some of these actions may be time limited and some on-going.
Strategic Goals
Maximise affordable housing provision across all development Goal 1 sites where there is a residential use.
Put in place a strategic housing and enabling function that Goal 2 supports the objectives of the HES. Ensure that corporate objectives and planning policy and practice Goal 3 support the delivery of new affordable homes.
Build strong relationships with key partners leading to deliverable Goal 4 and quantifiable outcomes.
Maximise resources available from the public and private sectors Goal 5 to investment in affordable housing.
Promote and raise awareness of the benefits of affordable Goal 6 housing in the wider social and economic context.
Shape and action the Council’s engagement in land promotion Goal 7 activities.
Establish the Council’s appetite and explore the opportunities for Goal 8 joint venture working.
3. Information
Delivery update and actions for consideration since the November 2024 report
3.1The Council has now let two properties under the Local Authority Housing Fund (LAHF) round 1 scheme.
3.2The Council is close to completing on a third property and is in Conveyance with a fourth under LAHF round 3 programme. This leaves a further property to acquire under the original LAHF3 allocation in the next financial year. Officers have also just secured a further £509,000 under LAHF which will support the acquisition of an additional 4 properties in 2025/26.
3.3Officers have been working with an external partner to consider opportunities for an affordable housing scheme on council owned land. A selected opportunity will progress through due diligence and, if feasible, a draft business & project plan will be presented to this Committee in Summer 2025 with further detail.
3.4Officers have been considering options to reduce rough sleeping in particular where there is a high exposure to risk for the homeless households, for example where the night-time economy is most active.
3.5Officers are considering active siting of suitable temporary provision such as sleeping pods or homeless pods and will progress through feasibility investigations, and local consultation, with a view to secure temporary permissions as required.
Progress against Goals
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Annual Disabled Facilities Grant UpdateThat the Committee agree to: 1. note the contents of this update report and in particular delivery of Disabled Facili...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.