Budget Proposals - 2026/27

Noted Committee 1 paper

AI summaryWorcester City Council Environment Committee backs three budget proposals for 2026/27 including a new £39 black bin replacement charge and a 5% rise in off-street car parking fees, recommending them to Policy and Resources Committee.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedThree savings proposals noted and forwarded for approval
Money£147,000 stated total annual savingsPer paragraph 5.1; table line items total 156 in £000s
What happens nextPolicy and Resources Committee then CouncilCouncil budget setting on 24th February 2026
Who it affectsNot stated

What was decided

The Committee noted the report and its Appendix 1 proposals, namely a £39 charge for replacement black bins, a 5% increase in off-street car parking charges, and parking charges at Diglis Playing Fields and Waterworks Road car parks subject to statutory consultation. Report P1, P3

The Committee recommended the three budget proposals to Policy and Resources Committee for consideration by Council as part of budget setting for 2026/27. Report 1.2

Why

Following the Local Government Financial Settlement, the council must close a £639,000 budget gap to set a balanced budget for 2026/27, with a £1.6m gap forecast for 2027/28. Report 2.1

The three proposals form part of a £400,000 savings plan for 2026/27, contributing over a third of the planned savings, with the balance of the gap met through the Extended Producer Responsibility grant. Report 2.3, P34

Officers assessed demand, income and benchmarking data and concluded these measures would not damage the quality or extent of services offered. Report 2.9, P37

What happens next

Policy and Resources Committee will consider the proposals, with full Council approval sought on 24th February 2026. Report 1.2

If approved, statutory consultation on the new car parking charges at Diglis Playing Fields and Waterworks Road would be undertaken after February Council, with a Variation Order to the off-street parking order and support required from Worcestershire County Council Highways. Report 2.15, P94, P95

Subject to approval, the new bin charge and 5% car park increase would take effect from 1st April 2026, with 21 days' notice given via the local press and signage. Report P49, P67

The money

  • £639,000 Budget gap to close for a balanced 2026/27 budget Report 2.1, 5.1
  • £1.6m Forecast budget gap for 2027/28 Report 2.1
  • £400,000 2026/27 savings plan target Report 2.3, P34
  • £147,000 Total estimated annual savings from the three proposals (per paragraph 5.1) Report 5.1
  • 57 Full year saving (£000s) from black bin replacement charge Report P30
  • 80 Full year saving (£000s) from 5% off-street car park increase Report P31
  • 19 Full year saving (£000s) from charges at Diglis and Waterworks Road Report P32
  • 156 Table total of full year savings (£000s) Report P33
  • £39.00 Proposed charge for replacement black wheeled bin Report 2.6, P49
  • £29.000 Concessionary bin charge for residents on Council Tax Support (as written in report) Report 2.6
  • £57,000 Annual savings expected from the black bin charge Report 2.7, 1.12
  • £80,000 Additional annual income from a 5% off-street car park increase Report 2.10
  • £19,000 Estimated additional annual income from Diglis and Waterworks Road Report 2.14
  • £83,000 Average annual council spend on replacement waste and recycling bins Report 1.3
  • 2,900 Average number of replacement bins each year Report 1.3
  • £79,660 Additional income from 5% car park increase on existing demand Report 2.14
  • £119,490 3% inflation factor previously assumed on car park income for 2026/27 Report 2.11

Options considered

  • Rejected: Bin replacement charge of £25 with no concessions. Not recommended; set out in Appendix 1 options table Report P59
  • Rejected: Bin replacement charge of £39 with no concessions. Not recommended; set out in Appendix 1 options table Report P60
  • Rejected: Bin charge of £25 with 25% concession (£18.50). Not recommended; set out in Appendix 1 options table Report P61
  • Chosen: Bin charge of £39 with 25% concession (£29.00) for Council Tax Support recipients. Recovers full processing cost of around £38 per bin and provides a concession consistent with other council services Report P62, 1.11, 1.4
  • Chosen: Apply 5% increase to all off-street car park charges for 2026/27. Benchmarking and demand data show no impact on demand; income higher than the 3% assumed in the Medium Term Financial Plan Report P67, 2.9, 2.10, 2.11
  • Chosen: Introduce Green Zone parking charges at Diglis Playing Fields and Waterworks Road car parks. Removes anomaly of free council car parks, recovers maintenance costs, and responds to anti-social behaviour at Waterworks Road Report 2.13, 2.14, P85, P89

Implications

  • Financial: Total estimated annual savings from the three proposals is £147,000 (per paragraph 5.1), against a £400,000 savings plan target and a £639,000 forecast deficit; the table in the report shows full year savings of 57, 80 and 19 (£000s) totalling 156 (£000s). Report 5.1, P30, P31, P32, P33, P34
  • Legal: Legal and governance implications will be considered, including ensuring required consultation on amendments to the off-street car parking order via a Variation Order. Report 5.2, 2.15, P94
  • Equalities: The bin charge includes a 25% concession for residents on Council Tax Support and exemptions for damage caused by the council, theft or vandalism, and exceptional circumstances; the new car parks would be Green Zone and offer seasonal permits. Report 2.6, P12, P66, 5.5, 5.8
  • Risk: Not approving the proposals would require officers to identify alternative savings, likely impacting front-line services; car park charges could disproportionately affect low-income households reliant on a car. Report 4.2, 5.3, 5.8
  • Climate: Introducing parking charges is expected to contribute in some part to reducing congestion and emissions and encouraging modal shift; capital improvements to the car parks will improve their look and feel. Report P44, P45
  • Other: No corporate/policy, human resources, or health and safety implications are identified in the report. Report 5.4, 5.6, 5.7

Who and where

  • Residents across all wards needing replacement black wheeled bins, including those on Council Tax Support eligible for a concession Report P46, 2.6, 5.5
  • Users of the 14 council off-street car parks facing a 5% tariff increase from 1st April 2026 Report P67, 2.1
  • Users of Diglis Playing Fields Car Park (Waverley Street) and Waterworks Road Car Park, served by Cherry Orchard Nature Reserve, Diglis Playing Fields, Diglis Basin and Waterside, Riverside, Pitchcroft and Gheluvelt Park Report 2.11, 2.13, P86, P87
  • Worcestershire County Council Highways, whose support is required before charges can be introduced at the two new sites Report 2.15, P95

Timeline

  • 27th January 2026: Environment Committee considers the budget proposals Report 2.2
  • After February 2026 Council: Statutory consultation on new parking charges at Diglis Playing Fields and Waterworks Road car parks Report 2.15, P94
  • 24th February 2026: Council approval sought as part of budget setting for 2026/27
  • 1st April 2026: Proposed start date for the £39 black bin replacement charge and 5% off-street car park increase Report P49, P67
  • 21 days' notice period: Notice of car park charge changes given via local press and signage as a minor variation to the off-street parking order

Plain English for the jargon

  • MTFP: Medium Term Financial Plan, the council's multi-year budget and savings planning document
  • EPR grant: Extended Producer Responsibility grant, an un-ringfenced government funding stream from packaging producers
  • Park Mark: A national police-backed accreditation for safer, well-managed car parks
  • RINGO: Cashless parking payment app and service used by the council
  • Green Zone: The lowest tariff band of Worcester City Council's off-street car parks
  • Variation Order: A legal amendment to the council's off-street car parking order to introduce or change charges
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item29

Resolved

That The Committee: 1. note the contents of the report, and in particular the budget proposals for 2026/27 included at Appendix 1, namely – a) Introduction of a charging policy for replacement black wheeled bins; b) Increase in off-street car parking charges; c) Introduction of parking charges at Diglis Playing Fields Car Park and Waterworks Road Car Park, subject to statutory consultation; and 2. recommends to Policy and Resources Committee the approval of the budget proposals set out in recommendation 1, for consideration by Council as part of budget setting for 2026/27.
Word for word from the decision Worcester published for this meeting. Source: committee.worcester.gov.uk

Follow this further

Built from Worcester's papers

What the report saysPro

Report to Environment Committee, 11 pages

Recommendation

That the Committee:

1.1Note the contents of the report, and in particular the budget proposals for 2026/27 included at Appendix 1, namely –

a) Introduction of a charging policy for replacement black wheeled bins b) Increase in off-street car parking charges c) Introduction of parking charges at Diglis Playing Fields Car Park and Waterworks Road Car Park, subject to statutory consultation; and

1.2Recommends to Policy and Resources Committee the approval of the budget proposals set out at recommendation 1.1, for consideration by Council as part of budget setting for 2026/27.

Background

2.1Following the recent Government Local Government Financial Settlement, the budget gap the council is required to close to deliver a balanced budget for 2026/27 is £639,000. In 2027/28 the budget gap is forecast to be £1.6m.

2.2For further information on proposals to manage these budget gaps please refer to the Environment Committee agenda item ‘Medium Term Financial Plan (MTFP) Update’ to be presented on 27th January 2026.

2.3This report sets out at Appendix 1, three budget proposals that contribute over a third of the £400,000 intended to be delivered through the 2026/27 savings plan.

2.4The budget proposals relate to service areas that fall under the constitutional remit of the Environment Committee and are of a nature where it is deemed Committee approval is required ahead of (subject to approval) onward consideration by Policy & Resources Committee and Council.

2.5Full details on each of the proposals are included at Appendix 1 and a summary of the proposals is included below.

Black Bin Replacement Charge

2.6This proposal would seek to introduce a charge of £39.00 to cover the full costs of processing requests for replacement of a domestic residual waste (black) wheeled bin. A 25% concession would be in place for residents who are in receipt of Council Tax Support bringing the charge down to £29.000. The fee would be waived where the following criteria can be met

• A bin has fallen into (or been damaged by) the collection vehicle and the crew has confirmed this. • Where a bin has been stolen or vandalised • Where Exceptional Circumstances Policy applies (i.e. where service users meet the requirements for additional capacity) • Any other matter that is justified by a member of the Waste & Recycling Management Team.

2.7Subject to approval and inclusion within the council’s fees & charges for 2026/27, this proposal would deliver annual savings of around £57,000

Off-Street Car Parking Charge Increase

2.8As part of setting the budget for 2025/26 and casting the Medium-Term Financial Plan, a 3% increase in off-street car park charges had been assumed for future years.

2.9Having reviewed car parking demand data, income reports and benchmarking data it is considered that an additional increase can be applied without having any impact on demand.

2.10It is proposed to apply a 5% increase (not 3% as assumed within MTFP) to all off- street car park charges for 2026/27. Subject to approval and inclusion within the council’s fees & charges for 2026/27 this proposal would increase annual income by £80,000.

Introduction of car parking charges at Diglis Playing Fields Car Park (Waverley Street) and Waterworks Road Car Park

2.11Most car parks operated and maintained by the council have car parking charges in place. There are however anomalies to this including Diglis Playing Fields Car Park and Waterworks Road Car Park.

2.12Both these car parks are well used and require the council to cleanse and maintain them which comes at a cost. The car parks generate no revenue to cover these costs, whilst other car parks on the edge of the city centre have charges in place.

2.13The proposal would seek to introduce parking charges at both these locations making them ‘Green Zone’ car parks in line with Pitchcroft, Tallow Hill, Tybridge Street, and Croft Road.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Budget Proposals: 2026/27Report 11 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

12 of 12 attended
ZC
Councillor Zoe CooksonChair, present
AC
Councillor Andrew CrossCommittee Member, present
KH
Councillor Karen HolmesCommittee Member, present
NH
Councillor Naz HussainCommittee Member, present
AK
Councillor Alex KinnersleyCommittee Member, apologies, sent representative
KL
Councillor Karen LewingVice-Chair, present
AM
Councillor Alex MaceCommittee Member, present as substitute
JR
Councillor John RudgeCommittee Member, present
AS
Councillor Atif SadiqCommittee Member, present
AS
Councillor Adam ScottCommittee Member, present
SS
Councillor Sue SmithCommittee Member, present
PS
Councillor Paul SobczykCommittee Member, present

On this subject at Worcester

Search all
  1. Budget Proposals - 2026/27This decision
  2. Feedback Report from the Policy Committees on the Draft Budget ProposalsAgreed
  3. Feedback Report from the Place and Economic Development Sub-Committee on the Draft Budget ProposalsAgreed
  4. Feedback Report from the Environment Committee on the Draft Budget ProposalsAgreed
  5. Feedback Report from the Communities Committee on the Draft Budget ProposalsAgreed

More from Worcester Environment Committee

All decisions
MeetingDecisionOutcome
10 Mar 2026 MinutesThat the minutes of the meeting held on 27 th January 2026 be approved as a correct record and signed by the Chair. Approved Open
10 Mar 2026 Proposed Committee Scorecard for 2026/27That the committee agree the proposed content of the Environment Performance Scorecard for 2026/27. Agreed Open
10 Mar 2026 Parking and Environmental Enforcement Service UpdateThat the Committee note the contents of the report. Noted Open
27 Jan 2026 MinutesThat the minutes of the meeting held on 4 th November 2025 be approved as a correct record and signed by the Chair. Approved Open
27 Jan 2026 Medium Term Financial Plan (MTFP) UpdateThat the Committee note the update on the Medium-Term Financial Plan (MTFP) as detailed in Appendix 1. Noted Open