Review of the Shrub Hill Quarter Supplementary Planning Document
ApprovedCommittee2 papers
AI summaryWorcester City Council's Place and Economic Development Committee approved a revised Shrub Hill Quarter Supplementary Planning Document for a five-week public consultation starting at the end of March 2026, ahead of a government adoption deadline of end of June 2026.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedDraft SPD to go to five-week public consultation
MoneyNo significant financial implicationsCosts met from existing service budgets
What happens nextFive-week public consultationStarting at the end of March 2026
Who it affectsCathedral ward and Shrub Hill areaWill guide future planning decisions in the Quarter
What was decided
The Committee approved the draft Shrub Hill Quarter Supplementary Planning Document, as set out in appendix 1, for a five-week public consultation. Report 1.1
The Committee authorised the Head of Planning and Economic Development, in consultation with the Chair and Vice-Chair of the Place and Economic Development Committee, to make any necessary minor amendments to the draft SPD prior to publication. Report 1.2
Why
The South Worcestershire Development Plan Review is expected to be adopted in March 2026, replacing the current plan, so the SPD needs to be reviewed to remain up to date and continue to be a material consideration in planning decisions. Report 2.4, 2.6
Government has set a deadline of end of June 2026 for adoption of SPDs under the current plan making framework, leaving only a limited window to review the document. Report 4.1
Not reviewing and adopting the SPD risks it carrying reduced weight as a material consideration in planning decisions, which could lead to less favourable outcomes for the regeneration of the Shrub Hill area. Report 5.3
What happens next
A revised SPD document will be produced to reflect the changes identified in appendix 1 prior to consultation. Report 2.5
Officers will administer the public consultation, review responses and make any necessary amendments using existing resources, before seeking approval to adopt the SPD. Report 5.6
The five-week statutory public consultation is planned to begin at the end of March 2026. Report 3.1
Options considered
Chosen: Progress the revised Shrub Hill Quarter SPD to statutory public consultation. Required to meet the government deadline of end of June 2026 and keep the SPD as a material consideration Report 3.1, 4.1
Rejected: Not continue with the review of the SPD. Would risk missing the end of June 2026 adoption deadline and the SPD carrying reduced weight in planning decisions Report 4.1
Implications
Legal: The consultation on the SPD will meet the relevant legal and regulatory requirements for producing a Supplementary Planning Document, and production to date has followed the regulations. Report 5.2
Risk: Not reviewing and adopting the SPD risks the document carrying reduced weight as a material consideration in planning decisions, which could harm the wider regeneration of the Shrub Hill area. Report 5.3
Staffing: Officer time and input will be needed to administer the consultation, review responses and make amendments, carried out using existing resources. Report 5.6
Equalities: There are no equality implications relating to the review and implementation of this SPD. Report 5.5
Other: The regeneration of the Shrub Hill Quarter is expected to have significant social, environmental and economic implications through land use change and new housing and employment opportunities, with the SPD emphasising sustainable delivery.
Who and where
Cathedral ward Report P20
Residents, developers, landowners and potential investors in the Shrub Hill Quarter Report 2.2, 5.4
Applicants for planning applications in the Shrub Hill area Report 2.2, 5.3
Timeline
January 2024: Committee approved launching public and stakeholder consultation on a draft SPD for the Shrub Hill Quarter Report 2.1
September 2024: The original SPD was adopted by the Council Report 2.1
March 2026: The South Worcestershire Development Plan Review is expected to be adopted, replacing the current SWDP Report 2.4
End of March 2026: Statutory public consultation on the revised SPD planned to begin Report 3.1
2026-03-16: Place and Economic Development Committee approved the revised draft SPD for consultation Report 1.1
End of June 2026: Government deadline for adoption of SPDs under the current plan making framework Report 4.1
Plain English for the jargon
Supplementary Planning Document (SPD): A planning document that sits under a development plan and provides detailed guidance on how policies will be applied, considered as a material consideration in planning decisions.
SWDP 44/4 Shrub Hill Opportunity Zone: A policy in the South Worcestershire Development Plan 2016 covering the Shrub Hill area, which the original SPD was prepared to support.
SWDPR: The South Worcestershire Development Plan Review, expected to be adopted in March 2026 and to replace the current SWDP in its entirety.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item48
Resolved
That the Committee: 1. approves the draft Shrub Hill Quarter Supplementary Planning Document, as set out in appendix 1, for a five-week public consultation; and 2. authorises the Head of Planning and Economic Development, in consultation with Chair and Vice-Chair of Place and Economic Development Committee to make any necessary minor amendments to the draft Shrub Hill Quarter Supplementary Planning Document prior to publication.
Word for word from the decision Worcester published for this meeting.Source: committee.worcester.gov.uk
Report to Place and Economic Development Committee
Recommendation
That the Committee:
1.1Approves the draft Shrub Hill Quarter Supplementary Planning Document, as set out in appendix 1, for a five-week public consultation; and
1.2Authorises the Head of Planning and Economic Development, in consultation with Chair and Vice-Chair of Place and Economic Development Committee to make any necessary minor amendments to the draft Shrub Hill Quarter Supplementary Planning Document prior to publication.
Background
2.1In January 2024, Committee approved the launching of public and stakeholder consultation on a draft Supplementary Planning Document (SPD) for the Shrub Hill Quarter. The SPD was well received and was adopted by the Council in September 2024.
2.2The SPD is based on earlier master planning work and an investigation into the constraints and opportunities for development in the Quarter. It sets out a framework for future planning decisions setting standards for the quality of development and design, provides confidence to developers and landowners and has increased the prominence of the programme with potential investors and government agencies.
2.3The SPD was prepared to sit under policy SWDP 44/4 Shrub Hill Opportunity Zone of the South Worcestershire Development Plan, 2016 (SWDP).
2.4The South Worcestershire Development Plan Review (SWDPR) is expected to be adopted in March 2026 which will replace in its entirety the SWDP. Therefore, the SPD needs to be reviewed to ensure it remains up to date and can be considered as a material consideration in the determination of planning applications.
2.5The document has been reviewed, updates required have been identified and are shown in appendix 1. Prior to consultation, a revised SPD document will be produced to reflect these changes.
2.6The updates focus on updating policy references and updating information to reflect the latest position regarding the regeneration of the Shrub Hill area. 3. Preferred Option
3.1The preferred option is to progress the revised Shrub Hill Quarter SPD to statutory public consultation, beginning at the end of March 2026.
Alternative options considered
4.1The Council could decide not to continue with the review of the SPD, however a deadline for adoption of SPDs under the current plan making framework has been set by Government of the end of June 2026. There is therefore only a limited window of opportunity to review the SPD to ensure that it can continue to be a material consideration in decision making on planning applications.
5. Implications
5.1Financial and Budgetary Implications There are no significant financial and/or budgetary implications for the council relating to the review of the SPD. The costs associated with the preparation of the SPD are being met from existing service budgets.
5.2Legal and Governance Implications The consultation on the SPD will meet the relevant legal and regulatory requirements for the production of a Supplementary Planning Document. The production of the SPD to date has been undertaken in accordance with the regulations for producing an SPD.
5.3Risk Implications Not reviewing and adopting the SPD risks the SPD carrying reduced weight as a material consideration in the assessment and decision making of planning applications, which could ultimately lead to less favourable outcomes of the wider regeneration of the Shrub Hill area.
5.4Corporate/Policy Implications The City Plan has the theme ‘a city where everyone can prosper’. Under this theme the Shrub Hill Quarter Supplementary Planning Document is identified as one way the City Council will work to achieve this aim. The revised SPD will ensure the City Council are able to continue to work to meet this theme.
5.5Equality Implications There are no equality implications relating to the review and implementation of this SPD.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Place and Economic Development Committee at Worcester and we tell you when its next papers are published, before the meeting rather than after it.
Proposed Committee Scorecard for 2026/27That the Committee agree the proposed content of the Place and Economic Development Performance Scorecard for 2026/27...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.