Homes and Environment Scrutiny Committee agreed this item on Wednesday 13 April 2016. Below is the council's own wording, with the papers it was decided on.
AGREED – ( i ) That the improvement in the overall condition of Wrexham’s classified A, B and C road network be noted. (ii) That the need to optimise the programming and timing of planned highway improvement works to maximise best value be acknowledged. (iii) That the effective use of powers afforded to the Highway Authority to better protect investment in the road network from the activities of statutory undertakers be acknowledged. (iv) That concerns regarding the level of investment available for the improvement of street lighting assets and highways and the increased demand this places on these services be noted. (v) That a further update report be presented to this Committee in 6 months on the continued development of the HAMP, to include the performance of the ... view the full minutes text for item 53.
Word for word from the decision Wrexham published for this meeting.Source: moderngov.wrexham.gov.uk
Report to Homes and Environment Scrutiny Committee
Purpose of the report
To present for Members consideration and support the work undertaken on the continued development and implementation of the Highways Asset Management Plan.
Executive summary
2.1In considering the outcomes of the work undertaken as part of a national collaboration project on the development of long term asset management investment strategies, Members have previously supported a number of important operational changes to the Council’s approach to the planned maintenance of the highway network in Wrexham, including the reprioritisation of budgets to maximise investment in the major asset groups.
2.2Examination of recent highway condition data has identified that, despite pressure on limited resources, highway condition levels in recent years have not only been sustained but improved. The number of roads classed as being in poor condition has fallen across the A, B and C classified network.
2.3Whilst acknowledging the positive trend in the improvement of the condition of the network, the availability of funding for future highway condition improvements is limited. It is therefore important that future improvements works are programmed and delivered at optimum times of the year to provide best value and make effective use of powers afforded to the Highways Authority to protect investment in the network.
2.4Welsh Government ‘Invest to Save’ funding of £900,000 has been awarded to WCBC to upgrade 2303 existing street lighting units to LED. Estimated savings from reductions in maintenance, carbon tax and energy costs will be used to fund repayments over the next 6 years. Whilst positive, without additional and sustained investment in the Council’s street lighting assets, the number of faults will continue to grow, placing significant and unsustainable demands of the street lighting service.
Recommendations
(i) Members note the improvement in the overall condition of Wrexham’s classified A, B and C road network.
(ii) Members acknowledge and support the need to optimise the programming and timing of planned highway improvement works to maximise best value.
(iii) Members acknowledge and support effective use of powers afforded to the Highway Authority better to protect investment in the road network from the activities of statutory undertakers.
(iv) Members acknowledge concerns regarding the level of investment available for the improvement of street lighting assets and the increased demands this places on the street lighting service.
REASONS FOR RECOMMENDATIONS Wrexham County Borough Council is a Highway Authority and, as such, has a statutory duty to maintain and improve the transport network. The continued development and implementation of the Highways Asset Management Plan enables the Council to take a strategic approach in ensuring that limited resources are directed to areas of need, balancing competing demands and risks in a way that recognises the needs of customers.
4. BACKGROUND INFORMATION
Introduction 4.1 Wrexham County Borough Council as a Highways Authority has a statutory duty under the Highways Act 1980 to maintain the network and ensure that it is fit for purpose. This is undertaken despite increasing pressures on limited resources, ageing infrastructure and increased demands and expectations from the public. Asset management is a strategic approach to enable and inform decisions on the levels of service that can be provided within the limited resources available. The adoption and application of good asset management principles helps identify best use of resources in the management, operation and enhancement of highway infrastructure to best meet the needs of the travelling public.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Homes and Environment Scrutiny Committee at Wrexham and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.