Customers, Performance, Resources and Governance Scrutiny Committee agreed this item on Wednesday 26 July 2017. Below is the council's own wording, with the papers it was decided on.
AGREED – (i) That the proposed changes to the reporting mechanism for contract overspends as set out in paragraphs 4.2 – 4.5 of the report (HF/72/2017S) be approved. (ii) That the Contract Overspends report currently scheduled for the October 2017 meeting be deferred to the November 2017 meeting. (iii) That the as attached at Appendix 1 to the report (HF/72/2017S) be agreed, subject to (i) and (ii) above.
Word for word from the decision Wrexham published for this meeting.Source: moderngov.wrexham.gov.uk
Report to Customers, Performance, Resources and Governance Scrutiny Committee
Purpose of the report
To assist the Committee in considering and agreeing its work programme.
Executive summary
The proposed work programme, for consideration up until July 2018 is attached at Appendix 2.
Recommendations
3.1Members consider the Work Programme attached at Appendix 2.
3.2Members consider the proposed changes to the reporting mechanism for contract overspends as set out at paragraphs 4.2 - 4.5.
Reasons for recommendations
To enable the Committee to develop an outcome-focused work programme for the next 12 months and beyond. 4. BACKGROUND INFORMATION
4.1At its Meeting on 28 June 2017 the Committee made the following changes to its forward work programme.
That the report in respect of the WAO Corporate Assessment also contain details of the WAO Good Governance When Determining Significant Service Changes guidance.
That the Corporate Health and Safety Action Plan be submitted to the September meeting.
That a report in respect of outturn variances in respect of Waste Management and School Transport be considered at the October 2017 meeting.
Customer Care Performance April 2016 – March 2017
That the results of the customer focus Wales review be fed back to the committee with details of any related resource issues.
That there be a presentation of digital customer services to the committee when they consider their item in respect of the ICT and Digital Strategy.
That further detail be included in future reports to ascertain reasons for any reduction in the volume of telephone contacts.
4.2The current reporting arrangements are as follows and only contract overspends for capital or Housing Revenue Account projects are included in the report using criteria a) and b) below.
a) Over 5% with more than a Detailed report every six months to £10k overspend CPRG SC b) Over 20% subject to a Detailed report to the next meeting of minimum of £30k CPRSC overspend c) Over 5% but less than a Summary report every six months to 10k overspend CPRG SC
4.3It is proposed to amend criteria c as follows :
c) Increases in order value Summary report every six months Over 10% but more than a 5k to CPRG SC overspend More detailed report showing individual orders, variances and reasons for increase.
4.4This will apply for other contracts where individual orders for work are placed such as the highways maintenance and council house voids frameworks etc. These will be shown in summary format to allow Members to scrutinise the number of jobs where there has been an increase over and above the original order value detailing the number of overspends with more detail being provided where the increase is more than 10% subject to a minimum overspend of £5,000. This is to reflect the fact that there can often be unforeseen work that cannot be identified at the initial order / specification stage without intrusive surveys being carried out.
4.5If Members support this amendment it is suggested that the report be considered at the November 2017 meeting.
5. IMPLICATIONS
5.1Policy Framework – The terms of reference of this Committee are aligned to the Council’s Strategic Theme ‘Organisation’ as set out in the Council Plan. Any topics identified will contributed to the following aims as stated in the Committees terms of reference “To ensure that we are customer focussed and innovative, soundly organised, resourced and governed, in order to deliver the best possible outcomes for the people of Wrexham.“
5.2Budget – There are no budget implications arising from this report.
5.3Legal – There are no legal implications arising from this report.
5.4Staffing – There are no staffing issues arising out of the report, but Officer resource will be required to support the preparation of information for Scrutiny Committee consideration
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Customers, Performance, Resources and Governance Scrutiny Committee at Wrexham and we tell you when its next papers are published, before the meeting rather than after it.
ICT and Digital Strategy 2024-2027AGREED – That the Committee i. Congratulate everyone involved in achieving the national Granicus award in respect of ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.