Corporate Health and Safety Action Plan 2017 - 2019 Progress Report
AgreedScrutiny3 papers
Customers, Performance, Resources and Governance Scrutiny Committee agreed this item on Wednesday 27 September 2017. Below is the council's own wording, with the papers it was decided on.
AGREED – ( i ) T hat the information contained in the report, which detailed the progress to date with implementing the Corporate Health and Safety Action Plan 2017/19 be noted. (ii) That the Customers, Performance, Resources and Governance Scrutiny Committee continue to monitor and support the delivery of the actions. (iii) That the departmental responsibility change for the Health and Safety function be noted. (iv) That the Lead Member consider the concerns of the Committee in respect of the topic areas in the action plan Health and Safety Training and Development and Contractor Control.
Word for word from the decision Wrexham published for this meeting.Source: moderngov.wrexham.gov.uk
Report to Customers, Performance, Resources and Governance Scrutiny Committee
Purpose of the report
To consider a report on progress on implementing the Corporate Health and Safety Action Plan 2017 -2019.
Executive summary
2.1A progress report on the Corporate Health and Safety Action Plan (the plan) is presented to this Committee annually. The last report was on 24 January 2017(HEP/08/17S).
2.2The plan focuses on areas of key health and safety risk to the Council, both corporate and departmental, that have been identified by the Corporate Health and Safety team (CH&S) and the Corporate Health and Safety Steering Group (which has representatives from each department and is chaired by the Head of Environment and Planning).
2.3Risk profiles change and this plan has incorporated emerging risks such as legionella, asbestos and radon as well as noise. These risks were identified as in need of a review on how they are being managed to ensure the Council is compliant with relevant legislation and its duty of care.
2.4The work involved to deliver the plan requires input from CH&S, the Strategic Leadership Team, Heads of Department and managers across the Council. Progress is monitored by the Corporate Health and Safety Steering Group and through regular reports to the Strategic Leadership Team (SLT) and the Senior Management Team (SMT). 2.5 Appendix A contains the 2017/19 plan which was updated on 6 September 2017. This plan has twelve key actions including a specific action (3.1) that “Effective systems are in place to manage the risk of HAVS”.
2.6The status of each action is shown with a colour code. Five actions are off-track, but progressing and are expected to be completed by the target dates. Six actions are on- track/completed and one action is due to commence in January 2018.
2.7All Departments have focussed on creating and implementing departmental H&S Plans, while the CH&S has assisted with this. Heads of Department retain responsibility for ensuring that actions are implemented effectively whilst CH&S provide assurance that this has been carried out.
2.8Whilst there is considerable effort being made in maintaining progress on achieving the outcomes of the plan, there remains a considerable amount of work to be done.
Recommendations
3.1That Members consider the information contained in this report, which details the progress to date with implementing the Corporate Health and Safety Action Plan 2017/19.
3.2The Customers, Performance, Resources and Governance Scrutiny Committee continue to monitor and support the delivery of the actions.
Reasons for recommendations
(i) Assurance that the Customers, Performance, Resources and Governance Scrutiny Committee are satisfied with the progress being made in the delivery of actions contained within the Corporate Health and Safety Action Plan 2017/19.
(ii) Compliance with good practice and our Health and Safety Policy to report health and safety performance.
4. BACKGROUND INFORMATION
4.1The Corporate Health and Safety Action Plan 2017/19 (Appendix A) provides direction for departments and the Corporate H&S team (CH&S) to progress in improving health and safety (H&S) management across the Council. The focus on H&S and how it is managed and implemented across the Council is central to the Council’s purpose.
4.2The plan focuses on the next two years with twelve key areas for action. Some of the actions are linked to previous areas of improvement as they are on-going in the development of a robust, but focused H&S management system.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Customers, Performance, Resources and Governance Scrutiny Committee at Wrexham and we tell you when its next papers are published, before the meeting rather than after it.
ICT and Digital Strategy 2024-2027AGREED – That the Committee i. Congratulate everyone involved in achieving the national Granicus award in respect of ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies