CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Wrexham County Borough Council
Homes and Environment Scrutiny Committee, Thursday 18 February 2021 at 2.30pm

Update on the Pothole Repair Programme

Agreed Scrutiny 1 paper

Homes and Environment Scrutiny Committee agreed this item on Thursday 18 February 2021. Below is the council's own wording, with the papers it was decided on.

Item36

Resolved

AGREED – ( i ) That the Lead Member and Officers be thanked for the report and their work in this programme. (ii) That the Committee consider a further report on this issue outlining: (a) Financial resources available to address this area of work, together with any additional funding, to address the outstanding shortfall to meet the programme of road repairs. (b) Details of lower category roads, related schemes and ... view the full minutes text for item 36.
Word for word from the decision Wrexham published for this meeting. Source: moderngov.wrexham.gov.uk

Follow this further

Built from Wrexham's papers

What the report saysPro

Report to Homes and Environment Scrutiny Committee

Purpose of the report

To provide the Scrutiny Committee with an update on performance of the pothole repair programme, including the impact of Covid-19.

Executive summary

2.1The Council manages 1,140km of carriageways. The roads range from busy major roads (typically A and B class roads) to minor rural lanes and residential streets.

2.2In September 2018 Executive Board approved a renewed Highways Safety Inspection Policy. This policy was based on an all-Wales standard, and a consistent approach to inspection frequency, intervention levels, categorisations and response times.

2.3Percentage of Category 1 defects completed in-line with policy in October 2018 was 22.5%. Percentage of Category 1 defects completed in-line with policy in October 2020 was 83%.

2.4Covid-19 has had an impact on the work of the department (as it has on all departments), as we have faced challenges of workforce being absent due to self- isolation, lack of availability of contractors etc. During this period, we have focussed on ensuring the delivery of critical services in order of priority (eg ensuring residents have had their household waste collected as usual).

2.5In spite of the challenges of 2020, there have been considerable changes within the Environment & Technical Department over the last 6 months, not least the introduction of a new senior management structure to support the Chief Officer to continue the improvement journey of the department. 2.6 The Hi ghways Safety Inspection policy is attached in Appendix A.

Recommendation

3.1That the Committee formulate their conclusions and recommendations based on the information in the report and the discussion at the meeting.

Reasons for recommendation

(i) To ensure that Elected Members are informed about the performance of the pothole repair programme, including the impact of Covid-19.

4. BACKGROUND INFORMATION

4.1The Council manages 1,140km of carriageways. The roads range from busy major roads (typically A and B class roads) to minor rural lanes and residential streets. The network is made up as follows: • 55% are classified roads (A, B and C roads, [623km]) • 60% of the roads are rural [688km] • 26% are residential street (Urban unclassified, [296km])

In April 2018 the total (gross) replacement value of the carriageway asset was estimated at £992 million.

4.2In September 2018 a programme of improvements was planned within the Streetscene service, as an initial phase of a wider programme of improvement within the Environment and Technical Department.

4.3Following a number of years with a difficult budget position in the department, work commenced in November 2018 on a series of initiatives to reduce the forecast budget pressures. Working across the whole service, initiatives included: • Rigorous control and management of agency use (a reduction of 89%) • Recruitment of staff to fill establishment gaps • In year reductions to various service revenue budgets, carefully planned to reduce budgets whilst maintaining critical service areas • Efficiency review of waste and recycling collection service This work resulted in a realigned budget and reduction in pressures from a high point of £1.2m.

4.4Also in September 2018 Executive Board approved a renewed Highways Safety Inspection Policy. This policy was based on an all-Wales standard, and a consistent approach to inspection frequency, intervention levels, categorisations and response times.

4.5The policy approved in 2018 also introduced an updated highways inspection regime. Figure 1 below shows comparative data for inspections and repairs in October 2018, and October 2020. *note the Cat 2 figure is for July 2020, as October figure not yet available due to 90 deadline*

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Update on the Pothole Repair ProgrammeReport 1.2 MB DownloadRead as text

At this meeting

Whole meeting
34Confirmation of MinutesAgreed 35Work ProgrammeAgreed
36Update on the Pothole Repair ProgrammeThis decision

Who was there

12 of 22 attended
BA
Councillor Bryan ApsleyCommittee Member, present
SB
Councillor Sonia Benbow-JonesCommittee Member, present
PB
Councillor Paul BlackwellCommittee Member, present
RA
Councillor R Alun JenkinsCommittee Member, present
MJ
Councillor Marc JonesVice-Chair, present
GL
Councillor Geoff LoweCommittee Member, present
DM
Councillor David MaddocksCommittee Member, expected
MG
Councillor M G MorrisCommittee Member, present
BP
Councillor Beverley Parry-JonesCommittee Member, present as substitute
PH
Councillor Paul H PembertonChair, present
JP
Councillor John PhillipsCommittee Member, present
GR
Councillor Graham RogersCommittee Member, present

All 22 on the meeting page

On this subject at Wrexham

Search all
  1. Update on the Pothole Repair ProgrammeThis decision
  2. Highway Asset Management Plan/Pothole Repair ProgrammeAgreed

More from Wrexham Homes and Environment Scrutiny Committee

All decisions
MeetingDecisionOutcome
15 Jul 2026 Confirmation of MinutesAGREED – That the Minutes of the Meeting held on 17 June 2026 be confirmed as a correct record. Agreed Open
15 Jul 2026 Work ProgrammeAGREED i) That the report in respect of the Hafod Landfill site be considered at the February 2027 meeting. ii) That ... Agreed Open
15 Jul 2026 Review of Allocations Policy - 12-month updateAGREED- i) That Members be provided with details of the number of over 50s that were on the waiting list, that may ha... Agreed Open
17 Jun 2026 Confirmation of MinutesAGREED – That the Minutes of the Meetings held on 22 April and 13 May 2026 be confirmed as a correct record. Agreed Open
17 Jun 2026 Work ProgrammeAGREED i) To note that Public Health Wales were not attending this meeting. ii) That the report in respect of Allocat... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies