Homes and Environment Scrutiny Committee agreed this item on Wednesday 20 July 2022. Below is the council's own wording, with the papers it was decided on.
AGREED – ( i ) That the Lettings report be considered at the October meeting. (ii) That an update report on Storm Christoph be considered at the September meeting. (iii) That subject to the aforementioned amendments, the work programme be agreed.
Word for word from the decision Wrexham published for this meeting.Source: moderngov.wrexham.gov.uk
Report to Homes and Environment Scrutiny Committee
Purpose of the report
To consider the revised work programme of the Homes and Environment Scrutiny Committee attached at Appendix 1.
Executive summary
2.1The proposed work programme up until December 2022, for consideration, is attached at Appendix 1.
2.2Proposed changes to the work programme are highlighted in paragraphs 4.2 and 4.3.
2.3The work programme is broadly aligned to the priorities and key areas of focus in the Council Plan. Council approved the Council Plan (2020-23) following a review of the priorities for the final year of the Plan (2022-23) at the meeting held on 16 March 2022.
Recommendation
3.1That the Committee considers and agrees the proposed work programme attached at Appendix 1.
Reason for recommendation
To enable the Committee to develop a work programme over the next 12 months and beyond 4. BACKGROUND INFORMATION
4.1At its meeting in March 2022 the Committee made the following changes to its work programme.
Climate and Ecological Emergency – Our Decarbonisation Plan
That the Committee continue to receive update reports on a four monthly basis.
Caru Cymru Project
That the Committee receive an update on this issue when considering the report on Behaviour Change at their December 2022 meeting.
4.2Members will recall that a report regarding Lettings was due to be considered at the meeting in June. This report has been delayed and it is proposed that this now be considered at the October meeting.
4.3Members will note that there was to be an update considered at this meeting in respect of the response to Storm Christoph. It is proposed that this be deferred to the September meeting.
4.4The work programme is broadly aligned to the priorities and key areas of focus in the Council Plan. Council approved the Council Plan 2020-23 following a review of the priorities for the final year of the Plan (2022-23) at the meeting held on 16 March 2022. A link to the report is included in the background papers.
4.3The Committee is asked to consider and agree the revised work programme, attached at Appendix 1.
5. IMPLICATIONS 5.1 Policy Framework
The terms of reference of this Committee are aligned to the Council’s Strategic Priorities ‘Improving the Environment’ and “Ensuring Everyone is Safe” as set out in the Council Plan. Any topics identified will contributed to the following aims as stated in the Committees terms of reference “To ensure that we are customer focussed and innovative, soundly organised, resourced and governed, in order to deliver the best possible outcomes for the people of Wrexham.“ To ensure that we support the delivery of homes that meet people’s needs and aspirations in well connected communities. To ensure that we are an environmentally responsible County Borough
5.2Budget - There are no budget implications arising from this report
5.3Legal – There are no legal implications arising from this report
5.4Staffing – There are no staffing issues arising out of the report, but Officer resource will be required to support the preparation of information for Scrutiny Committee consideration 5.5 Equality/Human Rights – This report provides information to inform a work programme and the Equality Manager has confirmed that the programme does not require an equality impact assessment as it merely sets out a timetable.
5.6Risks - The main purpose of Scrutiny is to review and improve Council services, to make recommendations on future policy options and to act as a check and balance on the decisions made. Successful work programming and identification of issues for scrutiny, focusing on outcomes contributing to the relevant Council priorities, should minimize the risk to them not being attained/delivered.
Consultation
6.1The work programme is routinely shared with relevant Lead Members and officers, the Chair of the Audit Committee, Association of Voluntary Organisations Wrexham and Senedd Yr Ifanc.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Homes and Environment Scrutiny Committee at Wrexham and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.