Natural Resources Wales Proposals to Decommission Ground Pumping Stations in the Area of the Lower Dee

Approved Committee 1 paper

Lead Member Delegated Decisions approved this item on Friday 7 October 2022. Below is the council's own wording, with the papers it was decided on.

Item1

Resolved

RESOLVED – ( i ) That the submission of a response to the NRW proposals to decommission the ground pumping stations in the area of the Lower Dee be approved. (ii) That this matter be dealt with as an urgent item of business in accordance with Section 5 (Rule 5.8.10(e)) of the Council’s Constitution. Reasons for decision ( i ) To respond to the NRW’s request for responses to their proposals for the future of the three pumping stations. (ii) The reason for urgency is to enable a response to be submitted to NRW by the deadline of 11 October 2022.
Word for word from the decision Wrexham published for this meeting. Source: moderngov.wrexham.gov.uk

Follow this further

Built from Wrexham's papers

What the report saysPro

Report to Lead Member Delegated Decisions

Purpose of the report

To provide details of a consultation by Natural Resources Wales (NRW) about the future of the Dolennion, Gwern-y-To and Wern-y-Davy pumping stations in Worthenbury.

Executive summary

2.1To detail a proposed response to the NRW correspondence on the future of pumping stations in the Worthenbury area.

Recommendations

3.1To support and approve the submission of a response to the NRW proposals to decommission the ground pumping stations in the area of the Lower Dee.

3.2That approval be given for this item to be dealt with as a matter of urgent business in accordance with Standing Order 43 (1) of the Council’s Standing Orders. REASONS FOR RECOMMENDATIONS

(i) To respond to the NRW’s request for responses to their proposals for the future of the three pumping stations.

(ii) The reason for urgency is to enable a response to be submitted to NRW by the deadline of 11 October 2022.

4. BACKGROUND INFORMATION

4.1NRW have distributed a letter regarding their intentions for the future operation of three ground water pumps in the Worthenbury area of the River Dee flood plain. A copy of the letter can be found at Appendix 1.

4.2Whilst the full implications of NRW’s proposals will require further detailed investigations there are a number of potential risks that the Council need to flag as part of a response to their consultation. These are detailed in Appendix 2.

5. IMPLICATIONS

5.1Policy Framework – N/A

5.2Budget – Impact on this based on the likely increase in reactive flooding response and recovery as a result of pumping stations not being active.

5.3Legal – Possibility of increased Section 19 claims.

5.4Staffing – Unable to deliver regular statutory requirements due to increased flooding events and extended recovery periods.

5.5Equality/Human Rights –

There is a risk that this could have an impact on vulnerable people.

Members are advised of their duty to consider the full Equality Impact Assessment which is available at http://vmwinsqld/equalityisalive/Menu.aspx report number [E&T/EIA00058/2022]. Members of the public can request a copy of the full Equality Impact Assessment from the Contact Officer named in the header box of this report.

A summary of the Equality Impact Assessment is attached as Appendix 3.

5.6Risks -

Damage to property and agricultural land along with highway infrastructure.

Risk of emergency services not being able to respond to incidents from Bangor on Dee, Worthenbury and surrounding areas. Full understanding of the extent of risk still needs to be investigated to understand the impact the decommissioning of the pumps will have.

Consultation

6.1Scope of consultation should include Lead Member for Environment & Technical and Local Member, along with affected flood wardens.

BACKGROUND PAPERS LOCATION WEBSITE INFO

N/A N/A N/A 08 September 2022

Dear [Landowner / Resident / Business]

Dolennion, Gwern-y-To and Wern-y-Davy Pumping Stations, Worthenbury Natural Resources Wales (NRW) manage three land drainage pumping stations at Worthenbury Meadows:- Dolennion, Gwern-y-To and Wern-y-Davy. These pumping stations have aimed to improve the quality and /or reliability of agricultural land for landowners by artificially draining excess water built up in drainage ditches and allowing water to reach natural watercourses quicker. The pumps are unable to stop flooding but they are helping to remove the flood water from the land quicker than would be the case naturally.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Natural Resources Wales Proposals to Decommission Ground Pumping Stations in the Area of the Lower DeeReport 1.5 MB DownloadRead as text

At this meeting

Whole meeting
1Natural Resources Wales Proposals to Decommission Ground Pumping Stations in the Area of the Lower DeeThis decision

On this subject at Wrexham

Search all
  1. Natural Resources Wales Proposals to Decommission Ground Pumping Stations in the Area of the Lower DeeThis decision
  2. Natural Resources Wales Flood Risk Management Plan ConsultationApproved
  3. Welsh Government Consultation Document - Taking Forward Wales' Sustainable Management of Natural ResourcesApproved

More from Wrexham Lead Member Delegated Decisions

All decisions
MeetingDecisionOutcome
12 Feb 2026 Attendance at Royal Garden Parties 2026(i) That the outgoing Mayor, Councillor Tina Mannering and the outgoing Mayoress , [name removed], along with one of ... Decided Open
8 Sep 2025 Consultation Response - Learner Travel Operational GuidanceRESOLVED - (i) To support and approve the submission of a response (Appendix 1) to the Welsh Government consultation ... Approved Open
7 Aug 2025 New Rent Service Charge Standard for Wales ReportRESOLVED (i) That the submission of the attached response to WG who are seeking views on proposals to strengthen the ... Approved Open
20 Jun 2025 Welsh Government Consultation - Homelessness and Social Housing Allocations BillRESOLVED- (i) That the draft response to Welsh Government (WG), who are seeking views of stakeholders regarding the p... Approved Open
18 Jun 2025 Time scales for Social Housing Landlords to Respond to Reports of Hazards which have Significant Health ImpactsRESOLVED- (i) That the draft response to Welsh Government (WG) who are seeking views on proposed changes to ensure so... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies