CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Wrexham County Borough Council
Lifelong Learning Scrutiny Committee, Thursday 20 April 2023 at 3.00pm

Education Estate - Capital Investment

Agreed Scrutiny 5 papers

Lifelong Learning Scrutiny Committee agreed this item on Thursday 20 April 2023. Below is the council's own wording, with the papers it was decided on.

Item36

Resolved

It was agreed to circulate a more detailed breakdown of the funding to Members of the Committee. · The pandemic, rising materials and labour costs had impacted on some existing projects resulting in variations in project costs. · Noted that all new projects will have a requirement to be Net Zero Carbon. · Schools and colleges under the new rules would also be required to demonstrate a 20% reduction on the amount of embodied carbon. As an example, wifi networks being turned off in schools at night which could save 150 tonnes of carbon over 7 years. · Noted that the Education Service’s bid for Welsh medium Capital – Welsh Government Grant had been successful. · Suggested that the workshop for Members of the Committee with information on the categorisation of Condition B secondary schools via their individual components be held on site at Ysgol Llan y Pwll . · The level of capacity in schools was being monitored. Information which included the number on roll as well as the current calculated capacity was sent to WG. More detail was provided in relation to the capacity of special provision. · Request for update in relation to the Welsh Medium education White Paper which aimed to increase the provision of education through the medium of Welsh. Noted that some English medium schools were already transitioning to provide some of the curriculum in Welsh. The LA had set a target in the WESP for number of pupils to be educated through the medium of Welsh but there were currently issues in being able to recruit Welsh speaking teachers. Response to White Paper to be submitted middle of June. · Planning Section 106 agreements in respect of developer contribution to schools. It was important to ensure that these were pursued and were set at an appropriate level. · The impact of pupils attending schools out of county or out of the local area. Officers confirmed that this information was tracked at the end of year and shared with schools and the admissions forum. AGREED – ( i ) That the Committee thank the Lead Member and Officers for the report and acknowledge the progress made in delivering the Sustainable Communities for Learning Programme . (ii) That the next annual update be scheduled for 12 months’ time and include a more detailed breakdown of the funding and expenditure ... view the full minutes text for item 36.
Word for word from the decision Wrexham published for this meeting. Source: moderngov.wrexham.gov.uk

Follow this further

Built from Wrexham's papers

What the report saysPro

Report to Lifelong Learning Scrutiny Committee

Purpose of the report

1.1The committee last considered the Education Estate – Capital Investment projects 12 months ago. This report highlights further progress against our programme and more up to date data available on condition and capacities of schools.

1.2In February 2022 the previous report (COEEI/03/22s) was submitted to the Lifelong Learning Scrutiny Committee which outlined details of the current position of capital schemes in relation to Band B of 21st Century Schools programme. The 21st Century Schools programme has since been renamed as the Sustainable Communities for Learning Programme (SCLP) by Welsh Government.

1.3At this meeting Members resolved:

(i) That the Lead Member and Officers be thanked for the detailed information in the report and the significant contribution made by Welsh Government (WG) to Wrexham Schools. (ii) That the committee receive an annual update report detailing the following:-  Progress on Band B programme.  Results of condition surveys, work completed during the period and school movement between category.  Feedback on school framework review.  Utilisation of MIMS funding  Breakdown of categorisation of Band B secondary schools, via their individual components, if possible.

(iii) That the above report to be scheduled based on the availability of the information requested above. (iv) That a Member Workshop be held early in the new Council outlining the details of priority ranking for school maintenance.

Executive summary

Progress of Band B Schemes

2.1During the last 12 months, Covid and increasing costs have continued to provide a considerable challenge to all aspects of work related to the delivery of significant projects. There is however, progress to report:

2.2At Borras, the project at the existing school’s Key Stage 2 site has been completed on time and within budget. It opened fully to all primary pupils in July 2022.

2.3The new Welsh medium school, Ysgol Llan Y Pwll is progressing well, with the main school now complete and occupied by pupils in the Nursery and Reception classes.

2.4At Ysgol y Hafod in Johnstown, significant progress has been made but there is a slight delay to accommodate changes to the kitchen design. The project was the first to encounter the impact of building cost inflation post pandemic. We will be reporting an overspend on this project, the reasons for which are highlighted in the body of this report.

Forward Work

2.5The following table outlines the status and projected completion dates for the remaining Band B schemes:

Band B Projects Projected Current Status Projected Completion Date Costs St Mary’ Brymbo £7,080,000 Business Case to September 2025 be submitted A site has been identified and we are working with the developer to secure early access for site investigation and pre-planning works (subject to planning permission and land transfer) St Mary’s RC £7,080,000 Business Case to Planning permission for Nine be submitted Acres was refused and no current alternative site has been identified New Provision £2,000,000 Business Case to By March 2026 be submitted (subject to planning permission)

Page 2 Specialist Provision £25,050,569 Business Case to By March 2026 be submitted (subject to planning permission)

2.6A successful outline bid has been agreed by Welsh Government to fully fund an extension to Ysgol Hooson which will support the LA in achieving the targets outlined in the Welsh in Education Strategic Plan (WESP). The extension will provide permanent spaces for learning to replace temporary accommodation and will temporarily house wraparound child care.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix 1Appendix 1 87 KB Download
PDF
Appendix 2Appendix 2 451 KB Download
PDF
Appendix 3Appendix 3 698 KB Download
PDF
Appendix 4Appendix 4 9 KB Download
PDF
Education Estate: Capital InvestmentReport 378 KB DownloadRead as text

At this meeting

Whole meeting
33Confirmation of MinutesAgreed 35Work ProgrammeAgreed
36Education Estate - Capital InvestmentThis decision

Who was there

10 of 16 attended
YC
Y Cynghorydd Beryl BlackmoreCommittee Member, apologies
YC
Y Cynghorydd Dana DaviesCommittee Member, present
YC
Y Cynghorydd Carrie HarperChair, present
YC
Y Cynghorydd Frank HemmingsCommittee Member, apologies
YC
Y Cynghorydd Peter HowellCommittee Member, present
YC
Y Cynghorydd Corin JarvisCommittee Member, present
YC
Y Cynghorydd Stella MatthewsVice-Chair, present
YC
Y Cynghorydd Becca MartinCommittee Member, present
YC
Y Cynghorydd Ross ShepherdCommittee Member, present
YC
Y Cynghorydd Alison TynanCommittee Member, present
YC
Y Cynghorydd Robert Ian WilliamsCommittee Member, present
BM
Mr Brendan McDonald - Cynrychiolydd yr EglwysChurch Representative, present

All 16 on the meeting page

On this subject at Wrexham

Search all
  1. Education Estate - Capital InvestmentThis decision
  2. Education Estate - Capital InvestmentAgreed
  3. Education Estate - Capital InvestmentAgreed
  4. Education Estate - Capital InvestmentAgreed
  5. Proposed Purchase of Land – Education EstateApproved

More from Wrexham Lifelong Learning Scrutiny Committee

All decisions
MeetingDecisionOutcome
15 Jul 2026 Confirmation of MinutesAGREED – That the Minutes of the Meeting held on 24 June 2026 be signed as a correct record. Agreed Open
15 Jul 2026 Work ProgrammeAGREED – That, subject to the aforementioned, the work programme be agreed. Agreed Open
15 Jul 2026 Education Estate - Capital InvestmentAGREED – ( i ) That future reports include numbers in each category to help with transparency. (ii) That a future inf... Agreed Open
15 Jul 2026 Schools, Education & Early Intervention Budget UpdateAGREED – ( i ) That information reports on licensed deficit be regularly highlighted to the Executive Board on an ong... Agreed Open
24 Jun 2026 Appointment of ChairAGREED – That Councillor Frank Hemmings be appointed Chair of the Lifelong Learning Scrutiny Committee for the coming... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies