AGREED: (i) To thank the Lead Member and Officers for the report. (ii) That, based on the revenue budget information presented at Q1, no specific budget pressures to be referred onto other Scrutiny Committees at this early stage (it was acknowledged that the Lifelong Learning Scrutiny Committee were already monitoring the area of school transport).
Word for word from the decision Wrexham published for this meeting.Source: moderngov.wrexham.gov.uk
Report to Customers, Performance, Resources and Governance Scrutiny Committee
Purpose of the report
1.1To present the Council’s 2025/26 current budgetary position for the first quarter of the 2025/26 financial year, including the Housing Revenue Account (HRA).
Executive summary
2.1The Council’s net revenue budget for 2025/26 is £345,144,954. The net revenue budget of £345,148,220 was agreed by Council on 19 February 2025 (COFI/06/25), however, following the Local Government Final Settlement there was a funding adjustment of £3,266.
2.2This Revenue Budget update report is the first quarterly report for the financial year 2025/26. The report forecasts the year-end position and is underpinned by assumptions and estimates, taking account of actual expenditure to the end of May. Therefore, this is an early forecast and allows time for assumptions underpinning projections to be revised as a result of the initial forecast, early in the year, if necessary.
Recommendation
3.1That Members consider the Q1 Budget Monitoring Report as reported to Executive Board on 8 July 2025 and formulate their conclusions and recommendations based on the information in this report and the discussion at the meeting. REASON FOR RECOMMENDATIONS
To ensure robust budget monitoring arrangements for the financial year and that action is taken to address the budget pressures forecast.
4 BACKGROUND INFORMATION 4.1 The current budgetary position is a gross projected budget pressure of £2.8m (it is worth noting that at the same point last year a pressure of £4m was forecast) and this is summarised in Appendix 1 of the Executive Board report, with more detail shown within Appendix 2 of the report. This is an early forecast position derived from the extrapolation of both current and historic data, along with some contingency built in where appropriate. The forecast pressure is within the scope of a reasonable variance that could be managed within normal operating parameters. In light of this, this report does not make any proposals about specific service mitigations, although all Chief Officers are aware of the position and of the need to manage within their cash limited budgets. Appendix 3 provides progress against savings proposals agreed for 2025/26. It is encouraging that at this early stage 54% are in either green or yellow. Appendix 4 details the projected outturn position for the HRA.
5 IMPLICATIONS 5.1 Policy Framework – Part 2, section 28 of the Local Government Act 2003 requires the Council to monitor its budget.
5.2Budget – The Council’s net revenue budget for 2025/26 is £345,144,954. The net revenue budget of £345,148,220 was agreed by Council on 19 February 2025 (COFI/06/25), however, following the Local Government Final Settlement there was a funding adjustment of £3,266.
5.3Legal – Any legal implications would be dealt within the body of the report.
5.4Staffing – Any staffing implications are included in the report. 5.5 Impact Assessment – This report does not present a proposal for decision and no Impact Assessment is required.
5.6Carbon Impact Assessment - This report does not present a proposal for decision and no Carbon Impact Assessment is required. 5.7 Risks – Risks identified during the budget process are managed through the regular reporting and close in-year scrutiny of service budgets. 6 CONSULTATION
6.1All Chief Officers have contributed to the information contained in this report through the agreed budget monitoring process and lead members have been informed. Budget reports and individual service areas have been examined by various scrutiny committees throughout the year. BACKGROUND PAPERS LOCATION WEBSITE INFO.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Customers, Performance, Resources and Governance Scrutiny Committee at Wrexham and we tell you when its next papers are published, before the meeting rather than after it.
ICT and Digital Strategy 2024-2027AGREED – That the Committee i. Congratulate everyone involved in achieving the national Granicus award in respect of ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.