AI summaryWrexham's CPRG scrutiny committee thanked officers and agreed a recommendation to the Chief Officer on the Change Programme, which has delivered £6.6m of savings over three years.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedAgreed a recommendation to the Chief Officer (wording truncated)
Money£6.6m total savingsAcross three financial years
What happens nextComplete resource reviewFinalise internal programme arrangements
Who it affectsAll council departmentsFive programme themes underway

What was decided

The committee thanked Lead Members and Officers for the report and information provided at the meeting.

The committee agreed to recommend to the Chief Officer; the full wording is not given in the supplied papers.

Why

The committee was asked to consider the update and use it to formulate recommendations. Report 3.1, P12

The report set out progress on the Change Programme since 2024, including a refocus in May 2025 around five transformation themes. Report P1, 2.1, 2.5, 4.5

What happens next

Complete the review of resource arrangements for the Change Programme. Report 4.28

Continue using external partners such as Local Partnerships to support delivery and provide specialist input.

Relevant scrutiny committees may request specific items related to the Change Programme as the work progresses. Report P54

The money

  • £4.7m Savings from 49 approved Change Programme proposals across 2024-25 and 2025-26 Report 2.3, 4.3
  • £6.6m Total budget savings delivered through Change Programme projects and proposals across three financial years Report 5.2
  • £1.9m Cost of the Change Programme in 2024/25, including £1.4m in VR/EVR costs Report 5.2
  • £198k Cost of the Change Programme in 2025/26 Report 5.2
  • £1.5m Saving from a 0.5% efficiency target and inflation adjustments applied to the 2026/27 budget Report 4.22
  • £429k Income maximisation contribution to the 2026/27 budget Report 4.22
  • £11.8m Forecast budget gap in 2027/28 per the MTFP approved in February 2026 Report 4.6, P20
  • £11.5m Forecast budget gap in 2028/29 per the MTFP Report 4.6, P20
  • £12.0m Forecast budget gap in 2029/30 per the MTFP Report 4.6, P20

Implications

  • Financial: Total budget savings of £6.6m have been delivered through Change Programme projects and proposals over three financial years. Report 5.2
  • Financial: Programme cost to date is £1.9m in 2024/25 (including £1.4m VR/EVR) and £198k in 2025/26. Report 5.2
  • Financial: MTFP shows forecast budget gaps of £11.8m (2027/28), £11.5m (2028/29) and £12.0m (2029/30). Report 4.6, P20
  • Staffing: Voluntary Redundancy and Voluntary Early Retirement formed part of the approved savings; further engagement with the workforce is planned. Report 4.3, 5.4
  • Legal: There is a legal requirement for the Council to set a balanced budget. Report 5.3
  • Equalities: High-level Integrated Impact Assessments have been completed for each Programme theme, with detailed IIAs to follow for specific projects. Report 5.5, P51
  • Climate: Decarbonisation and Climate Change is one of the five programme themes, supporting the Council's net zero 2030 commitment. Report P26, P169
  • Risk: The programme risk profile is described as strong, with an improving risk position and mitigations increasingly embedded. Report 5.6, P53

Who and where

  • Council workforce, including non-office-based and depot staff Report 4.18, P132
  • Elected members, who attended All Member Workshops between Autumn 2025 and Spring 2026 Report 4.13, P132
  • Service users, residents and unpaid carers across all wards Report P133, P184, P261
  • Partner agencies, including Local Partnerships and Smart Cities partners Report P132, P273

Timeline

  • December 2023: Change and Efficiency Board established Report 2.2
  • April 2024: Executive Board established the comprehensive Change Programme Report 2.1, 4.1
  • December 2024: Welsh Government grant settlement notified; review of the Change Programme began Report 2.4
  • May 2025: Executive Board agreed the Transformation Vision, guiding principles and five programme themes Report 2.5, 4.5
  • May 2025: Decision that Change and Efficiency Board would join LMSLT, meeting on alternating months Report 2.8
  • Summer and Autumn 2025: Both Programme Leads departed; the programme was incorporated into the PIPS service Report 2.9
  • Late December 2025: Interim Head of Service took up post for the programme Report 2.9
  • December 2025: Change and Efficiency Board reconvened, focusing on Social Care, Education and Environment Report 2.10
  • Autumn 2025 to Spring 2026: All Member Workshops held on each programme theme Report 4.13
  • February 2026: MTFP approved, showing forecast budget gaps to 2029/30 Report 4.6, P20
  • 2026-04-23: CPRG Scrutiny Committee considered the Change Programme update

Plain English for the jargon

  • MTFP: Medium Term Financial Plan, the council's forward-looking budget planning document.
  • LMSLT: The council's Senior Leadership Team arrangement, under which the Change and Efficiency Board now sits on alternating months.
  • PIPS: Performance, Improvement and Partnerships service, into which the Change Programme was incorporated.
  • VR/EVR: Voluntary Redundancy and Voluntary Early Retirement, used as part of the savings programme.
  • IIA: Integrated Impact Assessment, used to assess equalities, Welsh language, climate and other duties.
  • RAYG: Red, Amber, Yellow, Green status ratings used for projects on the programme.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item47

Resolved

AGREED - i. To thank Lead Members and Officers for the report and the information provided at the meeting. ii. To recommend to the Chief Officer ... view the full minutes text for item 47.
Word for word from the decision Wrexham published for this meeting. Source: moderngov.wrexham.gov.uk

Follow this further

Built from Wrexham's papers

What the report saysPro

Report to Customers, Performance, Resources and Governance Scrutiny Committee

Purpose of the report

To provide an update to the Customers, Performance, Resources and Governance Committee on the Council’s Change Programme arrangements, and to update the Committee on the progress made by the Change Programme since our last report.

Executive summary

2.1A decision of the Executive Board in April 2024 established a comprehensive Change Programme to address the forecast budget gap, with a core programme team of officers, supported by a wider team of officers and project managers to lead change within their service areas and provide technical advice when needed.

2.2A Change and Efficiency Board was established in December 2023 to provide a co-ordinated overview of the transformational change the Council will require in meeting budgetary challenges and providing an additional level of assurance to the sustainability, setting and delivery of the Council’s future service structure, budget and the Council Plan.

2.3As a result of the Change Programme, operating through the governance structure of the Change & Efficiency Board, the Executive Board approved 49 proposals, projected to save approximately £4.7m across the 2024-25 and 2025-26 financial years, and based on prioritisation and business case assessments. The proposals were not sub-categorised between different types of saving. The details of the savings that were agreed are shown as Appendix 1 (In-year Savings 2024/25) and Appendix 2 (Budget Savings 2025/26). 2.4 Following notification of Welsh Government grant settlement in December 2024, there was a period of review around the Change Programme in order to ensure that it was able to focus on long-term transformation change, as well as deliver the necessary financial benefits in the short-term.

2.5This review resulted in an Executive Board (May 2025) decision to support an overarching Transformation Vision for Wrexham Council, and a number of ‘key principles’ which applied to all programmes and projects within the Change programme; this would ensure that all programmes and projects across all parts of the organisation work in the same way, and have a clear direction-of-travel for the Council.

2.6Since the identification of this Vision, Principles, and Programme Themes, work continued to identify key areas of transformation, as well as specific projects which support the long-term vision and delivery of benefits in the short, medium and long-term.

2.7In addition, the Programme identified key areas of growing budget pressure / demand where additional resources were required in order to reduce or control the growing pressure in the immediate term and identify key opportunities for improvement moving forward. Initially this approach was applied within adults’ social care and children’s social care, with other areas identified in due course.

2.8In May 2025 the decision was taken for Change & Efficiency Board to become part of LMSLT, meeting on alternating months to focus on Change.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Change ProgrammeReport 805 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 22 attended
BA
Councillor Bryan ApsleyCommittee Member, expected
WB
Councillor William BaldwinCommittee Member, present
BB
Councillor Beryl BlackmoreCommittee Member, expected
FH
Councillor Frank HemmingsCommittee Member, present
PH
Councillor Pete HowellChair, present
CJ
Councillor Corin JarvisVice-Chair, present
CL
Councillor Claire LovettCommittee Member, expected
TM
Councillor Tina ManneringCommittee Member, apologies
SM
Councillor Stella MatthewsCommittee Member, apologies
MM
Councillor Michael MorrisCommittee Member, present
JN
Councillor Jeremy NewtonCommittee Member, present
AW
Councillor Anthony WedlakeCommittee Member, present

All 22 on the meeting page

On this subject at Wrexham

Search all
  1. Change ProgrammeThis decision
  2. Change Programme - Advancing Business Cases for Opportunities with External PartnersAgreed
  3. Change programme – Review of progress and defining the Next PhaseNoted
  4. Change ProgrammeAgreed
  5. Change ProgrammeAgreed
  6. Change ProgrammeAgreed

More from Wrexham Customers, Performance, Resources and Governance Scrutiny Committee

All decisions
MeetingDecisionOutcome
3 Sep 2026 Confirmation of MinutesAGREED – That the Minutes of the Meetings held on 5 and 25 June 2026 be confirmed and signed as a correct record. Agreed Open
3 Sep 2026 Work ProgrammeAGREED – That the work programme be agreed subject to the aforementioned amendmens. Agreed Open
3 Sep 2026 ICT and Digital Strategy 2024-2027AGREED – That the Committee i. Congratulate everyone involved in achieving the national Granicus award in respect of ... Agreed Open
25 Jun 2026 Confirmation of MinutesAGREED – That the minutes of the meeting held on 14 May 2026 be confirmed and signed as a correct record. Agreed Open
25 Jun 2026 Work ProgrammeAGREED – That the work programme be agreed subject to the above amendments. Agreed Open