CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Wrexham County Borough Council
Governance and Audit Committee, Thursday 16 July 2026 at 10.30am

Audit Wales Performance Audit Plan 2026-27'

Noted Finance 1 paper

AI summaryWrexham's Governance and Audit Committee noted the Audit Wales Performance Audit Plan 2026-27, which sets out three local reviews while a full plan awaits certification of the 2024-25 accounts.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedCommittee noted the performance audit plan for information
MoneyNot stated
What happens nextReviews by end of June 2027Performance audit work to be substantially completed by end of June 2027
Who it affectsCouncil audit programmeSets out three local review projects and delivery timescales

What was decided

The Committee noted the Audit Wales Performance Audit Plan 2026-27, a paper presented for information only. Report P5

Why

A full Audit Plan covering both financial and performance work cannot yet be issued because the Council's 2024-25 accounts remain uncertified due to a historical capital reserves issue. Report P5, P6, P7

Audit Wales expects the 2024-25 accounts to be certified over the summer of 2026, but wishes to confirm the proposed performance audit programme in the meantime. Report P6, P8

What happens next

Audit Wales will work with Council officers to agree exact timescales for each project, with progress reported through the work programme timetable and a mid-year update. Report P15

Audit Wales aims to substantially complete the planned performance audit work by the end of June 2027, and aspires to issue a full Audit Plan to the Committee early in the financial year from 2027-28 onwards. Report P15, P17

Options considered

  • Rejected: Issue full combined financial and performance Audit Plan for 2026-27 now. Not possible until 2024-25 accounts are certified Report P7
  • Chosen: Proceed with performance audit programme only and communicate timescales separately. Performance audit work continues while accounts certification is completed Report P8, P15

Implications

  • Governance: The Committee does not yet have a full Audit Plan combining financial and performance work for the year. Report P7
  • Risk: Outstanding certification of the 2024-25 accounts, linked to a historical capital reserves issue, continues to delay the full plan. Report P6
  • Other: Three local review topics have been set out: counter fraud arrangements, Transformation and Change Board value for money, and effectiveness of a sample project. Report P12, P13, P14

Who and where

  • Wrexham County Borough Council officers, who will work with Audit Wales on project timescales Report P15
  • The Governance and Audit Committee, which will receive a mid-year update and the next full plan from 2027-28 Report P15, P17

Timeline

  • 10 June 2026: Letter from Audit Wales setting out the proposed performance audit programme Report P3
  • Summer 2026: Expected certification of the Council's 2024-25 accounts Report P6
  • End of June 2027: Target for substantial completion of the 2026-27 performance audit work Report P15
  • From 2027-28 onwards: Audit Wales aspires to issue the full Audit Plan early in the financial year Report P17

Plain English for the jargon

  • Performance Audit Programme: Audit Wales reviews of whether the Council has proper arrangements, delivers value for money and achieves intended outcomes, separate from the financial accounts audit.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item17

Resolved

- That the Audit Wales Performance Audit Plan 2026-27 be noted.
Word for word from the decision Wrexham published for this meeting. Source: moderngov.wrexham.gov.uk

Follow this further

Built from Wrexham's papers

What the report saysPro

Report to Governance and Audit Committee

1 Cwr y Ddinas / 1 Capital Quarter Caerdydd / Cardiff CF10 4BZ Alwyn Jones Tel / Ffôn: 029 2032 0500 Fax / Ffacs: 029 2032 0600 Chief Executive Textphone / Ffôn testun: 029 2032 0660 The Guildhall [email removed] / [email removed] www.audit.wales / www.archwilio.cymru Wrexham

LL11 1AY

Date issued: 10 June 2026

Dear Alwyn,

Performance Audit Programme for 2026-27 You will be aware that in the normal course of events, Audit Wales would have issued Wrexham County Borough Council’s Audit Plan for 2026-27 by now.

However, while work is progressing at pace to audit outstanding sets of accounts as a result of a historical capital reserves issue, the Council’s 2024-25 accounts have not yet been certified. Our expectation is that this will be completed over the summer of 2026.

We are therefore not yet in a position to issue a final Audit Plan for this year covering both our financial and performance audit work, incorporating our plans and risk- assessment for our audit of the 2025-26 accounts.

In the meantime, our performance audit work programme continues, and I need to inform you of our proposed programme of work for the 2026-27 financial year. I set out below details and timings for delivery of planned outputs from this work:

Page 1 of 2

Please contact us in Welsh or English / cysylltwch â ni’n Gymraeg neu’n Saesneg. Exhibit 1: Planned outputs

Description Scope

Local project work – Following up on the Auditor General’s report ‘Raising counter fraud our Game’ Tackling Fraud in Wales as a basis for the arrangements Council having proper arrangements to prevent and detect fraud

Local project work – A review of the Council’s arrangements for managing Transformation and the impact of its projects and assessing value for Change Board money.

Local project work – A review of whether a project achieved the outcomes Effectiveness of it was intended to deliver against its defined Project Outcomes objectives. Sample project is to be confirmed

Timing of Performance Audit Work My team will work with officers in the Council to arrange exact timescales for the individual projects and will be communicated regularly through our work programme and timetable and subsequent mid-year update. My auditors aim to substantially complete the performance audit work set out in this plan by the end of June 2027.

I hope that you find this update of some use, and please contact me if you would like to discuss any of the above in more detail.

Looking ahead, our aspiration is that we will be able to issue our full Audit Plan to the Governance and Audit Committee early in the financial year from 2027-28 onwards, which will represent a significant step forward.

Yours sincerely,

Gareth Lucey

Audit Director

Page 2 of 2

Please contact us in Welsh or English / Cysylltwch â ni’n Gymraeg neu’n Saesneg.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Audit Wales Performance Audit Plan 2026-27'Report 358 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 12 attended
WB
Councillor William BaldwinCommittee Member, present, as expected, virtual
TB
Councillor Trevor BatesCommittee Member, present, as expected, virtual
BB
Councillor Beryl BlackmoreCommittee Member, apologies
AD
Councillor Annette DaviesCommittee Member, absent
DD
Councillor Dana DaviesCommittee Member, apologies
CJ
Councillor Corin JarvisCommittee Member, present, as expected, virtual
PR
Councillor Paul RobertsCommittee Member, present
PR
Councillor Paul RogersVice-Chair, present
CB
Claire Blanchard - Independent Lay MemberCo-Optee, present
CE
Carys Edwards - Independent Lay MemberChair, present
CH
Colin Hopwood - Independent Lay MemberCo-Optee, present
JJ
John Jarvis - Independent Lay MemberCo-Optee, present

On this subject at Wrexham

Search all
  1. Audit Wales Performance Audit Plan 2026-27'This decision
  2. Audit Wales Annual Audit Plan 2024-25Noted
  3. Audit Wales Work Programme and Timetable - Wrexham Council - 31 December 2025Noted
  4. Audit Wales: Arrangements for Commissioning ServicesNoted
  5. Audit Wales Work Programme and Timetable - Quarterly update 31 March 2025Noted
  6. Audit Wales - Wrexham Performance Audit Plan 2024 LetterDecided

More from Wrexham Governance and Audit Committee

All decisions
MeetingDecisionOutcome
16 Jul 2026 Confirmation of MinutesRESOLVED – That the Minutes of the meeting held on 18 June 2026 be signed as a correct record. Decided Open
16 Jul 2026 Terms of ReferenceRESOLVED – That the Governance and Audit Committee Terms of Reference be noted. Noted Open
16 Jul 2026 External Regulation & Inspection - Assurance re:implementation of recommendations- That members of GAC noted the progress made with the implementation of actins in response to the external regulatio... Noted Open
16 Jul 2026 Audit Wales Annual Audit Plan 2024-25- That the Audit Wales Annual Audit Plan 2024-25 be noted. Noted Open
16 Jul 2026 Governance and Audit Development Programme- That the Governance and Audit Development Programme be noted. Noted Open