AI summaryWrexham Executive Board approved the Local Development Plan Delivery Agreement for submission to Welsh Government, who must approve it by 30 September 2026. The new LDP will cover 2026-2041 and aims for adoption within 4 years.
Written from the decision and the officer reportPDF Pro
OutcomeAgreed
MoneyNo additional costs
What happens nextWelsh Government approval
Who it affectsLocal Development Plan 2026-2041
What was decided
The Executive Board approved the Wrexham Local Development Plan Delivery Agreement for submission to Welsh Government for their approval
The matter was dealt with as an urgent item of business in accordance with Section 5 (Rule 5.8.10 (m)) of the Council's Constitution
Why
To enable the Council to meet the requirements of the Planning and Compulsory Purchase Act 2004 Report P3, 5.3
To meet Welsh Government's requirement to submit a new Delivery Agreement to them by 30 September 2026, following their direction in March 2026 that the previous Local Development Plan be withdrawn Report P3
The Delivery Agreement includes the timetable for the LDP preparation together with a Community Involvement Scheme identifying who, how and when stakeholders will be involved
What happens next
Submit the Delivery Agreement to Welsh Government by 30 September 2026 Report 4.11
Welsh Government has 4 weeks to respond. If approved, preparation of the LDP commences in line with the timings and stages set out in the Delivery Agreement Report P20, 4.11
The money
Up to £500,000 Evidence Base (estimated additional cost of £225,000 on top of the £272,423 spent on LDP2, though this can be shared with the Strategic Development Plan) Report P26, P27
c. £220,000 Examination in Public (PEDW and Programme Officer) Report P28
c. £31,500 Database and Digital Mapping Report P28
c. £110,250 Translation and Printing Report P29, P30
£25,000 Examination Expert Witness Report P30
c. £652,000 Additional Staff Costs over 4 years of plan preparation Report P30
Options considered
Chosen: Approve the Delivery Agreement for submission to Welsh Government. The Delivery Agreement meets statutory requirements, has been consulted on with stakeholders, and enables the Council to meet Welsh Government's deadline of 30 September 2026 Report 6.1, 6.2, 5.3
Implications
Financial: No additional costs arise as the Council has previously committed funds in a specific reserve to undertake LDP preparation. Similar arrangements will be made for staffing, evidence base and associated revenue costs Report 5.2, P26
Legal: The Delivery Agreement accords with statutory requirements. Submission by the deadline demonstrates the Council's commitment to deliver an LDP in accordance with statutory duties Report 5.3
Policy: The LDP will help achieve Council Plan Priorities including Developing the Economy, Ensuring Wrexham is a Fair and Safe Place, Improving Education and Learning, and Promoting Good Health and Wellbeing Report 5.1, P24
Risk: The Delivery Agreement contains a Risk Assessment of 18 issues that could impact on delivery, including changes in Welsh Government policy, changes in evidence, challenges aligning with the emerging Strategic Development Plan, resources, political support and legal challenge Report 4.4, 4.5, 5.5
Equalities: The Council's Integrated Impact Assessment considers Well-being of Future Generations Act, Equality Act 2010, Welsh Language Measure 2011, and other requirements. The Impact Assessment will evolve as the LDP is developed Report 5.4, P33
Who and where
Specific consultation bodies including Wrexham Community Councils, adjoining community councils, adjoining local planning authorities, Natural Resources Wales, Local Health Board, Network Rail, utilities and statutory undertakers Report 6.1, P37
General consultation bodies including local voluntary bodies, racial and ethnic bodies, religious bodies, business bodies, disabled interest bodies, and Welsh cultural bodies Report P38
Welsh Government's Plans Branch, Planning Directorate, who have already indicated they are happy with the timetable
The Council's Planning Policy Team, which is currently small and needs appropriate resourcing
Timeline
May - September 2026: Stage 1: Delivery Agreement and Community Involvement Scheme Report P7
End of October 2026: Submission to Welsh Government and Welsh Government approval Report P8
November 2026 - August 2027: Stage 2: Pre-Deposit (Issues and Options) preparation and involvement Report P9
August 2027 - April 2028: Stage 3: Pre-Deposit Public Consultation on Preferred Strategy Report P10, P11
April 2028 - May 2029: Stage 4: Deposit Plan preparation and public consultation Report P12
June - October 2029: Stage 5: Submission to Welsh Government and Planning and Environment Decisions Wales Report P13
February - March 2030: Stage 6: Examination in Public Report P14
September 2030: Stage 7: Publish Inspector's Report Report P15
October 2030: Stage 8: Adoption Report P16
Annually following adoption: Stage 9: Annual Monitoring Report and Review Report P17
Plain English for the jargon
LDP: Local Development Plan - a statutory planning document setting out how land will be used and developed
Delivery Agreement: Document setting out the timetable for LDP preparation and the Community Involvement Scheme
Community Involvement Scheme (CIS): Policies identifying who, how and when stakeholders will be engaged in the LDP process
Strategic Development Plan (SDP): A higher-tier plan covering North Wales that the LDP must align with
PEDW: Planning and Environment Decisions Wales - the body that conducts LDP examinations
HRA: Habitats Regulations Assessment - assessment of impact on protected habitats
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item8
Resolved
RESOLVED – That the Executive Board continue to demonstrate their full support for Wrexham's bid to become UK City of Culture 2029. Reasons for Decision ( i ) Full support from Members is required in order to demonstrate to DCMS that there is unity for the bid across WCBC. This is particularly important as the winning city will have gone through an election process prior to 2029 and DCMS are keen to know that any change in the administration will not lead to a change of heart. (ii) DCMS monitor the level of digital engagement in relation to the bid, and Member support in encouraging residents to participate will be vital to success in the bidding process.
Word for word from the decision Wrexham published for this meeting.Source: moderngov.wrexham.gov.uk
2.1The Wrecsam2029 UK City of Culture 2029 bid was submitted on Thursday 6th August 2026. This was intentionally submitted 4 days in advance of the 10 th August deadline. The bid document was supported by a UK City of Culture promotional video to strengthen the bid and evidence that Wrexham is ready to deliver for 2029. The film can be viewed via this YouTube link and within the background papers section of the report.
The content of the Culture Bid remains strictly confidential in order to protect Wrexham’s position in what is a highly competitive process and to prevent competing bids from gaining access to our proposals. Members have received, and will continue to receive, verbal updates on the development of the bid. These updates are also confidential and should not be shared externally.
2.2Wrexham Community & Culture Trust (WCCT) was established to lead on Wrexham’s bid for UK City of Culture 2029. The bid was submitted by the Trust with support from WCBC. 2.3 9 places from across the UK, including Wrexham, have been longlisted to win the title:
2.4This equates to 7 applications from England, 1 from Wales and 1 from Scotland. The competition has been running since 2013, with previous winners all coming from England and Northern Ireland. Scotland and Wales have never previously won the title.
2.5The announcement of the final shortlist (likely to be 4 places) will be made in October 2026. The exact date has not yet been announced. If Wrexham reaches the shortlist, the Expert Advisory Panel will visit the county during November/December 2026, and a contingent of 4 will visit Department for Culture, Media & Sport (DCMS) offices in London for a further in-depth analysis of the bid.
The announcement of the final winner will be made in January 2027.
Bidding Timeline: Expression of Interest Submission – 8th February 2026 Longlist of 9 Places Announced – 18th March 2026 Longlisted Places Submit Full Application – 10th August 2026 Shortlisted Places Announced – Autumn 2026 Panel Visit to Shortlisted Places – Autumn 2026 Final Presentation – Autumn 2026 Winner Announced – December 2026 or early January 2027 UK City of Culture winner’s delivery year – January – December 2029
2.6Monthly member workshops have been and continue to be held to keep members informed and engaged throughout the bidding process, these include updates on the development and content of the bid.
2.7Three workshops have been held to date. These sessions have provided an opportunity for detailed discussion and exploration of the Wrecsam2029 vision, including what the programme could look like and the activities and opportunities it could deliver. The most recent workshop highlighted the 15 main events that were submitted as part of the bidding process which gave members an appreciation of the scale of the events and delivery that will happen if successful for 2029, attracting 2 million plus visitors across our county.
2.8Prior to submission of the full written application , the Trust commissioned an independent cultural consultant to review the content against the DCMS guidelines. The 37 submitted questions were each scored out of 10, with an overall score of 365 out of a possible 370. This represents an excellent result, and we are therefore hopeful that the submission will progress to the shortlisting stage.
Recommendation
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Health and Safety Policy 2026-2028RESOLVED – That the updated set out in report COFI/25/26 be approved. Reason for Decision To meet the requirements of...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.