Resolved 1. To Recommend to the Executive Board that post project reviews for significant projects should continue to be carried out and reported to the Executive Board once projects are contractually complete; 2. That the Committee reaffirms it is satisfied with the present arrangements for the scrutiny of capital project management.
Word for word from the decision Wychavon published for this meeting.Source: mgov.wychavon.gov.uk
Report to Overview and Scrutiny Committee, 3 pages
Summary
1.1The Overview and Scrutiny Committee is invited to review the suggestions contained in the report and identify a way forward.
Recommendations
2.1That the Overview and Scrutiny Committee recommends to the Executive Board that post project reviews for significant projects should continue to be carried out and reported to the Executive Board once projects are contractually complete.
2.2That the Overview and Scrutiny Committee reaffirm that they are satisfied with the present arrangements for the scrutiny of capital project management.
3. Implications & Impact
3.1Council Priorities and Community Plan Themes
3.1.1. Good project management arrangements will contribute to the Council’s Priority to be “an excellently run Council”.
3.2Resource Implications
3.2.1. None arising directly from the report although good project management arrangements will directly address the Council’s Corporate Risk of “failure to deliver major capital projects as promised.”
Background
4.1At the last meeting of the Overview and Scrutiny Committee there was some discussion about the potential scrutiny of decision making in respect of possible capital projects and performance in delivery of approved capital projects. It was agreed that a report would be submitted to this meeting regarding the options available in order that any work can be properly specified and programmed. 4.2 It was acknowledged that scrutiny of specific projects should only be carried out after the completion of that project. Otherwise officers who should be involved in project delivery may be distracted to support the scrutiny process. There could also be contractual difficulties in scrutinising a project whilst it is still under way. It is however considered beneficial for post project reviews to continue to be carried out following the completion of each major project. The Overview and Scrutiny Committee may want to consider formalising this practice by making the appropriate recommendation to the Executive Board. All significant projects (by value or otherwise) could be reviewed with the aim of identifying key learning points.
4.3Such a review took place in May 2004 with a report to the Executive Board by the Development Manager on the key learning issues following the completion of the Pershore Leisure Centre project. This report outlined the background to the project and whilst the completed building was good, the project was over budget and completed late. Key learning points related to design team appointment, the design process, selection of the main contractor, the form of contract, clerk of works and the level of contingencies.
4.4These learning points were carried forward into subsequent projects such as the Waitrose Supermarket and the new Pershore Hospital and Health Centre project. The post project report for the Waitrose project has not yet been prepared owing to a 12 month defects liability period and a few minor issues relating to access arrangements and landscaping are unresolved. Consequently the Council is holding a retention fee to safeguard its position. A full report will be presented to the Executive Board once all the outstanding issues have been resolved and final payment made. Similarly, a post project report will be made on the Hospital project in due course. Furthermore, given recent interest, it is hoped that a post project report will be submitted to the September meetings of the Executive Board and Overview and Scrutiny Committee in relation to the Pershore Skatepark scheme.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.