Project Managers Highlight Report Number 1

Decided Committee 1 paper

South Worcestershire Shared Services Partnership Joint Committee decided this item on Monday 14 January 2008. Below is the council's own wording, with the papers it was decided on.

Item30

Resolved

Resolved That the Project Managers Highlight report be received That a current project plan summary with key dates be reported to each Joint Committee meeting
Word for word from the decision Wychavon published for this meeting. Source: mgov.wychavon.gov.uk

Follow this further

Built from Wychavon's papers

What the report saysPro

Report to South Worcestershire Shared Services Partnership Joint Committee, 5 pages

Revenue & Benefits Shared Services Project

Highlight Report 001 th Date 12 December 2007 Period Covered November/December Author Martyn Dymott Version FV

1. Purpose

To inform the project board and the Joint Committee of progress of this project and the stage status.

Deliberations by the project board and additional information since the project board are shown in bold.

2. Schedule Status

2.1The project manager joined the team 3rd December and has begun to install the PRINCE based project structure and reporting processes. Work has started on identifying all of the project products (deliverables) to enable the production of; a project plan, a Project Initiation Document and a communication plan for the project boards’ consideration and endorsement at the January 2008 meeting.

2.2The following early documents have been produced and are attached as pre reading for the project boards’ attention and discussion at the meeting.

o A Project Structure – for endorsement o An initial Product Breakdown Structure – for information only o A project activity plan for the pilot stage – for information only

The project structure was amended by the project board and agreed.

2.3Although a project plan has not yet been written, the project has already started with the initial stage involving the transfer of a number of Revenue and Benefits teams for the pilot exercise. The project teams’ efforts are currently focused on ensuring that the transfer of staff from the three sites successfully happens during week commencing 7th January 2008.

As at 3rd January 2008 – Wychavon and Malvern Hills pilot teams will transfer on Wednesday 9th January and Worcester teams on Thursday 17th January. – MD.

File: E:\moderngov\data\published\Intranet\C00000640\M00002328\AI00010944\Highlight140108J CVERSIONamended0.doc Date saved: 04 Jan. 08 Revenue & Benefits Shared Services Project

At the meeting the project manager will update the board on progress against the pilot activity plan but the numbers planned to move to the new location are:

Malvern Worcester Wychavon Total NDR 1 2 1 4 Recovery 3 4 6 13 Billing 4 3 4 11 8 9 11 28

All staff have had 1-2-1 meetings with their managers to discuss the overall project and how it will impact on them and giving them the opportunity to raise any concerns. As part of these meetings the pilot selection process was discussed and staff were invited to indicate their willingness to join in the pilot. The pilot was actually over subscribed and it was decided after careful consideration not to include the visiting officers and Inspectors who volunteered as their immediate relocation would not have contributed to the pilot.

Fraud teams (2 from Malvern and 2 from Wychavon) were considered, but their inclusion would impact upon the space available to the other teams. Additionally Fraud teams have some specialist storage requirements which would have further reduced the space available for the pilot.

A letter from the Head of Service has been sent to all staff notifying them of the intention to give them a minimum of 6 months notice for their relocation.

The project board agreed that the transfer of R&B teams to the new location should be the priority albeit it is recognized that this may require some workaround solutions for IT as we head towards convergence to a single system. Nick stressed that getting the teams together in one location was his priority in order to start developing a single SSO culture. Martyn stated that he would revisit the current project plan. It was agreed that the aim is to have all staff that will be located in Pershore, moved by the end of 2008. This will require some careful planning regarding the logistics and timings of moves.

3. Budget Status

The reporting process is currently under discussion.

File: E:\moderngov\data\published\Intranet\C00000640\M00002328\AI00010944\Highlight140108J CVERSIONamended0.doc Date saved: 04 Jan. 08 Revenue & Benefits Shared Services Project

4. Products Completed

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Project Managers Highlight Report Number 1Report 5 pages DownloadRead as text

At this meeting

Whole meeting
28Minutes of the previous meetingApproved
30Project Managers Highlight Report Number 1This decision
31Financial Performance MonitoringNoted

On this subject at Wychavon

Search all
  1. Project Managers Highlight Report Number 1This decision
  2. Project Managers Highlight Report Number 2Noted

More from Wychavon South Worcestershire Shared Services Partnership Joint Committee

All decisions
MeetingDecisionOutcome
11 Apr 2011 Minutes of the previous meetingResolved That the Minutes of the meeting of the Joint Committee held on Monday 24 January 2011 be approved as a corre... Approved Open
11 Apr 2011 Annual External Audit Plan 2010/11Resolved That the Audit Approach Memorandum for 2010/11 be approved. Approved Open
11 Apr 2011 DWP Performance LetterResolved That the letter from the Department of Works and Pensions be noted. Noted Open
11 Apr 2011 Performance MonitoringResolved 1. That the service performance of the Revenues and Benefits Shared Service Organisation be noted, and that ... Noted Open
11 Apr 2011 Update ReportResolved 1. That the achievement of Customer Service Excellence accreditation be noted. 2. That the progress of devel... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies