Resolved (1) That the owner of the premises be given until 30 September 2008 to submit an appropriate valid planning application, but if this is not done then enforcement action be commenced as detailed in (2) and (3) below. (2) That the Head of Legal and Support Services be authorised in consultation with the Head of Planning to serve an enforcement notice pursuant to section 172 of the Town and Country Planning Act 1990 (as amended) upon the owner(s) and or occupier(s) of the land requiring the step(s) below to be taken within the period(s) specified; and (3) That the Head of Legal and Support Services be authorised to commence and pursue a prosecution pursuant to Section 179 of the Town and Country Planning Act 1990 (as amended) against the owner(s) and / or occupier(s) of the land in the event that the enforcement notice is not complied with. Requirements of Notice To permanently remove the marquee. Compliance Period One month. Reasons for the Service of the Notice 1. It appears to the Council that the breach has occurred within the last 4 years. 2. The erection of a marquee in this location is considered to be detrimental to visual amenities of the area and adversely affects the open setting of the surrounding environment. The size, scale and design of the development is not in keeping with the Cotswold Area of Outstanding Natural Beauty and locality and as such, the development is considered to be contrary to policy QE3 of the Regional Spatial Strategy, policies CTC1, CTC3, CTC4, CTC19 of the Worcestershire County Structure Plan and policies GD1, GD2, ENV1, ENV2, ENV3, ENV5, ENV10 of the Wychavon District Local Plan 2006.
Word for word from the decision Wychavon published for this meeting.Source: mgov.wychavon.gov.uk
1.1This Enforcement report advises Members of the ongoing investigating relating to the erection of a marquee at Woollas Hall, Eckington.
1.2This report seeks authorisation to pursue formal Enforcement action in relation to the operations identified herein.
Recommendations
2.1The Head of Legal and Support Services be authorised in consultation with the Head of Planning to issue an enforcement notice pursuant to section 172 of the Town and Country Planning Act 1990 (as amended) requiring the step(s) below to be taken within the period(s) specified; and
2.2The Head of Legal and Support Services be authorised to commence and pursue a prosecution pursuant to Section 179 of the Town and Country Planning Act 1990 (as amended) against the owner(s) and / or occupier(s) of the land in the event that the enforcement notice is not complied with.
Requirements of Notice
1. To remove the marquee and return the land to its former condition.
Compliance Period
One month.
Reasons for the Service of the Notice
1. It appears to the Council that the breach has occurred within the last 4 years.
2. The erection of a marquee in this location is considered to be detrimental to visual amenities of the area and adversely affects the open setting of the surrounding environment. The size, scale and design of the development is not in keeping with the Cotswold Area of Outstanding Natural Beauty and locality and as such, the development is considered to be contrary to policy QE3 of the Regional Spatial Strategy, policies CTC1, CTC3, CTC4, CTC19 of the Worcestershire County Structure Plan and policies GD1, GD2, ENV1, ENV2, ENV3, ENV5, ENV10 of the Wychavon District Local Plan 2006.
3. Implications & Impact
3.1Council Priorities and Community Plan Themes
The control of unauthorised development or changes of use should contribute to the Council’s priority 2 - Greener: a better environment for today and tomorrow.
3.2Resource Implications
(a) Financial Implications: None
(b) Staff Implications: Officer time will be required.
(c) Risks: None.
(d) Legal: Officer time will be required.
(e) Property: None.
Background
4.1On the 11th June 2008 a complaint was received by your officers in relation to the erection of a marquee at Woollas Hall. The complainant has alleged a marquee was erected on the 1st May 2008 and is being used in connection with commercial wedding functions at the site.
4.2Members may recall that the marquee was discussed last year during a Development Control Committee meeting on 23rd August 2007. It was considered that the siting of the marquee for a temporary period may have been acceptable subject to the imposition of relevant conditions limiting the use and restricting it to a temporary period throughout any one year, whilst a more suitable permanent proposal that would meet the owner’s requirements could be sought. As a consequence of this, Members agreed at the time that an application should be sought within 2 months from the Committee date to retain the marquee, although this was never submitted. Instead, an application to extend the existing building was submitted, which was later refused on design grounds. Following this refusal the marquee was removed from the site, which resolved the outstanding breach.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Planning Application Ref W/11/00298/PN.Resolved Conditionally approved:- Z001 The development hereby permitted shall be begun no later than the expiration o...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.