Planning application Ref W/09/01585/PN - The development consists of the construction of a series of floodwalls and flood embankments to the south of the Defford Road, Pershore, in order to protect 61 properties and a severn trent pumping s
ApprovedPlanning1 paper
Development Control Committee approved this item on Thursday 20 August 2009. Below is the council's own wording, with the papers it was decided on.
Resolved Conditionally approved, subject to (a) no substantive objections being received to the submitted surface water management plan within the public consultation period, and (b) any other conditions deemed necessary in respect of surface water management:- T002 The development hereby permitted shall be begun before the expiration of three years from the date of this permission. Reason: In accordance with the requirements of Section 91 (1) of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004. A004 Samples of the external facing bricks to be used in the construction of the wall, shall be subject to the approval, in writing, of the Local Planning Authority before any work on the site commences and the scheme shall subsequently be implemented in accordance with the approved details. Reason: To ensure that the development is visually satisfactory. LS01 No part of the development shall be commenced until full details of soft landscaping works have been submitted to and approved in writing by the Local Planning Authority. The details submitted must include: i) a plan(s) showing details of all existing trees and hedges on the application site. The plan should include, for each tree/hedge, the accurate position, canopy spread and species, together with an indication of any proposals for felling/pruning and any proposed changes in ground level, or other works to be carried out, within the canopy spread. ii) a plan(s) showing the layout of proposed tree, hedge and shrub planting and grass areas. iii) ... view the full minutes text for item 71.
Word for word from the decision Wychavon published for this meeting.Source: mgov.wychavon.gov.uk
Major Application Description: The development consists of the construction of a series of floodwalls and flood embankments to the south of the Defford Road, Pershore, in order to protect 61 properties and a severn trent pumping station from flooding to 1 in 100 year standard of protection.
Site: Land Rear of, Defford Road, Pershore
Applicant: Environment Agency
Agent:
Date Valid: 10/07/2009 Case Heather Pearson Officer: Expiry Date: 08/10/2009 Tel: 01386 565325 Member(s): Cllr C G J Tucker Cllr J T Grantham
1. Site Description and Details of Proposal
The proposal is to erect a flood defence barrier to protect properties in Pershore. It consists of a combination of flood walls and embankments. The scheme includes:-
- provision of embankments/bund to the south of the town as close as possible to the Defford Road to minimise any loss of floodplain storage; and - flood walls provided through the existing allotments to minimise ground uptake; and - construction of two new surface water pumping stations; and - flood proofing of the Toll House on Bridge Street. - a new driveway is proposed for No.82 Bridge Street to tie in with the flood wall.
The applicants state that these measures will provide protection of a 1 in 100 year standard to 61 properties along the Defford Road and the Severn Trent Water Sewage pumping station. In addition it will reduce the risk of sewage flooding to other properties in Pershore during times of flood.
The flood bund will be constructed parallel to Defford Road and will be approximately 2.5m high and stretch 410m in length. Its base will be 25 - 30m wide. It will be set back approximately 2m from an existing bank and hedgerow which will be retained to screen the new bund.
A wall will be constructed along the boundary of the Severn Trent site, again the hedgerow is to be kept to provide screening. The wall will be 1.8m high and 65m long at this section and constructed from concrete blocks with brick facing on both sides.
A new pumping station will be constructed within the Severn Trent site. This will be used during times of flooding to over-pump surface and groundwater seepage back into the flood plain.
The bund will then continue a further 300m around the southern boundary of the pumping station and behind the nursery. This will be 1.09m high with an access track along the top for maintenance. The footprint will be approximately 15m wide.
A flood wall will be constructed through the allotments at approximately 0.9m high and 400m in length. The two existing tracks will be raised to ramp up and over the wall with a 1 in 10 gradient for vehicle access. There will be a new 3m wide access track on the landward side of the wall along the section to the rear of the Nogains properties. This will be used for maintenance and emergency vehicles.
A second pumping station is proposed within the driveway at Nogains. This will be underground and not visible in the landscape. It will be used to collect surface water and drain it to the east, discharging into the Avon upstream of Bridge Street.
At the Bridge Street end of the site a bund will be constructed to tie into a raised driveway to No.82. This is approximately 1.3m high and 70m long with an access track along the top. A flood wall will run along Bridge Street to tie in with the Toll House (a Listed Building). It is proposed to apply 1.2m of waterproof render to the Toll House, this will be subject to a separate listed building application.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Planning application Ref W/09/01585/PN: The development consists of the construction of a series of floodwalls and flood embankments to the south of the Defford Road, Pershore, in order to protect 61 properties and a severn trent pumping station from flooding to 1 in 100 year standard of protectionReport
71Planning application Ref W/09/01585/PN - The development consists of the construction of a series of floodwalls and flood embankments to the south of the Defford Road, Pershore, in order to protect 61 properties and a severn trent pumping sThis decision
Planning application Ref W/09/01585/PN - The development consists of the construction of a series of floodwalls and flood embankments to the south of the Defford Road, Pershore, in order to protect 61 properties and a severn trent pumping sThis decision
Planning Application Ref W/11/00298/PN.Resolved Conditionally approved:- Z001 The development hereby permitted shall be begun no later than the expiration o...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.