2008/09 Final Accounts: Auditor's Final Accounts Memorandum

Decided Committee 2 papers

South Worcestershire Shared Services Partnership Joint Committee decided this item on Monday 21 September 2009. Below is the council's own wording, with the papers it was decided on.

Item59

Resolved

Resolved That the Final Accounts Report be accepted.
Word for word from the decision Wychavon published for this meeting. Source: mgov.wychavon.gov.uk

Follow this further

Built from Wychavon's papers

What the report saysPro

Report to South Worcestershire Shared Services Partnership Joint Committee, 7 pages

Appendices

A ISAUK 260 requirements

© 2009 Grant Thornton UK LLP. All rights reserved final accounts report 2008-09 1

1 Key findings

1.1Status of audit We have performed our final accounts audit in accordance with the Audit Commission’s Code of Audit Practice and applicable auditing standards and our audit is substantially complete.

1.2Matters identified at the planning stage In the conduct of our audit, we have not had to alter or change our Audit Plan. Specifically, the priorities identified when planning our audit, which were dealt with satisfactorily through the course of our audit, were:

• the Joint Committee’s arrangements for the preparation of its financial statements; • internal audit, to determine the extent of reliance we can place on it for the purposes of our audit; • the internal control framework for key financial systems; • the materiality of balances and transactions impacting on the financial statements; and • the key risks relevant to the preparation and audit of the financial statements. • We can confirm that all issues were dealt with satisfactorily through the course of our audit, and there are no matters we wish to bring to the Committee's attention.

1.3Accounting system and internal control We have undertaken sufficient work on the key financial controls for the purpose of designing our programme of work for the statement of accounts audit. Our evaluation of the key financial control systems did not identify any control issues presenting a material risk to the accuracy of the statement of accounts. We produced an interim report of our findings, which was shared with management early in the audit process.

Internal Audit We have reviewed the work of Internal Audit and concluded that the scope and conduct of the testing was appropriate for us to rely on to understand the key financial systems of the Joint Committee. We have therefore taken assurance from the work of Internal Audit to support our responsibilities in documenting and understanding material systems used to prepare the Statement of Accounts.

IT Controls As part of our role as external auditors and to support the accounts work Grant Thornton undertake, we undertook a high level post implementation review of the Academy Project to assess whether or not:

• Manual processes - Interim procedures were in place to ensure the security of any hardcopy data during the period of implementation that the Councils experienced 'downtime'; and - Data entry integrity checking processes for the input of data after the downtime were in place.

© 2009 Grant Thornton UK LLP. All rights reserved final accounts report 2008-09 2

• User Access - The adequacy of the data security parameters; - The adequacy of the existing user access request/delete and modification processes; and - Restriction are in place to control powerful privilege sets to the operating system and database. • Data Migration - Test procedures were adequately documented.

Overall the Academy Project was well managed with a dedicated Project Manager in post and good use made of the recognised project management methodology, Projects In a Controlled Environment 2, 'PRINCE2'. This ensured good documentation was maintained and key project processes, such as use of project plans, were utilised.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Grant Thornton final accounts reportReport 7 pages DownloadRead as text
PDF
Report to Joint Committee 210909 Final AccountsReport 1 pages Download

At this meeting

Whole meeting

On this subject at Wychavon

Search all
  1. 2008/09 Final Accounts: Auditor's Final Accounts MemorandumThis decision
  2. 2020/21 Final Accounts: Statement of Accounts and Audit Results Report for 2020/21Approved
  3. 2019/20 Final Accounts: Statement of Accounts and Audit Results Report for 2019/20Approved
  4. 2018/19 Final Accounts: Statement of Accounts and Audit Results reportApproved
  5. 2017/18 Final Accounts: Statement of Accounts and Audit Results ReportNoted
  6. 2016/17 Final Accounts: Statement of Accounts and Audit Results ReportApproved

More from Wychavon South Worcestershire Shared Services Partnership Joint Committee

All decisions
MeetingDecisionOutcome
11 Apr 2011 Minutes of the previous meetingResolved That the Minutes of the meeting of the Joint Committee held on Monday 24 January 2011 be approved as a corre... Approved Open
11 Apr 2011 Annual External Audit Plan 2010/11Resolved That the Audit Approach Memorandum for 2010/11 be approved. Approved Open
11 Apr 2011 DWP Performance LetterResolved That the letter from the Department of Works and Pensions be noted. Noted Open
11 Apr 2011 Performance MonitoringResolved 1. That the service performance of the Revenues and Benefits Shared Service Organisation be noted, and that ... Noted Open
11 Apr 2011 Update ReportResolved 1. That the achievement of Customer Service Excellence accreditation be noted. 2. That the progress of devel... Noted Open