Update on the Procurement of Single Application Software for the South Worcestershire Building Control Partnership

Decided Committee 2 papers

South Worcestershire Shared Services Partnership Joint Committee decided this item on Monday 27 September 2010. Below is the council's own wording, with the papers it was decided on.

Item130

Resolved

Resolved 1. That the Business Case attached to the report be endorsed and the purchase of the MIS Headway IT system be recommended. 2. That the costs of acquiring and implementing the MIS IT system (as detailed in the Business Case) be met from the projected service budget underspend in 2010/11.
Word for word from the decision Wychavon published for this meeting. Source: mgov.wychavon.gov.uk

Follow this further

Built from Wychavon's papers

What the report saysPro

Report to South Worcestershire Shared Services Partnership Joint Committee, 10 pages

Business Case for Procurement

Project Name: Procurement of a single application software package for SWBC Partnership

Date: September 2010

Version: Final

M alvern Hills D istrict Council Procurement SWBCITBusinesscase0.docinsert project name Date:

Project Details Project name SWBC Single application system Status Draft * Status Types: Draft, Final, Outline, Other (please specify)

Author REZA SANEIE/Building Control Partnership Manager Owner SOUTH WORCESTERSHIRE BUILDING CONTROL PARTNERSHIP Client SOUTH WORCESTERSHIRE BUILDING CONTROL PARTNERSHIP

Document History Version Date of Author Reason for Changes Summary of Changes Distribution Issue

1.0002.07.2010 Reza FIRST DRAFT GARY Saneie WILLIAMS,ANDY BALDWIN, BEN BROWN, MAC, DAVE SMITH,LORETTA 2.00 27.07.2010 Reza Mac & Andy’s comments SECOND DRAFT Gary Williams, Andy Saneie Baldwin, Ben Brown 3.00 08.09.2010 Reza Final Report Gary Williams, Gill Saneie Collins, John Wrightson, Andy Baldwin, Ben Brown

Approvals Name Signature Title Date of Approval Version

Purpose To consider procurement of a single application software for South Worcestershire Building Control Partnership to replace the existing three system arrangement. The business case is to detail the cost of implementation and maintenance of the single system against the risks and anticipated business benefits and savings gained.

Contents This Business Case contains the following topics:

Topic See Page Background & reasons to procure 3 Drawbacks 4 Benefits expected 5 Option appraisal 6 Cost 6 Preferred option 7 Integration with other systems 7 Proposal/recommendations 8 Timescales and resourcing 8 Risk management 9 Appendix A 10

Page 2 of 10 Version: Procurement SWBCITBusinesscase0.docinsert project name Date:

Background & South Worcestershire Building Control (SWBC) Partnership commenced operation in reasons to April 2009 as a result of a merger between the Building Control Services of the procure districts of Malvern Hills, Wychavon and Worcester City.

The initial business case recommended continuing, to use the existing back office systems operated by the three Building Control Services. It was considered that migration to a single system at the start of the Partnership would have been a major piece of work which potentially could have had a negative impact on the shared service implementation and service delivery. This meant that the decision to adopt a single system was postponed until the Partnership had been implemented and the Partnership Manager was in place.

As part of the future strategic plan for the Partnership, the implementation of a single application system has been identified as a priority action, which is considered essential to enable the future aspirations of the partnership for service development and enhancement. There is a strong case to move to a single IT system and replace the existing inefficient and labour intensive arrangements.

The main drivers behind this case are:

1. To improve service delivery to customers 2. To reduce cost by stream lining processes, increasing capacity and reducing duplication 3. Introduce innovative and smart working practices e.g. Electronic submission of applications, mobile working, hot desking 4. Remove the need for team members to learn three separate systems and increase use of the system by all team members and potentially the Worcestershire hub. 5. Allow the partnership to expand and take on additional partner councils, whilst maintaining efficient operating practices.

The three existing systems are as follows:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
SWBC IT BusinesscaseReport 10 pages DownloadRead as text
PDF
Update on the Procurement of Single Application Software for the South Worcestershire Building Control PartnershipReport 2 pages Download

At this meeting

Whole meeting

On this subject at Wychavon

Search all
  1. Update on the Procurement of Single Application Software for the South Worcestershire Building Control PartnershipThis decision
  2. Update on the Procurement of Single Application Software for the South Worcestershire Building Control PartnershipNoted

More from Wychavon South Worcestershire Shared Services Partnership Joint Committee

All decisions
MeetingDecisionOutcome
11 Apr 2011 Minutes of the previous meetingResolved That the Minutes of the meeting of the Joint Committee held on Monday 24 January 2011 be approved as a corre... Approved Open
11 Apr 2011 Annual External Audit Plan 2010/11Resolved That the Audit Approach Memorandum for 2010/11 be approved. Approved Open
11 Apr 2011 DWP Performance LetterResolved That the letter from the Department of Works and Pensions be noted. Noted Open
11 Apr 2011 Performance MonitoringResolved 1. That the service performance of the Revenues and Benefits Shared Service Organisation be noted, and that ... Noted Open
11 Apr 2011 Update ReportResolved 1. That the achievement of Customer Service Excellence accreditation be noted. 2. That the progress of devel... Noted Open